Mandangad, Ratnagiri
4 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects15
Registrations15
Completion still due47 past their date
Median extension4 months36% of registrations extended
Regulatory cases0none on MahaRERA's lists
7 in 10 registrations run late here
15 MahaRERA registrations in Mandangad and the places within it
1 not yet due3 extended, not yet due7 past even the latest date4 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Mandangad
15 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Vrundhavan ComplexNagesh Narayan Ambekar | Due Dec 2030 | — | — |
| Shree Swami Samarth ResidencyShankar Iranna Jangam | Due Apr 2030, extended 4 mo | — | — |
| Chipolkar ComplexSarfaraz Yunus Chipolkar | 10 mo late | — | 25% |
| Ratna ResidencyDinesh Tulaju Rathod | Due Apr 2027, extended 4 mo | — | 7% |
| Ashokvardhan ResidencyShankar Iranna Jangam | 1 yr 10 mo late | — | 25% |
| City PrideMahammad Salim Sayyad | Due Apr 2029, extended 4 mo | — | 0% |
| Shri Samarth CharanAnil Anant Ghartkar | 2 yrs 10 mo late | — | 0% |
| Hill View ApartmentAnant Pandurang Ghosalkar | 4 yrs 4 mo late | — | 0% |
| Golden PlazaIqbal Umar Mukadam | 1 yr 10 mo late | — | 35% |
| Kings VillageJasvinder Pal Singh | 6 yrs 11 mo late | — | — |
| Srushti ComplexAakar Developers | 3 yrs 3 mo late | — | 4% |
| Asiya Heritage | No date on record | — | — |
| Samar Residency - Wing A | No date on record | — | — |
| Sayyad Complex | No date on record | — | — |
| Shigwan Complex | No date on record | — | — |
Nearby: other talukas in Ratnagiri
Most active promoters
- Shankar Iranna Jangam2 projects
- Aakar Developers1 project
- Anant Pandurang Ghosalkar1 project
- Anil Anant Ghartkar1 project
- Dinesh Tulaju Rathod1 project
- Iqbal Umar Mukadam1 project
- Jasvinder Pal Singh1 project
- Mahammad Salim Sayyad1 project
- Nagesh Narayan Ambekar1 project
- Sarfaraz Yunus Chipolkar1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology