2 projects under 2 MahaRERA registrations, registered 2017–2017. 50% have a completion date extended beyond the one promised.

Locality
2RERA projects
2Registrations
1Completion still due1 past their completion date
96 monthsMedian extension beyond promised date50% of registrations extended
2Regulatory caseson 2 projects
2Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20172

Projects in Girim

2 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
K K Sundarban Building A1K K DevelopersP5210000896519 Aug 201730 Jun 201930 Jun 2019Promised date passed1
K K Sundarban Building HK K DevelopersP521000043209 Aug 201731 Dec 201831 Dec 2026Extended 96 mo1

Other localities in Daund

Most active promoters

By projects registered here, as named on MahaRERA.

  1. K K Developers2 projects
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology