111 projects under 115 MahaRERA registrations, registered 2017–2026. 23% have a completion date extended beyond the one promised.
111RERA projects
115Registrationssome projects hold several
38Completion still due77 past their completion date
18 monthsMedian extension beyond promised date23% of registrations extended
0Regulatory casesnone on MahaRERA's lists
21Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 41 |
| 2018 | 7 |
| 2019 | 8 |
| 2020 | 4 |
| 2021 | 5 |
| 2022 | 11 |
| 2023 | 10 |
| 2024 | 10 |
| 2025 | 6 |
| 2026 | 13 |
Projects in Wadagaon (Ct)
111 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Vedant PrideG And D Developers | PM1260002602007 | 23 Sep 2026 | 31 Dec 2028 | — | Not yet due | 0 |
| S M TowerJawaleshwar Construction | PR1260002601950 | 17 Sep 2026 | 31 Dec 2029 | — | Not yet due | 0 |
| Kutumb Prime LifeNaiknavare Townships LLP | PM1260002601509 | 11 Aug 2026 | 19 Oct 2029 | — | Not yet due | 0 |
| Shravani HeightsShreyash Engineers And Developers | PR1260002601305 | 24 Jul 2026 | 31 Dec 2029 | — | Not yet due | 0 |
| Kutumb WoodsNaiknavare Townships LLP & Mr.hemant Dattaji Naiknavare | PR1260002601201 | 16 Jul 2026 | 31 Dec 2028 | — | Not yet due | 0 |
| Shri Vinayak HeightsShri Vinayak Construction | PR1260002600319 | 30 Apr 2026 | 31 Mar 2027 | — | Not yet due | 0 |
| Moraya ResidencyGuru Infra | PR1260002600218 | 18 Apr 2026 | 31 Dec 2028 | — | Not yet due | 0 |
| Kutumb Bhoomi Phase IINAIKNAVARE TOWNSHIPS LLP & Mr.Hemant Dattaji Naiknavare | PP1260002502669 | 9 Mar 2026 | 31 Mar 2027 | — | Not yet due | 0 |
| Samarth VishvaB And P Developers | PM1260002502667 | 9 Mar 2026 | 30 Dec 2029 | — | Not yet due | 0 |
| 56 Kings AvenueVastushree Infra Reality | PM1260002502558 | 2 Mar 2026 | 30 Dec 2028 | — | Not yet due | 0 |
| Rudraksha 2Trilochan Developers | PR1260002502318 | 10 Feb 2026 | 31 Dec 2027 | — | Not yet due | 0 |
| SwarajyaVc Bace Constrotech LLP | PM1260002501991 | 6 Jan 2026 | 31 Dec 2029 | — | Not yet due | 0 |
| Riddhi Siddhi HeightsSmw Builders And Developers | PR1260002501880 | 26 Dec 2025 | 31 Jan 2029 | — | Not yet due | 0 |
| Sunbliss VillaAdvika Enterprises | PR1260002501526, PR1260002601093 | 21 Nov 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Keshav KunjGraystone Realty | P52100081012 | 13 Oct 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Aakar TathastuAakar Lifespaces | PR1260002500111 | 23 Jun 2025 | 31 Mar 2028 | — | Not yet due | 0 |
| Rkl Indrayani CityR K Lunkad Housing Company | P52100080330 | 22 May 2025 | 31 Dec 2031 | — | Not yet due | 0 |
| Gauri Nandan ApartmentsVC Bace Constrotech LLP | P52100079826 | 27 Mar 2025 | 30 Dec 2027 | — | Not yet due | 0 |
| Sky Tree TowerKiran Buildcon | P52100078260 | 4 Dec 2024 | 31 Jan 2027 | — | Not yet due | 0 |
| Crystal TowerSantosh Kakasaheb Pathade | P52100078251 | 29 Nov 2024 | 31 May 2027 | — | Not yet due | 0 |
| Everest Phase 2J P Construction | P52100077451 | 16 Aug 2024 | 31 May 2027 | — | Not yet due | 0 |
| Skyview ParkKiran Buildcon | P52100076965 | 10 Jul 2024 | 31 Mar 2027 | — | Not yet due | 0 |
| Tilak B ZoneShivtilak Creations | P52100056213 | 22 May 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Sai SrushtiAshok Nirman Developers | P52100056155 | 16 May 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Anandam Phase IA V Bhat Developers LLP | P52100055818 | 22 Apr 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Konark ArcadeKonark Property & Developer | P52100055455 | 22 Mar 2024 | 31 May 2027 | — | Not yet due | 0 |
| RudrakshaAvantika Pownikar | P52100055171 | 5 Mar 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Yashvi GreensAkshay Baburao Waikar | P52100055020 | 26 Feb 2024 | 31 Mar 2026 | — | Promised date passed | 0 |
| Avighna HeightsAvighna Developers | P52100053719 | 22 Nov 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Guruta NakshatraSwami Developers | P52100052651 | 15 Sep 2023 | 31 Dec 2030 | — | Not yet due | 0 |
| AranyaNaiknavare Township LLP. | P52100052216 | 31 Jul 2023 | 31 Mar 2027 | — | Not yet due | 0 |
| EverestJawaleshwar Construction | P52100051215 | 8 Jun 2023 | 31 Mar 2026 | — | Promised date passed | 0 |
| Veer ShivanshVeershivansh Developers LLP | P52100051110 | 29 May 2023 | 31 Mar 2025 | — | Promised date passed | 0 |
| Aanant VastuOcean Developers | P52100050014 | 6 Mar 2023 | 31 Dec 2025 | — | Promised date passed | 0 |
| CrystalSaijyoti Developers | P52100049880 | 6 Mar 2023 | 31 Dec 2024 | — | Promised date passed | 0 |
| Gurudatta ResidencySamarth Developers And Pramoters | P52100049062 | 30 Jan 2023 | 30 Dec 2024 | 30 Nov 2025 | Extended 11 mo | 0 |
| Sahyadri ComplexLuxuriant Group | P52100048768 | 17 Jan 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Veer Chs Ltd.Aara Infraprojects | P52100048031 | 7 Dec 2022 | 31 Dec 2025 | — | Promised date passed | 0 |
| Surya HeightsSsb Developer | P52100047814 | 28 Nov 2022 | 31 Dec 2026 | — | Not yet due | 0 |
| Avasa Meadows TalegaonNaiknavare Township LLP | P52100047658 | 17 Nov 2022 | 31 Dec 2025 | — | Promised date passed | 0 |
| Residential Building on CTS No 107/1P -GIRIVAR RESIDENCYShrivar Builders LLP | P52100047061 | 29 Sep 2022 | 31 Dec 2026 | — | Not yet due | 0 |
| Iristo GoldM/s Iristo Developers llp | P52100046568 | 13 Aug 2022 | 31 Jan 2025 | 31 Jan 2026 | Extended 12 mo | 0 |
| Sahajanand CornerKacha Developers LLP | P52100046275 | 20 Jun 2022 | 31 Dec 2025 | — | Promised date passed | 0 |
| NilayaYUVVRAJ PAIGUDE proprietor of Vasundhara Buildcon | P52100045308 | 12 May 2022 | 31 Dec 2024 | 31 Mar 2027 | Extended 27 mo | 0 |
| Shivkrupa ComplexBharat Premchand Kothari | P52100034012 | 17 Mar 2022 | 31 Dec 2024 | — | Promised date passed | 0 |
| Samarth LakshmiSiddhesh Rajaram Dhore | P52100033115 | 9 Feb 2022 | 22 Dec 2023 | — | Promised date passed | 0 |
| PinnacleJawaleshwar Construction | P52100032446 | 4 Jan 2022 | 31 Dec 2023 | — | Promised date passed | 0 |
| Sai ApartmentsKevinn Construction | P52100031375 | 23 Oct 2021 | 15 Dec 2022 | 30 Jun 2025 | Extended 30 mo | 0 |
| Harmony ApartmentSwaroop Developers | P52100030399 | 20 Aug 2021 | 31 Mar 2024 | — | Promised date passed | 0 |
| Aaradhya ParkAkshay Balasaheb Kalokhe, Akshay Balasaheb Kalokhe | P52100030159, P52100048888 | 31 Jul 2021 | 31 Dec 2024 | — | Promised date passed | 0 |
| Sai Anirudha DhamSmw Builders And Developers | P52100028756 | 30 Mar 2021 | 30 Jun 2024 | 30 Jun 2025 | Extended 12 mo | 0 |
| MilestoneSantosh Kakasaheb Pathade | P52100028569 | 22 Mar 2021 | 30 Jun 2023 | — | Promised date passed | 0 |
| Morya AlphansoMorya Developers | P52100027324 | 2 Dec 2020 | 30 Jun 2023 | — | Promised date passed | 0 |
| Samarth VrundavanGanesh Uttamrao Bhegade | P52100026966 | 7 Nov 2020 | 23 Apr 2024 | — | Promised date passed | 0 |
| Kutumb BhoomiNaiknavare Buildcon Pvt Ltd | P52100026636 | 12 Oct 2020 | 30 Jun 2024 | — | Promised date passed | 0 |
| Ashirwad HomesBharat Premchand Kothari | P52100025081 | 18 Mar 2020 | 30 Mar 2023 | — | Promised date passed | 0 |
| Vastu SiddhiVastu Developers | P52100023521 | 18 Dec 2019 | 30 Dec 2023 | — | Promised date passed | 0 |
| Corner View ResidencyKacha Builders & Developers | P52100022330 | 16 Sep 2019 | 30 Dec 2021 | — | Promised date passed | 0 |
| 7AvenueHansraj Babruvan Jadhav | P52100022197 | 5 Sep 2019 | 25 Jul 2022 | — | Promised date passed | 0 |
| Akshay ResidencyAkshay Balasaheb Kalokhe | P52100021431 | 28 Jun 2019 | 30 Dec 2021 | — | Promised date passed | 0 |
| Bhakti AanganNirmiti Developers | P52100020919 | 23 May 2019 | 31 Dec 2028 | — | Not yet due | 0 |
| Ashtavinayak ResidencySuryoday Developers | P52100020740 | 8 May 2019 | 30 Mar 2023 | 29 Mar 2024 | Extended 12 mo | 0 |
| Samarth NabhanganSamarth Construction | P52100020565 | 26 Apr 2019 | 30 Mar 2024 | — | Promised date passed | 0 |
| Vardhaman GoldIntella Homes | P52100019944 | 15 Mar 2019 | 30 Jun 2021 | 30 Dec 2022 | Extended 18 mo | 0 |
| BrahmachaitanyaAvantika Shriniwas Pownikar | P52100018015 | 3 Oct 2018 | 31 Jan 2021 | 30 Dec 2021 | Extended 11 mo | 0 |
| Hanging GardenHariiharr Developers | P52100017512 | 23 Aug 2018 | 31 Dec 2019 | 30 Dec 2021 | Extended 24 mo | 0 |
| Vardhman SplendourIntella Homes | P52100017125 | 16 Jul 2018 | 30 Dec 2021 | — | Promised date passed | 0 |
| vastushilpDaksh Promoters And Devolopers | P52100017042 | 4 Jul 2018 | 31 Dec 2026 | — | Not yet due | 0 |
| Vardhman SplendourChrishh Holdings | P52100016943 | 22 Jun 2018 | 30 Dec 2021 | — | Promised date passed | 0 |
| Aditya Vardhan HeightsShree Ganesh Developers | P52100015460 | 27 Feb 2018 | 31 Dec 2019 | 31 Dec 2026 | Extended 84 mo | 0 |
| Kalpana ResidencyOm Shree Associates | P52100015322 | 15 Feb 2018 | 23 Dec 2022 | — | Promised date passed | 0 |
| Akshay AanganAkshay Properties | P52100014607 | 15 Dec 2017 | 29 Mar 2019 | — | Promised date passed | 0 |
| Mount VistaTirupati Lands and Building Constructions LLP | P52100014425 | 30 Nov 2017 | 30 Apr 2025 | 30 Oct 2025 | Extended 6 mo | 0 |
| Swami KrupaMeenal Prakash Rao | P52100012744 | 13 Nov 2017 | 31 Dec 2017 | — | Promised date passed | 0 |
| GrukrupaGurukrupa Associates | P52100013430 | 5 Oct 2017 | 1 Apr 2019 | — | Promised date passed | 0 |
| Silver TreasureMark Bulidcon | P52100013384, P52100013392 | 4 Oct 2017 | 30 Dec 2023 | 31 Mar 2026 | Extended 27 mo | 0 |
| Namo Panchratna ResidencyShital Samir Oswal | P52100013359 | 26 Sep 2017 | 30 Apr 2019 | 29 Oct 2020 | Extended 18 mo | 0 |
| VastupurtiUnity Spaces LLP | P52100013189 | 18 Sep 2017 | 31 Dec 2017 | — | Promised date passed | 0 |
| EmeraldAvantika Shriniwas Pownikar | P52100013091 | 14 Sep 2017 | 30 Nov 2019 | 28 Nov 2021 | Extended 24 mo | 0 |
| Global CityDivine Developers | P52100012401 | 1 Sep 2017 | 15 Jun 2021 | 30 Mar 2024 | Extended 33 mo | 0 |
| Samarth SrushtiSwami Samarth Developers | P52100012037 | 1 Sep 2017 | 30 May 2018 | — | Promised date passed | 0 |
| Vaishnavi - 2Varad Developers | P52100012398 | 1 Sep 2017 | 30 Jun 2018 | — | Promised date passed | 0 |
| Jadhav ComplexDisha Constructions | P52100010809 | 31 Aug 2017 | 31 Dec 2018 | — | Promised date passed | 0 |
| Jai GaneshVastushri construction | P52100011271 | 31 Aug 2017 | 30 Jun 2018 | 28 Jun 2019 | Extended 12 mo | 0 |
| Prathamesh ApartmentDisha Constructions | P52100011069 | 31 Aug 2017 | 31 Dec 2018 | — | Promised date passed | 0 |
| Shree Navnath ApartmentRaghu Bapuji Kude | P52100008550 | 19 Aug 2017 | 30 Sep 2018 | — | Promised date passed | 0 |
| Paradise HomesParadise Maker | P52100008042 | 18 Aug 2017 | 30 Dec 2021 | — | Promised date passed | 0 |
| Shubham SiddhiShubham Realtors | P52100008013 | 18 Aug 2017 | 31 Dec 2017 | — | Promised date passed | 0 |
| Papa ImperioAnup Bashani | P52100007015 | 17 Aug 2017 | 31 Dec 2019 | — | Promised date passed | 0 |
| Aayush ParadiseMorya Developers | P52100006957 | 16 Aug 2017 | 30 Oct 2018 | 30 Nov 2021 | Extended 37 mo | 0 |
| Samarth DhanvatikaSwami Samarth Developers | P52100005854 | 14 Aug 2017 | 31 May 2019 | — | Promised date passed | 0 |
| Spot 9Ramniklal Gopal Gangani | P52100006534 | 14 Aug 2017 | 31 Dec 2018 | — | Promised date passed | 0 |
| Phase I Vision RoyalleShubban Properties Vision Roiyalle | P52100005624 | 11 Aug 2017 | 31 Mar 2018 | — | Promised date passed | 0 |
| Sai DevelpoerSai Developers | P52100005487 | 11 Aug 2017 | 31 Dec 2017 | — | Promised date passed | 0 |
| Papa Mamta ResidencyAnup Bashani | P52100005206 | 10 Aug 2017 | 30 Jun 2019 | — | Promised date passed | 0 |
| Mahavirs NATURAMas Creations | P52100004246 | 9 Aug 2017 | 31 Dec 2018 | — | Promised date passed | 0 |
| Nisarga SparshArya Nisarga Properties | P52100004715 | 9 Aug 2017 | 30 Dec 2019 | — | Promised date passed | 0 |
| Nisarg VatikaM/s Shubh Ganesh Properties | P52100004252 | 9 Aug 2017 | 31 Jul 2019 | 30 Sep 2022 | Extended 38 mo | 0 |
| Devi CrestDevi Construction Co. | P52100003935 | 7 Aug 2017 | 25 Dec 2018 | 25 Dec 2019 | Extended 12 mo | 0 |
| Malhar ResidencyRanjeet Developers | P52100003817 | 6 Aug 2017 | 30 Dec 2019 | 31 Jan 2021 | Extended 13 mo | 0 |
Other localities in Mawal
- Talegaon Dabhade (M Cl)199 projects
- Talegaon Dabhade (R)96 projects
- Lonavala (M Cl)40 projects
- Kivale39 projects
- Varale38 projects
- Gahunje31 projects
- Somatane25 projects
- Urse12 projects
- Kanhe11 projects
- Chandkhed10 projects
- Jambhul10 projects
- Katavi10 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- Naiknavare Buildcon Pvt Ltd4 projects
- Jawaleshwar Construction3 projects
- Akshay Balasaheb Kalokhe2 projects
- Anup Bashani2 projects
- Avantika Shriniwas Pownikar2 projects
- Bharat Premchand Kothari2 projects
- Disha Constructions2 projects
- Intella Homes2 projects
- Kiran Buildcon2 projects
- Morya Developers2 projects
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology