RERA projects in Nivali
1 project under 1 MahaRERA registration, registered 2017–2017. 100% have a completion date extended beyond the one promised.
Locality
1RERA projects
1Registrations
0Completion still due1 past their completion date
48 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
2Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 1 |
Projects in Nivali
1 project registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Shakambhari builders and developersSudhakar Shridhar Sawant | P52800007017 | 17 Aug 2017 | 24 Jul 2019 | 31 Jul 2023 | Extended 48 mo | 0 |
Other localities in Ratnagiri
Most active promoters
By projects registered here, as named on MahaRERA.
- Sudhakar Shridhar Sawant1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology