Guhagar, Ratnagiri

Deedo IDDL-RAT-GUHAGAR

4 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects70
Registrations77some projects hold several
Completion still due2146 past their date
Median extension4 months36% of registrations extended
Regulatory cases1on 1 project
Guhagar market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

8 in 10 registrations run late here

77 MahaRERA registrations in Guhagar and the places within it

4 not yet due17 extended, not yet due46 past even the latest date10 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Guhagar

70 projects registered with MahaRERA in this taluka and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Samarth Sai Prasad Apartment-4 Building No 2Sai Prasad Builders & DevelopersDue Mar 2031, extended 4 mo——
Konkan Bliss ResidencesVaishali Vikrant VaidyaDue Apr 2029, extended 4 mo——
Golden HeightsQaisar Qasim ChunawalaDue Apr 2030, extended 4 mo——
Mango Lakefront Paradise GuhagarSamir Shrinivas KaleDue Jun 2035, extended 4 mo—0%
Shree Mahakal HeightsSunil Shivpoojan GuptaDue Apr 2028, extended 4 mo—0%
MHVG BungalowSamir Shrinivas KaleDue Sep 2027—0%
Bamne TowerArsh ConstructionDue Apr 2029, extended 4 mo—0%
Sai MandirSai Tapaswi BuildersDue Apr 2030, extended 4 mo—0%
Mango Lakefront Paradise Guhagar Bungalow No 38Samir Shrinivas KaleDue Mar 2027, extended 4 mo——
PashchimaMakarand Gajanan KhareDue Feb 2027, extended 4 mo—9%
Vithoba ResidencyAnil Vithoba KasarDue Apr 2028, extended 4 mo——
Govinda HeightsRahul Mangesh ShetyeDue Jun 2029, extended 4 mo—0%
Butler ComplexNoor Mohammed Abbas BoatDue Apr 2027, extended 4 mo—9%
Mango Lakeview GuhagarSamir Shrinivas KaleDue Jan 2030, extended 4 mo——
IndradityaSuvarna Bhaskar Infrastructure Private LimitedDue Apr 2029, extended 4 mo—0%
Samarth Sai Prasad Apartment-4Sai Prasad Builders & DevelopersDue Jul 2028, extended 4 mo——
Mango Holiday Village Guhagar BungalowSamir Shrinivas Kale1 mo late——
Mango Holiday Village Guhagar Bungalow No 108Samir Shrinivas Kale10 mo late—0%
Mango Holiday Village Guhagar Bungalow No 90Samir Shrinivas Kale11 mo late—0%
Mango Holiday Village Guhagar Bungalow No 92Samir Shrinivas Kale1 yr 1 mo late—0%
Mango Holiday Village Guhagar Bungalow No 56Samir Shrinivas Kale1 yr 10 mo late—100%
Shree Sadgurukripa Gruhasankul PrakalpRishikesh Ramchandra TavasalkarDue Apr 2032, extended 4 mo——
Siddhakala SwapnapurtiNitin Gopal BendalDue Apr 2028, extended 4 mo——
Mango Holiday Village Guhagar Bungalow No 87Samir Shrinivas Kale2 yrs 5 mo late—0%
Mango Holiday Village Guhagar Bungalow No 106Samir Shrinivas Kale2 yrs 7 mo late—0%

Most active promoters

  1. Samir Shrinivas Kale29 projects
  2. Anil Vithoba Kasar2 projects
  3. Arsh Construction2 projects
  4. Sai Prasad Builders & Developers2 projects
  5. Aakanksha Ajay Salvi1 project
  6. Gokanirmitee1 project
  7. Ishakrisha Associates1 project
  8. Keystone Developers1 project
  9. Makarand Gajanan Khare1 project
  10. Mandke and Mandke Infrastructure Pvt. Ltd.1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology