Zen-Dale
Deedo IDDP-PUN-FJWHCompletion was pushed back 4 months, to Jul 2027; no MahaRERA orders on record.
Urse, Pune 410506 · by Elite Promoters And Builders
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Jul 2027
- This projectRegistered 20 Aug 2024, completion promised 31 Mar 2027, revised to 31 Jul 2027.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100077518
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100077518 | 20 Aug 2024 | 31 Mar 2027 | 31 Jul 2027 | Elite Promoters and Builders | Project page |
Documents35
1 document held by Deedo, 34 filings listed on MahaRERA's project page
Finance
- PAN CardPAN Card.pdf · uploaded 29 Jun 2024Source
Legal
Migrated
- 1 PAN CardPAN Card.pdf · uploaded 29 Jun 2024Source
- 1 Copy of the legal title reportTitle Search Report Annexure.pdf · uploaded 29 Jun 2024Source
- 1 a Details of encumbrances concerned to FinanceEncumbrance Certificate.pdf · uploaded 29 Jun 2024Source
- 1 b Details of encumbrances concerned to LegalEncumbrance Certificate.pdf · uploaded 29 Jun 2024Source
Show all 35 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 29 Jun 2024Source
- 1 Building Plan Approval / NA Order for plotted developmentLayout.pdf · uploaded 29 Jun 2024Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 29 Jun 2024Source
- 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 29 Jun 2024Source
- 1 Declaration in FORM BForm B.pdf · uploaded 29 Jun 2024Source
- 1 CERSAI detailsCERSAI Declaration.pdf · uploaded 29 Jun 2024Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest.pdf · uploaded 29 Jun 2024Source
- 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 29 Jun 2024Source
- 1 Proforma of Agreement for saleDraft Agreement.pdf · uploaded 29 Jun 2024Source
- 1 Deviation Report with respect to Allotment letterDeviation Report - Allotment Letter.pdf · uploaded 29 Jun 2024Source
- 1 Deviation Report with respect to model copy of AgreementDeviation Report - Agreement.pdf · uploaded 29 Jun 2024Source
- 1 Other – TechnicalAnnexure A.pdf · uploaded 29 Jun 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 9 Jul 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Encumbrance Certificate.pdf · uploaded 10 Jul 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 10 Jul 2024Source
- 1 Disclosure for secured/unsecured finance availed for the projectDisclosure of Finances.pdf · uploaded 24 Jul 2024Source
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Bank Letter.pdf · uploaded 7 Aug 2024Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)Declaration of Designated Bank Accounts.pdf · uploaded 8 Aug 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 21 Mar 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 21 Mar 2025Source
Technical
Technical (Architect)
Technical (Engineer)
- DocumentForm 2.pdf · uploaded 10 Jul 2024Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 244, 245
As registered with MahaRERA and published on its project page
- Project type
- Plotted
- Status on MahaRERA
- Certificate Signed
- Address
- Gat No. 226, 244, 245 & 246, Urse, UrsePIN 410506
- Village
- Urse, Mawal taluka
- Land area for this project
- 40,560 sq m (4,36,584 sq ft)
- Permissible built-up area
- 20,000 sq m (2,15,278 sq ft)
- Sanctioned built-up area
- 0 sq m (0 sq ft)
- Recreational open space
- 4,042 sq m (43,509 sq ft)
- Designated bank account
- 82
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Gat No. 226, 244, 245 & 246
Boundaries
- North
- By Gat No 240 and 248
- South
- By Gat No 227 and 228
- East
- By Gat No 242 and 243
- West
- By Gat No 225
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Milind Patil | — |
| Chartered accountant | CA Rohan M Khustale | — |
| Engineer | Sachin Patil | — |
Source: MahaRERA project page. Contact details are not shown.