8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects13
Registrations16some projects hold several
Completion still due124 past their date
Median extension4 months56% of registrations extended
Regulatory cases0none on MahaRERA's lists

8 in 10 registrations run late here

16 MahaRERA registrations in Urse

3 not yet due9 extended, not yet due4 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Urse

13 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Woodshire Phase 2GUDDWILL RVN Land VenturesDue Apr 2027——
Phase INitin Govind SableDue Mar 2027——
Vaarivana Phase B-2Sanjivani Integrated Township LLPDue Dec 2028, extended 4 mo——
Zen-DaleElite Promoters and BuildersDue Jul 2027, extended 4 mo——
Vaarivana Cove Essential Shopping-2Sanjivani Integrated Township LLPDue Aug 2027, extended 4 mo——
All 13 projects →
Urse market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Sanjivani Integrated Township LLP7 projects
  2. GUDDWILL RVN Land Ventures2 projects
  3. Balasaheb Chaburao Dhamankar1 project
  4. Elite Promoters And Builders1 project
  5. Nitin Govind Sable1 project
  6. Ramdas Chaburao Dhamankar1 project

Urse, in questions

How many projects in Urse run late?

8 in 10 MahaRERA registrations (13 of 16): their completion date was extended or has passed, data through 27 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Urse by Deedo. Medians on fewer than 3 deeds are not shown.

Data through27 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology