RERA projects in Kanhe
11 projects under 11 MahaRERA registrations, registered 2017–2024. 55% have a completion date extended beyond the one promised.
11RERA projects
11Registrations
2Completion still due9 past their completion date
10 monthsMedian extension beyond promised date55% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 6 |
| 2018 | 3 |
| 2019 | 0 |
| 2020 | 0 |
| 2021 | 0 |
| 2022 | 0 |
| 2023 | 1 |
| 2024 | 1 |
Projects in Kanhe
11 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Saidham CitySanjaykumar Chandanmal Jain | P52100054568 | 31 Jan 2024 | 31 Dec 2024 | 30 Sep 2025 | Extended 9 mo | 0 |
| Namrata BreezioNamrata Developers | P52100052230 | 31 Jul 2023 | 30 Jun 2025 | — | Promised date passed | 0 |
| Spot OneShrikrishna Realty | P52100017674 | 4 Sep 2018 | 31 Jul 2029 | — | Not yet due | 0 |
| Eco Valley PlusNamrata Jalan Ventures | P52100016509 | 18 May 2018 | 30 Apr 2022 | 30 Sep 2022 | Extended 5 mo | 0 |
| Sai Samarth ResidencyShree Mahalaxmi Developers | P52100015205 | 7 Feb 2018 | 31 Mar 2027 | — | Not yet due | 0 |
| 9 Luxure EstatesSVB Realty Pvt Ltd | P52100014314 | 20 Nov 2017 | 9 Nov 2019 | 8 Nov 2021 | Extended 24 mo | 0 |
| Yash ResidencyDnyandeo Bapu Katkar | P52100014309 | 20 Nov 2017 | 1 Nov 2022 | — | Promised date passed | 0 |
| Osian LifeLands 1Prime Realty | P52100009363 | 22 Aug 2017 | 31 Jul 2018 | 31 Jul 2019 | Extended 12 mo | 0 |
| Osian LifeLands 2Planet-i Realty | P52100005088 | 9 Aug 2017 | 31 Jul 2018 | 31 Jan 2019 | Extended 6 mo | 0 |
| CollinaBharucha & Sons Realtors & Developers Pvt Ltd | P52100002704 | 2 Aug 2017 | 30 Mar 2022 | — | Promised date passed | 0 |
| Akshay City A And B BuildingRajendra Ramanlal Lunakd | P52100002357 | 31 Jul 2017 | 31 May 2019 | 30 Nov 2020 | Extended 18 mo | 0 |
Other localities in Mawal
- Talegaon Dabhade (M Cl)199 projects
- Wadagaon (Ct)111 projects
- Talegaon Dabhade (R)96 projects
- Lonavala (M Cl)40 projects
- Kivale39 projects
- Varale38 projects
- Gahunje31 projects
- Somatane25 projects
- Urse12 projects
- Chandkhed10 projects
- Jambhul10 projects
- Katavi10 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- Bharucha & Sons Realtors & Developers Pvt Ltd1 project
- Dnyandeo Bapu Katkar1 project
- Namrata Developers1 project
- Namrata Jalan Ventures1 project
- Planet-i Realty1 project
- Prime Realty1 project
- Rajendra Ramanlal Lunakd1 project
- Sanjaykumar Chandanmal Jain1 project
- Shree Mahalaxmi Developers1 project
- Shrikrishna Realty1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology