2,215 MahaRERA projects in Pune are past their promised completion date, and MahaRERA shows no completion for them.
Most overdue first
Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 32 of 45.
| Project | Locality | Promised | Revised | Delivery |
|---|---|---|---|---|
| Icon RoseliaIcon Realty Unit 2 | Ghorapade Peth | Jan 2025 | Mar 2026 | 1 yr 10 mo late |
| Iristo GoldIristo Developers llp | Wadagaon (Ct) | Jan 2025 | Jan 2026 | 1 yr 10 mo late |
| Marigold ResidencyJ W Associates | Dighi | Jan 2025 | Jan 2025 | 1 yr 10 mo late |
| Neelkanth Landmarks Shreeniwas ResidencyNeelkanth Landmarks | Kadamwak Wasti | Jan 2025 | Mar 2026 | 1 yr 10 mo late |
| Ohana EstatesOhana Estates LLP | Bhegadewadi | Jan 2025 | Jul 2026 | 1 yr 10 mo late |
| Punit TowerPunit Developers | Pune (M Corp.) | Jan 2025 | Jan 2025 | 1 yr 10 mo late |
| Sona RupaParshwa Developers | Pune (M Corp.) | Jan 2025 | Jan 2025 | 1 yr 10 mo late |
| ChandrakamalBhaktamar Realities LLP | Shukrawar Peth | Feb 2025 | Feb 2025 | 1 yr 9 mo late |
| Golden PlazaGanraj Properties | Hadapsar | Feb 2025 | Dec 2025 | 1 yr 9 mo late |
| Omkar HeightsPasalkar And Patil Associates | Pune (M Corp.) | Feb 2025 | Feb 2025 | 1 yr 9 mo late |
| Ishanya SrushtiJogeshwari Developers | Kondhve Dhawade | Feb 2025 | Feb 2025 | 1 yr 9 mo late |
| Shree Swami SamarthEmpire Developers | Pune (M Corp.) | Feb 2025 | Feb 2025 | 1 yr 9 mo late |
| Samartha ParadiseSamartha Properties | Lonikalbhor | Feb 2025 | Feb 2025 | 1 yr 9 mo late |
| Prime CornerPrime Construction | Narayangaon | Feb 2025 | Feb 2025 | 1 yr 9 mo late |
| SwapnshilpUmesh Vasantrao Meshram | Narhe | Feb 2025 | Feb 2025 | 1 yr 9 mo late |
| 29 Gold Coast Phase 7Mantra 29 Gold Cost Developers LLP | Dhanori | Feb 2025 | Feb 2025 | 1 yr 9 mo late |
| Sai ShyamPrashant Shamrao Pawar | Daund (M Cl) | Feb 2025 | Feb 2025 | 1 yr 9 mo late |
| Nyati Ekaant INitin Dwarkadas Nyati | Dhayari (Part) | Feb 2025 | Feb 2025 | 1 yr 9 mo late |
| Sai Reeyansh ParkSwapnil Rajendra Kashid | Charholi | Feb 2025 | Feb 2025 | 1 yr 9 mo late |
| Bihani ComplexSunil Tarachand Bihani | Pune City | Mar 2025 | Mar 2025 | 1 yr 8 mo late |
| Belmont NexusBelmont Properties | Dhanori | Mar 2025 | Mar 2025 | 1 yr 8 mo late |
| Pruthvi TowerVaishali Santosh Lokhande | Indapur (M Cl) | Mar 2025 | Mar 2025 | 1 yr 8 mo late |
| Empyrean - XFabriworld Structural Engineering Private Limited | Haveli | Mar 2025 | Mar 2025 | 1 yr 8 mo late |
| EcoviharSiddhesh Ramchandra Bangar | Shikrapur | Mar 2025 | Mar 2025 | 1 yr 8 mo late |
| Amit SankulGhansham Jagannath Dahiwal | Katraj | Mar 2025 | Mar 2025 | 1 yr 8 mo late |
| Itrend Life PlusManas Pearl Ventures | Wakad | Mar 2025 | Mar 2025 | 1 yr 8 mo late |
| 51 SiberiaBunty Properties Unit No VII | Dhanori | Mar 2025 | Mar 2025 | 1 yr 8 mo late |
| Bhargav StellaBhargav Shelters | Dhankawadi | Mar 2025 | Mar 2026 | 1 yr 8 mo late |
| DnyaneshNimit Group | Dudulgaon | Mar 2025 | Mar 2025 | 1 yr 8 mo late |
| Empress ViewMohit Construction | Wanwadi | Mar 2025 | Mar 2026 | 1 yr 8 mo late |
| KingstownRaga Developers | Chandkhed | Mar 2025 | Mar 2025 | 1 yr 8 mo late |
| RKH Golden Sunrise Building ASargun Developers | Moshi | Mar 2025 | Mar 2025 | 1 yr 8 mo late |
| Aishwarya HeightsShree Sadguru Construction | Ambegaon Bk | Mar 2025 | Jul 2026 | 1 yr 8 mo late |
| Aishwaryam GemstoneEssen Realtors | Pimpri Chinchawad (M Corp.) | Mar 2025 | Jun 2025 | 1 yr 8 mo late |
| Ananya ResidencyRajan Dhananjay Kolekar | Baramati Rural | Mar 2025 | Mar 2025 | 1 yr 8 mo late |
| Apex Trade ZoneTyagi And Rameshwar Infrastructures | Pune (M Corp.) | Mar 2025 | Mar 2025 | 1 yr 8 mo late |
| AriseSaksham Properties | Wagholi | Mar 2025 | Mar 2025 | 1 yr 8 mo late |
| Avalon City - Wing AClassic Promoters and Builders Private Limited | Pimpri Chinchawad (M Corp.) | Mar 2025 | Mar 2025 | 1 yr 8 mo late |
| Bhongade Pak Phase VISharad Bhongade | Varale | Mar 2025 | Mar 2025 | 1 yr 8 mo late |
| Bora PrideKonark Associates | Pimpri | Mar 2025 | Mar 2025 | 1 yr 8 mo late |
| Bhairav HeightsBasagonda Ningonda Patil | Gultekadi | Mar 2025 | Mar 2025 | 1 yr 8 mo late |
| Chintamani HeightsNarendra Balasaheb Badave | Manjari Kh | Mar 2025 | Feb 2026 | 1 yr 8 mo late |
| Casa ElanzaParmaz Green Realty LLP | Keshavnagarmundwa | Mar 2025 | Sep 2026 | 1 yr 8 mo late |
| Clover CASA 30Worthwhile Properties Pvt. Ltd. | Sate | Mar 2025 | Mar 2025 | 1 yr 8 mo late |
| Dnyaneshwari AppartementShree Swami Samarth Developers And Builders | Moshi | Mar 2025 | Mar 2025 | 1 yr 8 mo late |
| Eastern AvenueKhandge Brothers & Associates | Talegaon Dabhade (M Cl) | Mar 2025 | Mar 2025 | 1 yr 8 mo late |
| Ganesh Siddhi B1 B2Ganeshconstruction | Chikhali | Mar 2025 | Mar 2025 | 1 yr 8 mo late |
| Grace AvenueTrimurthy Narayan | Baner | Mar 2025 | Sep 2026 | 1 yr 8 mo late |
| Gracious GardenRohan Properties | Kharadi | Mar 2025 | Mar 2025 | 1 yr 8 mo late |
| Hillcrest ResidencyJijau Developers | Tandulwadi | Mar 2025 | Mar 2025 | 1 yr 8 mo late |
Delayed projects by district
All MaharashtraPune · 2,215Thane · 1,158Raigarh · 1,042Mumbai Suburban · 994Nashik · 483Palghar · 362Nagpur · 323Aurangabad · 243Mumbai City · 242Satara · 228Ratnagiri · 192Sangli · 176Solapur · 155Kolhapur · 131Amravati · 72Sindhudurg · 72Ahmednagar · 69Chandrapur · 39Jalgaon · 39Latur · 28Akola · 23Beed · 21Nanded · 18Dhule · 17Wardha · 16Buldana · 14Jalna · 12Parbhani · 9Bhandara · 8Yavatmal · 6
SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology