RERA projects in Daund (M Cl)
29 projects under 29 MahaRERA registrations, registered 2017–2026. 28% have a completion date extended beyond the one promised.
29RERA projects
29Registrations
10Completion still due19 past their completion date
21 monthsMedian extension beyond promised date28% of registrations extended
0Regulatory casesnone on MahaRERA's lists
38Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 11 |
| 2018 | 3 |
| 2019 | 2 |
| 2020 | 3 |
| 2021 | 1 |
| 2022 | 3 |
| 2023 | 0 |
| 2024 | 2 |
| 2025 | 1 |
| 2026 | 3 |
Projects in Daund (M Cl)
29 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| SwapnavatJadhav Associates | PM1260002601498 | 10 Aug 2026 | 31 Dec 2029 | — | Not yet due | 0 |
| Avadhut PrimeMandhare Construction | PR1260002502905 | 18 Mar 2026 | 5 Feb 2031 | — | Not yet due | 0 |
| NakshatraPrakash Realty | PR1261012502932 | 18 Mar 2026 | 31 Dec 2029 | — | Not yet due | 0 |
| EkdantaM/S Prakash Construction Co. | PR1260002501541 | 21 Nov 2025 | 18 Dec 2028 | — | Not yet due | 0 |
| Royal ResidencyUdayan Pravin Dhame | P52100078318 | 4 Dec 2024 | 31 Dec 2030 | — | Not yet due | 0 |
| Gopalnath ResidencyBhivaji Navnath Bandgar | P52100077353 | 9 Aug 2024 | 1 Feb 2029 | — | Not yet due | 0 |
| Shri Ashtavinayak ParkAjay Builders And Associates Daund | P52100048366 | 27 Dec 2022 | 24 Oct 2026 | — | Not yet due | 0 |
| Royal PalmUdayan Pravin Dhame | P52100047532 | 7 Nov 2022 | 12 Dec 2029 | — | Not yet due | 0 |
| Desai ResidencyYogesh Laxman Chaporkar | P52100034667 | 20 Apr 2022 | 15 Feb 2023 | 15 Feb 2024 | Extended 12 mo | 0 |
| Sai ShyamPrashant Shamrao Pawar | P52100030232 | 10 Aug 2021 | 21 Feb 2025 | — | Promised date passed | 0 |
| R CityReva Construction And Developers | P52100027362 | 6 Dec 2020 | 31 Mar 2028 | — | Not yet due | 0 |
| Pancham ParkS R K Developers | P52100025821 | 18 Jul 2020 | 30 Jun 2024 | — | Promised date passed | 0 |
| Shridhar ResidencyMahendra Mahadeo Bhongle | P52100024114 | 21 Jan 2020 | 30 Sep 2023 | — | Promised date passed | 0 |
| Krushnakunj Housing SocietyDisha Constructions | P52100023366 | 12 Dec 2019 | 24 Dec 2023 | — | Promised date passed | 0 |
| Pahal ApartmentPrerana Construction | P52100022308 | 9 Sep 2019 | 30 Dec 2024 | 31 Dec 2026 | Extended 24 mo | 0 |
| Swapna RatnaJadhav Associates | P52100019026 | 28 Dec 2018 | 30 Dec 2022 | — | Promised date passed | 0 |
| Mount Galaxy A WingAnthony Sebastian Philip | P52100015459 | 27 Feb 2018 | 30 Dec 2023 | — | Promised date passed | 0 |
| Priya ApartmentM/S Mantri Construction | P52100015204 | 7 Feb 2018 | 30 Sep 2020 | — | Promised date passed | 0 |
| Daffodil Greens F BuildingVishhram Nlp Associates | P52100011911 | 31 Aug 2017 | 30 Dec 2023 | — | Promised date passed | 0 |
| Dattakala ParkDipali Ramdas Jadhav | P52100008688 | 19 Aug 2017 | 30 Mar 2018 | 31 Jul 2018 | Extended 4 mo | 0 |
| GirnarAbhay Chandramohan Sawant | P52100007331 | 17 Aug 2017 | 31 Mar 2019 | 30 Sep 2020 | Extended 18 mo | 0 |
| Saraswati ApartmentAarin Constructions Daund | P52100007213 | 17 Aug 2017 | 31 Dec 2018 | 30 Dec 2022 | Extended 48 mo | 0 |
| Town CentralVaibhav Construction | P52100007390 | 17 Aug 2017 | 31 Mar 2019 | 30 Dec 2021 | Extended 33 mo | 0 |
| Ganraya Mall phase1 wing BPrakash Realty | P52100005707 | 11 Aug 2017 | 31 Dec 2019 | 30 Dec 2021 | Extended 24 mo | 0 |
| Kasturi PrideGovind Vasant Sangalgikar | P52100002948 | 4 Aug 2017 | 31 Jul 2019 | — | Promised date passed | 0 |
| Yashada ResidencyAgresar Construction | P52100002610 | 2 Aug 2017 | 31 Dec 2018 | — | Promised date passed | 0 |
| Sarvesh ApartmentsPrakash Construction Co | P52100001214 | 27 Jul 2017 | 30 Jul 2019 | 29 Jan 2021 | Extended 18 mo | 0 |
| Tarangan ResidencyRupali Sham Kate | P52100001318 | 27 Jul 2017 | 30 Apr 2019 | — | Promised date passed | 0 |
| Crystal NestUnique Associates | P52100000103 | 3 Jul 2017 | 30 Jun 2019 | — | Promised date passed | 0 |
Other localities in Daund
- Daund (Ct)12 projects
- Gopalwadi10 projects
- Boripardhi9 projects
- Yawat5 projects
- Kedgaon Station4 projects
- Lingali4 projects
- Patas4 projects
- Girim2 projects
- Kurkumbh2 projects
- Warwand2 projects
- Bhandgaon1 project
- Boribhadak1 project
Most active promoters
By projects registered here, as named on MahaRERA.
- Jadhav Associates2 projects
- Prakash Realty2 projects
- Udayan Pravin Dhame2 projects
- Aarin Constructions Daund1 project
- Abhay Chandramohan Sawant1 project
- Agresar Construction1 project
- Ajay Builders And Associates Daund1 project
- Anthony Sebastian Philip1 project
- Bhivaji Navnath Bandgar1 project
- Dipali Ramdas Jadhav1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology