Delayed projects in Pune

2,215 MahaRERA projects in Pune are past their promised completion date, and MahaRERA shows no completion for them.

Most overdue first

Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 32 of 45.

ProjectLocalityPromisedRevisedDelivery
Icon RoseliaIcon Realty Unit 2Ghorapade PethJan 2025Mar 20261 yr 10 mo late
Iristo GoldIristo Developers llpWadagaon (Ct)Jan 2025Jan 20261 yr 10 mo late
Marigold ResidencyJ W AssociatesDighiJan 2025Jan 20251 yr 10 mo late
Neelkanth Landmarks Shreeniwas ResidencyNeelkanth LandmarksKadamwak WastiJan 2025Mar 20261 yr 10 mo late
Ohana EstatesOhana Estates LLPBhegadewadiJan 2025Jul 20261 yr 10 mo late
Punit TowerPunit DevelopersPune (M Corp.)Jan 2025Jan 20251 yr 10 mo late
Sona RupaParshwa DevelopersPune (M Corp.)Jan 2025Jan 20251 yr 10 mo late
ChandrakamalBhaktamar Realities LLPShukrawar PethFeb 2025Feb 20251 yr 9 mo late
Golden PlazaGanraj PropertiesHadapsarFeb 2025Dec 20251 yr 9 mo late
Omkar HeightsPasalkar And Patil AssociatesPune (M Corp.)Feb 2025Feb 20251 yr 9 mo late
Ishanya SrushtiJogeshwari DevelopersKondhve DhawadeFeb 2025Feb 20251 yr 9 mo late
Shree Swami SamarthEmpire DevelopersPune (M Corp.)Feb 2025Feb 20251 yr 9 mo late
Samartha ParadiseSamartha PropertiesLonikalbhorFeb 2025Feb 20251 yr 9 mo late
Prime CornerPrime ConstructionNarayangaonFeb 2025Feb 20251 yr 9 mo late
SwapnshilpUmesh Vasantrao MeshramNarheFeb 2025Feb 20251 yr 9 mo late
29 Gold Coast Phase 7Mantra 29 Gold Cost Developers LLPDhanoriFeb 2025Feb 20251 yr 9 mo late
Sai ShyamPrashant Shamrao PawarDaund (M Cl)Feb 2025Feb 20251 yr 9 mo late
Nyati Ekaant INitin Dwarkadas NyatiDhayari (Part)Feb 2025Feb 20251 yr 9 mo late
Sai Reeyansh ParkSwapnil Rajendra KashidCharholiFeb 2025Feb 20251 yr 9 mo late
Bihani ComplexSunil Tarachand BihaniPune CityMar 2025Mar 20251 yr 8 mo late
Belmont NexusBelmont PropertiesDhanoriMar 2025Mar 20251 yr 8 mo late
Pruthvi TowerVaishali Santosh LokhandeIndapur (M Cl)Mar 2025Mar 20251 yr 8 mo late
Empyrean - XFabriworld Structural Engineering Private LimitedHaveliMar 2025Mar 20251 yr 8 mo late
EcoviharSiddhesh Ramchandra BangarShikrapurMar 2025Mar 20251 yr 8 mo late
Amit SankulGhansham Jagannath DahiwalKatrajMar 2025Mar 20251 yr 8 mo late
Itrend Life PlusManas Pearl VenturesWakadMar 2025Mar 20251 yr 8 mo late
51 SiberiaBunty Properties Unit No VIIDhanoriMar 2025Mar 20251 yr 8 mo late
Bhargav StellaBhargav SheltersDhankawadiMar 2025Mar 20261 yr 8 mo late
DnyaneshNimit GroupDudulgaonMar 2025Mar 20251 yr 8 mo late
Empress ViewMohit ConstructionWanwadiMar 2025Mar 20261 yr 8 mo late
KingstownRaga DevelopersChandkhedMar 2025Mar 20251 yr 8 mo late
RKH Golden Sunrise Building ASargun DevelopersMoshiMar 2025Mar 20251 yr 8 mo late
Aishwarya HeightsShree Sadguru ConstructionAmbegaon BkMar 2025Jul 20261 yr 8 mo late
Aishwaryam GemstoneEssen RealtorsPimpri Chinchawad (M Corp.)Mar 2025Jun 20251 yr 8 mo late
Ananya ResidencyRajan Dhananjay KolekarBaramati RuralMar 2025Mar 20251 yr 8 mo late
Apex Trade ZoneTyagi And Rameshwar InfrastructuresPune (M Corp.)Mar 2025Mar 20251 yr 8 mo late
AriseSaksham PropertiesWagholiMar 2025Mar 20251 yr 8 mo late
Avalon City - Wing AClassic Promoters and Builders Private LimitedPimpri Chinchawad (M Corp.)Mar 2025Mar 20251 yr 8 mo late
Bhongade Pak Phase VISharad BhongadeVaraleMar 2025Mar 20251 yr 8 mo late
Bora PrideKonark AssociatesPimpriMar 2025Mar 20251 yr 8 mo late
Bhairav HeightsBasagonda Ningonda PatilGultekadiMar 2025Mar 20251 yr 8 mo late
Chintamani HeightsNarendra Balasaheb BadaveManjari KhMar 2025Feb 20261 yr 8 mo late
Casa ElanzaParmaz Green Realty LLPKeshavnagarmundwaMar 2025Sep 20261 yr 8 mo late
Clover CASA 30Worthwhile Properties Pvt. Ltd.SateMar 2025Mar 20251 yr 8 mo late
Dnyaneshwari AppartementShree Swami Samarth Developers And BuildersMoshiMar 2025Mar 20251 yr 8 mo late
Eastern AvenueKhandge Brothers & AssociatesTalegaon Dabhade (M Cl)Mar 2025Mar 20251 yr 8 mo late
Ganesh Siddhi B1 B2GaneshconstructionChikhaliMar 2025Mar 20251 yr 8 mo late
Grace AvenueTrimurthy NarayanBanerMar 2025Sep 20261 yr 8 mo late
Gracious GardenRohan PropertiesKharadiMar 2025Mar 20251 yr 8 mo late
Hillcrest ResidencyJijau DevelopersTandulwadiMar 2025Mar 20251 yr 8 mo late

Delayed projects by district

SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology