RERA projects in Lingali
4 projects under 4 MahaRERA registrations, registered 2017–2018. 50% have a completion date extended beyond the one promised.
Locality
4RERA projects
4Registrations
0Completion still due4 past their completion date
18 monthsMedian extension beyond promised date50% of registrations extended
0Regulatory casesnone on MahaRERA's lists
7Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 3 |
| 2018 | 1 |
Projects in Lingali
4 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Sai ParadiseSJ Construction | P52100018848 | 6 Dec 2018 | 30 Dec 2024 | 30 Dec 2025 | Extended 12 mo | 0 |
| Prachi ApartmentOm Siddhi Associates | P52100010681 | 31 Aug 2017 | 15 Sep 2018 | 15 Sep 2018 | Promised date passed | 0 |
| Green CitySwati Tushar Doshi | P52100010123 | 24 Aug 2017 | 15 Aug 2018 | 15 Aug 2018 | Promised date passed | 0 |
| Rajnandini ComplexRajnandini Construction | P52100003160 | 4 Aug 2017 | 31 Dec 2019 | 30 Dec 2021 | Extended 24 mo | 0 |
Other localities in Daund
Most active promoters
By projects registered here, as named on MahaRERA.
- Om Siddhi Associates1 project
- Rajnandini Construction1 project
- SJ Construction1 project
- Swati Tushar Doshi1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology