RERA projects in Lanja

41 projects under 41 MahaRERA registrations, registered 2017–2026. 28% have a completion date extended beyond the one promised.

41RERA projects
41Registrations
15Completion still due21 past their completion date
33 monthsMedian extension beyond promised date28% of registrations extended
0Regulatory casesnone on MahaRERA's lists
5Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
201711
20184
20197
20203
20211
20221
20231
20244
20251
20263

Projects in Lanja

41 projects registered with MahaRERA in this taluka and the places within it.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Lanja City Pride Phase ITechnobuilt InfraPM12810126017482 Sep 202631 Dec 2030—Not yet due0
AashirwadProficient Builders And DevelopersPR12800026011239 Jul 202631 Dec 2028—Not yet due0
Shree Krushnanand SaraswatiMohin Parvesh GharePM128000250297218 Mar 202631 Dec 2027—Not yet due0
Desai BuildingPramod Ramchandra DesaiP5280008099029 Sep 202531 Dec 2027—Not yet due0
Elite ParkSamir Mahamad GhareP5280007815425 Nov 202431 Dec 2026—Not yet due0
Om PlazaOm Builders & DevelopersP5280007749720 Aug 202431 Dec 2026—Not yet due0
SnehbandhSnehabandh Builders & ContractorsP5280005622722 May 202431 Dec 2027—Not yet due0
Marigold 2Samir Mahamad GhareP528000542389 Jan 202431 Dec 2026—Not yet due0
Kripalu HeightsSunil Manoharlal PuriP5280005363121 Nov 202331 Mar 2026—Promised date passed0
Konkan ParkMahesh Rajaram MestryP5280003331715 Feb 202231 Dec 2026—Not yet due0
Audumber ChayaLaxmi DevelopersP5280002880630 Mar 202130 Sep 202330 Sep 2025Extended 24 mo0
Rk Shopping CenterRamchandra Balkrishna KatgalkarP528000273131 Dec 202030 Jun 2027—Not yet due0
Sai Samarth HeritageSai Samarth BuildersP5280002726328 Nov 20201 Jun 2031—Not yet due0
Morya ResidencyManoj Vasant MahadikP5280002605012 Aug 202030 Jun 2026—Promised date passed0
MarigoldSamir Mahamad GhareP528000221494 Sep 201930 Dec 202131 Dec 2026Extended 60 mo0
Swapnsrushti-4Swapna Shrushti - 4P528000206853 May 201930 Jun 2019—Promised date passed0
Swapnsrushti-2Rutuja Rajesh GuravP5280002025129 Mar 201930 Jun 2019—Promised date passed0
Swapnsrushti-1Ashutosh Narayan UpadhyeP5280002006325 Mar 201930 Mar 2019—Promised date passed0
Swapnsrushti-3Ashutosh Narayan UpadhyeP5280002003519 Mar 201930 Mar 2019—Promised date passed0
Swapnsrushti-5Hemant Madhukar NaikP5280002000718 Mar 201930 Mar 2019—Promised date passed0
Taj City Centre and Taj ResidencyK. M. DevelopersP528000198255 Mar 201930 Dec 2023—Promised date passed0
Madhavi ShrushtiGurushrushti Builders & Developers Pvt LtdP5280001900628 Dec 201830 Dec 2024—Promised date passed0
Royal ParkSamir Mahamad GhareP528000176434 Sep 201830 Jun 202130 Dec 2022Extended 18 mo0
Sarvada HeightsSarvada EnterprisesP528000159069 Apr 201830 Sep 202225 Sep 2025Extended 36 mo0
Mr. Hemant Madhukar NaikHemant Madhukar NaikP528000147852 Jan 201830 Dec 2028—Not yet due0
Mr. Ashutosh Narayan UpadhyeAshutosh Narayan UpadhyeP5280001459415 Dec 201730 Nov 2017—Promised date passed0
Samiksha ApartmentShriram Balkrishna JangamP5280001432123 Nov 201714 Dec 2017—Promised date passed0
Kokan ParkMahesh Rajaram MestryP5280001040424 Aug 201730 Jun 202131 Dec 2023Extended 30 mo0
Baitul Zubeeda ApartmentSIMConstructionsP5280000817118 Aug 201731 Dec 2018—Promised date passed0
Satyavinayak GardenRamchandra Balkrishna KatgalkarP5280000833218 Aug 201730 Dec 201929 Dec 2021Extended 24 mo0
Lavish Legend D And EShree Siddhivinayak ConstructionP5280000670616 Aug 201730 Jun 201830 Dec 2021Extended 42 mo0
Belwalkar Shopping CenterKokan Builders & ContractorP528000045009 Aug 201731 Dec 201815 Jan 2022Extended 37 mo0
Haji Abdul Gafur ComplexIsmail Gafur KasuP528000043909 Aug 201730 Oct 202131 Dec 2027Extended 74 mo0
Sai Ganesh ApartmentShri Dattakrupa DevlopersP528000049599 Aug 201730 Jun 20181 Jul 2019Extended 13 mo0
Brahmagiri Bungalow Project Phase 6Saurabh Agro ProductP528000028894 Aug 201730 Dec 2024—Promised date passed0
Sai Samarth MauliSamarth BuilderP5280000219031 Jul 201730 Dec 2028—Not yet due0
Arvind ResidencyP52800019166————0
Galaxy ApartmentP52800024992————0
Jainab ComplexP52800030677————0
Omkar ResidencyP52800014647————0
Vasanti SankulP52800014572————0

Other talukas in Ratnagiri

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Samir Mahamad Ghare4 projects
  2. Ashutosh Narayan Upadhye3 projects
  3. Hemant Madhukar Naik2 projects
  4. Mahesh Rajaram Mestry2 projects
  5. Ramchandra Balkrishna Katgalkar2 projects
  6. Gurushrushti Builders & Developers Pvt Ltd1 project
  7. Ismail Gafur Kasu1 project
  8. K. M. Developers1 project
  9. Kokan Builders & Contractor1 project
  10. Laxmi Developers1 project
Data through8 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology