Ratnagiri
Deedo IDDL-RAT-RATNAGIRI4 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects1,149in 117 localities
Registrations1,173some projects hold several
Completion still due342651 past their date
Median extension4 months36% of registrations extended
Regulatory cases64on 64 projects
8 in 10 registrations run late here
1,173 MahaRERA registrations in Ratnagiri and the places within it
92 not yet due250 extended, not yet due651 past even the latest date180 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Ratnagiri
1,149 projects registered with MahaRERA in this district and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Prathamesh SankulSanjay Mahadev Chiplunkar | Due Apr 2029, extended 4 mo | — | — |
| Shiv-Shakti ApartmentSunil Vishnu Mane | Due Jan 2028 | — | 0% |
| Al Fatah SterlingSterling Associates | Due Jul 2028, extended 4 mo | — | — |
| Club OceanClub Ocean Land Developers LLP | Due Dec 2030, extended 4 mo | — | — |
| Bait Ul Noor Wing AFaiyaz Hussain Naguthane | Due Jul 2030, extended 4 mo | — | — |
| Ekdant HeightsEkdant Heights | Due Apr 2029, extended 4 mo | — | — |
| The WindArihant Vastu Nirman Pvt. Ltd | Due Apr 2033, extended 4 mo | — | — |
| Konkan Bliss ResidencesVaishali Vikrant Vaidya | Due Apr 2029, extended 4 mo | — | — |
| Bella VistaPravin Narayan Lad | Due Apr 2030, extended 4 mo | — | — |
| Golden HeightsQaisar Qasim Chunawala | Due Apr 2030, extended 4 mo | — | — |
| Haji Umar ComplexSiraj Karim Pathan | Due Apr 2029, extended 4 mo | — | 0% |
| Shri Kalkai ResidencyShree Swami Samarth Developers | Due Dec 2030 | — | — |
| Desai BuildingPramod Ramchandra Desai | Due Apr 2028, extended 4 mo | — | 0% |
| VrindavanUmket Corporation LLP | Due Jul 2028, extended 4 mo | — | — |
| AboliRajesh Raghunath Nikam | Due Apr 2031, extended 4 mo | — | — |
| Haroon HeightsHaroon Moinuddin Khot | Due Apr 2030, extended 4 mo | — | — |
| Parkar ResidencyAltaf Ahmed Bebal | Due Apr 2031, extended 4 mo | — | — |
| Sai Bhoomi Nagar Phase - IIASita Rajendra Jain | Due Apr 2030, extended 4 mo | — | 0% |
| Abhishek ResidencyAlliance Heights | Due Apr 2029, extended 4 mo | — | — |
| Mango Lakefront Paradise GuhagarSamir Shrinivas Kale | Due Jun 2035, extended 4 mo | — | 0% |
| Cape of Bliss 1BHOABL Management Private Limited | Due Apr 2027, extended 4 mo | — | — |
| Laxmi Narayan HeightsBhairi Bhavani Devlopers | Due Apr 2029, extended 4 mo | — | 0% |
| Mahaajan HorizonMihir Deepak Mahajan | Due Apr 2028, extended 4 mo | — | — |
| Sagar SparshAbhay Mahendra Jain | Due Apr 2031, extended 4 mo | — | 0% |
| TARA HEIGHT PH llMahesh Suresh Gundecha | Due Apr 2029, extended 4 mo | — | 0% |
Localities in Ratnagiri
- Nachane (Ct)121 projects
- Chiplun (M Cl)112 projects
- Khed (M Cl)57 projects
- Zadgaon Ct52 projects
- Dapoli Camp49 projects
- Ratnagiri44 projects
- Chiplun37 projects
- Ratnagiri (M Cl)34 projects
- Dapoli32 projects
- Jalgaon31 projects
- Lanja (Ct)27 projects
- Kirtanwadi Tarf Guhagar25 projects
All 117 localities
- Kherdi (Ct)22
- Bharane20
- Rahataghar20
- Savarde20
- Khed19
- Khedshi19
- Kuwarbav (Ct)14
- Bharana Naka13
- Guhagar13
- Shringartali13
- Mirjoli12
- Kalambaste11
- Khedbhadgaon10
- Gimhavane9
- Guhagar9
- Padavewadi9
- Chinchghari8
- Dhamandivi8
- Harnai8
- Kapsal8
- Karvanchiwadi8
- Kolthare8
- Veral8
- Asage7
- Mandangad7
- Uktad7
- Devrukh (Ct)6
- Lanja6
- Anjarle5
- Mandangad5
- Rajapur (M Cl)5
- Sangameshwar5
- Govalkot4
- Mauje Dapoli4
- Bhoste3
- Brahmanwadi3
- Dhamanvane3
- Ganapatipule3
- Gavhe3
- Ladghar3
- Lote3
- Malgund3
- Mirjole3
- Padale3
- Pimpli Kh.3
- Rajapur3
- Shirshinge3
- Tiwandewadi3
- Walope3
- Asud2
- Bhagaavatinagar2
- Bhingaloli2
- Boraj2
- Ghanekhunt2
- Jogale-Dapoli2
- Kondwadi Tarfe Patpanhale2
- Kumbhave2
- Pachal2
- Sadavali2
- Shirgaon2
- Agave1
- Aghari1
- Ambavali Khurd1
- Ambeshet1
- Asgoli1
- Chandranagar1
- Chikhali1
- Dabhol1
- Dabhole Bk.1
- Ghadewadi1
- Golap1
- Jamsud1
- Juikar Mohalla1
- Karle (Ct)1
- Kasaba Sangmeshwar1
- Kasarwadi1
- Kasop1
- Khalgaon1
- Khandat1
- Khed Bhadgaon1
- Kodavali1
- Kondgaon1
- Kondhe1
- Kondhe1
- Kurne1
- Navedar1
- Neware1
- Nivali1
- Oni1
- Pavas1
- Pethwadi (N.V.)1
- Pimpli-Khurud1
- Ravnangwadi1
- Rowale1
- Sakharpa1
- Savarde Kh.1
- Shirgaon1
- Shiwnari1
- Sondeghar1
- Sukondi1
- Tadil1
- Talyachiwadi Tarfe Palpene1
- Tarfe Guhagar1
- Varveli1
- Veldur1
Other districts
Most active promoters
- Samir Shrinivas Kale29 projects
- Arihant Vastu Nirman Pvt. Ltd10 projects
- Prasad Prabhakar Waghdhare10 projects
- Dinesh Mohanlal Jain8 projects
- Deepak Yashwant Salvi7 projects
- Jain And Jain Construction Company7 projects
- Akar Infrastructure6 projects
- House of Abhinandan Lodha Estate Holdings Private Limited6 projects
- Gandhi Developers5 projects
- Prakash Vasudev Desai5 projects
Data through29 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology