Malgund, Ratnagiri
Deedo IDDL-RAT-MALGUND10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects3
Registrations3
Completion still due12 past their date
Median extension4 months33% of registrations extended
Regulatory cases1on 1 project
10 in 10 registrations run late here
3 MahaRERA registrations in Malgund
1 extended, not yet due2 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Malgund
3 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Swami Prasad ApartmentMauli Developers | 1 yr 11 mo late | — | 9% |
| Keshav BaugVinod Keshav Joshi | 1 yr 11 mo late | — | — |
| Sea VistaChaitanya Developers | Due Apr 2039, extended 4 mo | — | 73% |
Nearby: other villages in Ratnagiri
Most active promoters
- Chaitanya Developers1 project
- Mauli Developers1 project
- Vinod Keshav Joshi1 project
Malgund, in questions
How many projects in Malgund run late?
10 in 10 MahaRERA registrations (3 of 3): their completion date was extended or has passed, data through 22 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Malgund by Deedo. Medians on fewer than 3 deeds are not shown.
Data through22 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology