4 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects1,149in 117 localities
Registrations1,173some projects hold several
Completion still due342651 past their date
Median extension4 months36% of registrations extended
Regulatory cases64on 64 projects
Ratnagiri market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

8 in 10 registrations run late here

1,173 MahaRERA registrations in Ratnagiri and the places within it

92 not yet due250 extended, not yet due651 past even the latest date180 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Ratnagiri

1,149 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Prathamesh SankulSanjay Mahadev ChiplunkarDue Apr 2029, extended 4 mo——
Shiv-Shakti ApartmentSunil Vishnu ManeDue Jan 2028—0%
Al Fatah SterlingSterling AssociatesDue Jul 2028, extended 4 mo——
Club OceanClub Ocean Land Developers LLPDue Dec 2030, extended 4 mo——
Bait Ul Noor Wing AFaiyaz Hussain NaguthaneDue Jul 2030, extended 4 mo——
Ekdant HeightsEkdant HeightsDue Apr 2029, extended 4 mo——
The WindArihant Vastu Nirman Pvt. LtdDue Apr 2033, extended 4 mo——
Konkan Bliss ResidencesVaishali Vikrant VaidyaDue Apr 2029, extended 4 mo——
Bella VistaPravin Narayan LadDue Apr 2030, extended 4 mo——
Golden HeightsQaisar Qasim ChunawalaDue Apr 2030, extended 4 mo——
Haji Umar ComplexSiraj Karim PathanDue Apr 2029, extended 4 mo—0%
Shri Kalkai ResidencyShree Swami Samarth DevelopersDue Dec 2030——
Desai BuildingPramod Ramchandra DesaiDue Apr 2028, extended 4 mo—0%
VrindavanUmket Corporation LLPDue Jul 2028, extended 4 mo——
AboliRajesh Raghunath NikamDue Apr 2031, extended 4 mo——
Haroon HeightsHaroon Moinuddin KhotDue Apr 2030, extended 4 mo——
Parkar ResidencyAltaf Ahmed BebalDue Apr 2031, extended 4 mo——
Sai Bhoomi Nagar Phase - IIASita Rajendra JainDue Apr 2030, extended 4 mo—0%
Abhishek ResidencyAlliance HeightsDue Apr 2029, extended 4 mo——
Mango Lakefront Paradise GuhagarSamir Shrinivas KaleDue Jun 2035, extended 4 mo—0%
Cape of Bliss 1BHOABL Management Private LimitedDue Apr 2027, extended 4 mo——
Laxmi Narayan HeightsBhairi Bhavani DevlopersDue Apr 2029, extended 4 mo—0%
Mahaajan HorizonMihir Deepak MahajanDue Apr 2028, extended 4 mo——
Sagar SparshAbhay Mahendra JainDue Apr 2031, extended 4 mo—0%
TARA HEIGHT PH llMahesh Suresh GundechaDue Apr 2029, extended 4 mo—0%

Most active promoters

  1. Samir Shrinivas Kale29 projects
  2. Arihant Vastu Nirman Pvt. Ltd10 projects
  3. Prasad Prabhakar Waghdhare10 projects
  4. Dinesh Mohanlal Jain8 projects
  5. Deepak Yashwant Salvi7 projects
  6. Jain And Jain Construction Company7 projects
  7. Akar Infrastructure6 projects
  8. House of Abhinandan Lodha Estate Holdings Private Limited6 projects
  9. Gandhi Developers5 projects
  10. Prakash Vasudev Desai5 projects
Data through29 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology