8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects1,149in 117 localities
Registrations1,173some projects hold several
Completion still due341653 past their date
Median extension4 months36% of registrations extended
Regulatory cases66on 66 projects

8 in 10 registrations run late here

1,173 MahaRERA registrations in Ratnagiri and the places within it

93 not yet due248 extended, not yet due653 past even the latest date179 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Ratnagiri

1,149 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
ShriganeshaMahesh Maruti MahadikDue Jul 2027, extended 4 mo—19%
Asha Neelam ResidencyAsha Ashok Kanase11 mo late——
Shreejee Ocean ViewDinesh Mohanlal JainDue Jul 2028, extended 4 mo——
Omkar SwamikrupaPrasad Prabhakar WaghdhareCompleted—76%
Janhavi AvenueRavindra Murlidhar ManeDue Apr 2028, extended 4 mo—20%
Siddhi A SquareJogesh Madhukar SadvilkarCompleted—53%
Butler ComplexNoor Mohammed Abbas BoatDue Apr 2027, extended 4 mo—9%
Shrihari SankulSaukhyam Builders Private LimitedDue Jul 2027, extended 4 mo——
Mango Lakeview GuhagarSamir Shrinivas KaleDue Jan 2030, extended 4 mo——
Rushang ResidencyRakesh Rajaram ChalkeDue Apr 2029, extended 4 mo—17%
Kshitij Serviced ApartmentsDeepak Vishwas VichareDue Apr 2028, extended 4 mo—6%
Anandi ResidencyAarambha ConstructionsDue Apr 2028, extended 4 mo——
IndradityaSuvarna Bhaskar Infrastructure Private LimitedDue Apr 2029, extended 4 mo——
Shalini WadiSanjay Tukaram KhanvilkarDue Apr 2034, extended 4 mo—4%
Dream HorizonDelight DevelopersDue Apr 2027, extended 4 mo——
Marigold 2Samir Mahamad GhareDue Apr 2027, extended 4 mo——
Sahar HeightsAmina Dawood DalwaiCompleted——
Rajlaxmi SankulDinesh Mohanlal JainDue Apr 2029, extended 4 mo——
Ratnasagar ResidencyBarsana GroupDue Apr 2027, extended 4 mo—13%
KeshavrajAnil Bajarang ChanneDue Apr 2028, extended 4 mo——
Hiray's WisteriaHiray DevelopersDue Apr 2029, extended 4 mo——
Dwarka ShrushtiDwarka Builders And DevelopersDue Jan 2029, extended 4 mo——
Aparant PrimeAparant DevelopersCompleted—34%
Swami Chaitanya ComplexSwami Chaitanya Builders & DevelopersDue May 2027, extended 4 mo——
Kripalu HeightsSunil Manoharlal Puri8 mo late——
Ratnagiri market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Samir Shrinivas Kale29 projects
  2. Samir Shrinivas Kale22 projects
  3. Arihant Vastu Nirman Pvt. Ltd10 projects
  4. Prasad Prabhakar Waghdhare10 projects
  5. Dinesh Mohanlal Jain8 projects
  6. Jain And Jain Construction Company8 projects
  7. Akar Infrastructure6 projects
  8. Gandhi Developers5 projects
  9. Phatak Developers5 projects
  10. Prakash Vasudev Desai5 projects

Ratnagiri, in questions

How many projects in Ratnagiri run late?

8 in 10 MahaRERA registrations (901 of 1,173): their completion date was extended or has passed, data through 22 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Ratnagiri by Deedo. Medians on fewer than 3 deeds are not shown.

Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology