RERA projects in Shringartali
13 projects under 13 MahaRERA registrations, registered 2017–2026. 69% have a completion date extended beyond the one promised.
Locality
13RERA projects
13Registrations
7Completion still due6 past their completion date
4 monthsMedian extension beyond promised date69% of registrations extended
0Regulatory casesnone on MahaRERA's lists
16Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 2 |
| 2018 | 1 |
| 2019 | 0 |
| 2020 | 0 |
| 2021 | 0 |
| 2022 | 3 |
| 2023 | 1 |
| 2024 | 3 |
| 2025 | 2 |
| 2026 | 1 |
Projects in Shringartali
13 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Samarth Sai Prasad Apartment-4 Building No 2Sai Prasad Builders & Developers | PR1280002502742 | 12 Mar 2026 | 30 Nov 2030 | 30 Mar 2031 | Extended 4 mo | 0 |
| Golden HeightsQaisar Qasim Chunawala | PM1280002501043 | 1 Oct 2025 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| Bamne TowerArsh Construction | P52800079385 | 3 Mar 2025 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Vithoba ResidencyAnil Vithoba Kasar | P52800056434 | 31 May 2024 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Butler ComplexNoor Mohammed Abbas Boat | P52800055017 | 26 Feb 2024 | 31 Dec 2026 | 30 Apr 2027 | Extended 4 mo | 0 |
| IndradityaSuvarna Bhaskar Infrastructure Private Limited | P52800054581 | 31 Jan 2024 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Samarth Sai Prasad Apartment-4Sai Prasad Builders & Developers | P52800053584 | 10 Nov 2023 | 31 Mar 2028 | 31 Jul 2028 | Extended 4 mo | 0 |
| Gargi ApartmentAnil Vithoba Kasar | P52800034510 | 11 Apr 2022 | 31 Dec 2022 | 31 Dec 2022 | Promised date passed | 0 |
| Ayasha PlazaArsh Construction | P52800034193 | 25 Mar 2022 | 31 Dec 2022 | 31 Dec 2023 | Extended 12 mo | 0 |
| Anant PalaceShubhlaxmi Ganesh Jadhav | P52800033047 | 3 Feb 2022 | 31 Dec 2024 | 31 Dec 2024 | Promised date passed | 0 |
| Star PlazaStar Construction & Developers | P52800018871 | 10 Dec 2018 | 30 Dec 2023 | 30 Dec 2023 | Promised date passed | 0 |
| Shri Maryambi Vansh ParkNarendra Namdeo Dhadve | P52800013301 | 22 Sep 2017 | 31 Dec 2019 | 30 Jun 2023 | Extended 42 mo | 0 |
| Star CityYasmeen Gulaam Tandel | P52800008558 | 19 Aug 2017 | 30 Jun 2019 | 30 Jun 2019 | Promised date passed | 0 |
Other localities in Guhagar
Most active promoters
By projects registered here, as named on MahaRERA.
- Anil Vithoba Kasar2 projects
- Arsh Construction2 projects
- Sai Prasad Builders & Developers2 projects
- Narendra Namdeo Dhadve1 project
- Noor Mohammed Abbas Boat1 project
- Qaisar Qasim Chunawala1 project
- Shubhlaxmi Ganesh Jadhav1 project
- Star Construction & Developers1 project
- Suvarna Bhaskar Infrastructure Private Limited1 project
- Yasmeen Gulaam Tandel1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology