Deedo IDDL-RAT-KARVANCHIWADI5 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects8
Registrations8
Completion still due26 past their date
Median extension8 months50% of registrations extended
Regulatory cases0none on MahaRERA's lists
10 in 10 registrations run late here
8 MahaRERA registrations in Karvanchiwadi
2 extended, not yet due6 past even the latest date
Extended registrations moved their completion date by a median of 8 months.
Projects in Karvanchiwadi
8 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Shree Krishna HeightsGajanan Builders and Developers | Due Apr 2027, extended 4 mo | — | 13% |
| Anand ParkSD Associates | Due Sep 2028, extended 4 mo | — | 29% |
| Gajanan HeightsAshokkumar Narsinga Parihar | 10 mo late | — | 93% |
| Mahalakshmi ResidencyPushpendra Real Construction Private Limited | 1 yr 7 mo late | — | 50% |
| Tara Residency phase -IIMestry Housing And Infrastructure | 2 yrs 1 mo late | — | 25% |
| Tara ResidencyPrashant Rajaram Mestry | 4 yrs 10 mo late | — | 27% |
| NandadeepM R Group | 2 yrs 2 mo late | — | 2% |
| Shri Swami Samarth MauliShree Swami Samarth Enterprises | 7 yrs 7 mo late | — | 78% |
Nearby: other localities in Ratnagiri
Most active promoters
- Ashokkumar Narsinga Parihar1 project
- Gajanan Builders and Developers1 project
- Mestry Housing And Infrastructure1 project
- M R Group1 project
- Prashant Rajaram Mestry1 project
- Pushpendra Real Construction Private Limited1 project
- SD Associates1 project
- Shree Swami Samarth Enterprises1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology