Deedo IDDL-RAT-RATNAGIRI8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects1,149in 117 localities
Registrations1,173some projects hold several
Completion still due341653 past their date
Median extension4 months36% of registrations extended
Regulatory cases66on 66 projects
8 in 10 registrations run late here
1,173 MahaRERA registrations in Ratnagiri and the places within it
93 not yet due248 extended, not yet due653 past even the latest date179 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Ratnagiri
1,149 projects registered with MahaRERA in this district and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Aai Ekvira MauliIndra Builders And Developers | 6 mo late | — | — |
| Dapoli by the BayRahul Subhash Habbu | Due Jul 2027, extended 4 mo | — | — |
| Dhanwantari EnclaveMedha Vinay Kali | Due Apr 2029, extended 4 mo | — | 22% |
| Mohsin ResidencyReetaj Builders & Developers | Due Apr 2027, extended 4 mo | — | — |
| Vithoba ResidencyAnil Vithoba Kasar | Due Apr 2028, extended 4 mo | — | — |
| Rajasvi EnclaveVivek Prabhakar Bapat | Due Sep 2029, extended 4 mo | — | — |
| SnehbandhSnehabandh Builders & Contractors | Due Apr 2028, extended 4 mo | — | — |
| Unity AsterUnitymegacorppvtltd | Due Apr 2029, extended 4 mo | — | 3% |
| Mauli Park Phase 1Sanjay Govind Joshi | Due Apr 2031, extended 4 mo | — | — |
| Neermiti ResidencyImran Mujahid Mulla | Due Apr 2031, extended 4 mo | — | — |
| Madhuryash Phase IIMansi Rakesh Vichare | 6 mo late | — | — |
| Bharatmata Smart SpacesRahul Builders And Developers | Due Apr 2028, extended 4 mo | — | 21% |
| NityanandnilayamOmram Infratech Private Limited | Completed | — | — |
| Swami ComplexAmey Developers | Due Apr 2029, extended 4 mo | — | — |
| Wellness HomesPurva Naresh Rajeshirke | Due Apr 2029, extended 4 mo | — | 33% |
| Govinda HeightsRahul Mangesh Shetye | Due Jun 2029, extended 4 mo | — | — |
| VrindavanSamruddhi Developers | 8 mo late | — | — |
| Vrundavan ResidencyDream House Construction | 2 yrs 1 mo late | — | — |
| Mauli ResidencyIra Developers | Completed | — | 46% |
| Gadre EmpireSawakar And Company | Due Apr 2029, extended 4 mo | — | — |
| Siddheshwar VihaanSiddheshwar Infra | 6 mo late | — | — |
| AmrutdharaAnmol Builders And Developers | Due Apr 2029, extended 4 mo | — | 15% |
| ArohiPradip Chandrakant Raut | Due Jul 2028, extended 4 mo | — | — |
| Mahadev ComplexMangalmurti Developers And Builders | Due Apr 2030, extended 4 mo | — | — |
| Sea View ApartmentShree Datta Construction | Due May 2027, extended 4 mo | — | — |
Localities in Ratnagiri
- Nachane (Ct)121 projects
- Chiplun (M Cl)111 projects
- Khed (M Cl)57 projects
- Zadgaon Ct56 projects
- Dapoli Camp49 projects
- Chiplun37 projects
- Ratnagiri (M Cl)34 projects
- Jalgaon33 projects
- Ratnagiri33 projects
- Dapoli28 projects
- Lanja (Ct)27 projects
- Kirtanwadi Tarf Guhagar25 projects
All 117 localities
- Khedshi22
- Kherdi (Ct)22
- Rahataghar22
- Bharane20
- Savarde20
- Khed19
- Kuwarbav (Ct)14
- Shringartali14
- Bharana Naka13
- Mirjoli13
- Guhagar12
- Kalambaste11
- Gimhavane10
- Khedbhadgaon10
- Guhagar9
- Harnai9
- Padavewadi9
- Veral9
- Chinchghari8
- Dhamandivi8
- Kapsal8
- Karvanchiwadi8
- Kolthare8
- Mandangad8
- Asage7
- Uktad7
- Devrukh (Ct)6
- Lanja6
- Anjarle5
- Rajapur (M Cl)5
- Sangameshwar5
- Govalkot4
- Mandangad4
- Mauje Dapoli4
- Tiwandewadi4
- Bhoste3
- Brahmanwadi3
- Dhamanvane3
- Ganapatipule3
- Gavhe3
- Ladghar3
- Lote3
- Malgund3
- Mirjole3
- Padale3
- Pimpli Kh.3
- Rajapur3
- Shirshinge3
- Walope3
- Asud2
- Bhagaavatinagar2
- Bhingaloli2
- Boraj2
- Ghanekhunt2
- Jogale-Dapoli2
- Kasop2
- Kondwadi Tarfe Patpanhale2
- Kumbhave2
- Pachal2
- Sadavali2
- Shirgaon2
- Agave1
- Aghari1
- Ambavali Khurd1
- Ambeshet1
- Asgoli1
- Chandranagar1
- Chikhali1
- Dabhol1
- Dabhole Bk.1
- Ghadewadi1
- Golap1
- Jamsud1
- Juikar Mohalla1
- Karle (Ct)1
- Kasaba Sangmeshwar1
- Kasarwadi1
- Khalgaon1
- Khandat1
- Khed Bhadgaon1
- Kodavali1
- Kondgaon1
- Kondhe1
- Kondhe1
- Kurne1
- Navedar1
- Neware1
- Nivali1
- Oni1
- Pavas1
- Pethwadi (N.V.)1
- Pimpli-Khurud1
- Ravnangwadi1
- Rowale1
- Sakharpa1
- Savarde Kh.1
- Shirgaon1
- Shiwnari1
- Sondeghar1
- Sukondi1
- Tadil1
- Talyachiwadi Tarfe Palpene1
- Tarfe Guhagar1
- Varveli1
- Veldur1
Other districts
Most active promoters
- Samir Shrinivas Kale29 projects
- Samir Shrinivas Kale22 projects
- Arihant Vastu Nirman Pvt. Ltd10 projects
- Prasad Prabhakar Waghdhare10 projects
- Dinesh Mohanlal Jain8 projects
- Jain And Jain Construction Company8 projects
- Akar Infrastructure6 projects
- Gandhi Developers5 projects
- Phatak Developers5 projects
- Prakash Vasudev Desai5 projects
Ratnagiri, in questions
How many projects in Ratnagiri run late?
8 in 10 MahaRERA registrations (901 of 1,173): their completion date was extended or has passed, data through 22 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Ratnagiri by Deedo. Medians on fewer than 3 deeds are not shown.
Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology