RERA projects in Padavewadi

9 projects under 9 MahaRERA registrations, registered 2017–2025. 44% have a completion date extended beyond the one promised.

Locality
9RERA projects
9Registrations
4Completion still due5 past their completion date
8 monthsMedian extension beyond promised date44% of registrations extended
0Regulatory casesnone on MahaRERA's lists
11Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20171
20181
20192
20200
20211
20222
20230
20240
20252

Projects in Padavewadi

9 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Brahmachaitanya SrushtiManisha Rajaram SarfareP5280007998811 Apr 202531 Dec 202830 Apr 2029Extended 4 mo0
Nakoda PrimeKohinoor RealtorsP528000794376 Mar 202531 Dec 202830 Apr 2029Extended 4 mo0
Guru SagarJk UnisonP5280003328515 Feb 202230 Dec 202429 Dec 2025Extended 12 mo0
Amrut DhamGajanan ConstructionP528000329342 Feb 202231 Dec 202631 Dec 2026Not yet due0
Arihant PrimeArihant Dream Homes Pvt LtdP5280003027815 Aug 202131 Dec 202631 Dec 2026Not yet due0
Arihant ShivamArihant Vastu Nirman Pvt. LtdP5280002061726 Apr 201930 Dec 202530 Dec 2025Promised date passed0
Shivalaya HeightsShivraj ConstructionP5280001928615 Jan 201930 Dec 202330 Dec 2023Promised date passed0
Girija ResidencySandip Balchandra SawantP5280001762029 Aug 201828 Nov 202128 Nov 2021Promised date passed0
Sharv ParadiseAshok Pawar & SonsP528000127637 Sep 201730 Jun 202130 Nov 2022Extended 17 mo0

Other localities in Ratnagiri

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Arihant Dream Homes Pvt Ltd1 project
  2. Arihant Vastu Nirman Pvt. Ltd1 project
  3. Ashok Pawar & Sons1 project
  4. Gajanan Construction1 project
  5. Jk Unison1 project
  6. Kohinoor Realtors1 project
  7. Manisha Rajaram Sarfare1 project
  8. Sandip Balchandra Sawant1 project
  9. Shivraj Construction1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology