10 projects under 12 MahaRERA registrations, registered 2018–2026. 8% have a completion date extended beyond the one promised.
10RERA projects
12Registrationssome projects hold several
7Completion still due5 past their completion date
12 monthsMedian extension beyond promised date8% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2018 | 1 |
| 2019 | 2 |
| 2020 | 0 |
| 2021 | 1 |
| 2022 | 1 |
| 2023 | 2 |
| 2024 | 1 |
| 2025 | 0 |
| 2026 | 4 |
Projects in Chandkhed
10 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Belmont ReserveEden Real Projects LLP | PP1260002602048, PP1260002602151 | 24 Sep 2026 | 31 Dec 2031 | — | Not yet due | 0 |
| Belmont Reserve Phase 3Eden Real Projects LLP | PP1260002601975 | 21 Sep 2026 | 31 Dec 2031 | — | Not yet due | 0 |
| Belmont Reserve Phase 5Eden Real Projects LLP | PP1260002601939 | 16 Sep 2026 | 31 Dec 2031 | — | Not yet due | 0 |
| OmkaraShree Dattaguru Builders And Developers | P52100077487 | 20 Aug 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Sai HeightsGuddwill Homes | P52100054043 | 27 Dec 2023 | 30 Jun 2027 | — | Not yet due | 0 |
| Sai Vatika - JuiAbhilasha Developers | P52100047197 | 11 Oct 2022 | 31 Dec 2024 | — | Promised date passed | 0 |
| Sai Vatika - ParijatAbhilasha Developers | P52100030300 | 15 Aug 2021 | 31 Dec 2022 | 31 Dec 2023 | Extended 12 mo | 0 |
| KingstownRaga Developers | P52100023079 | 29 Nov 2019 | 30 Mar 2025 | — | Promised date passed | 0 |
| Sai VatikaAbhilasha Developers | P52100022735, P52100052605 | 16 Oct 2019 | 31 Dec 2026 | — | Not yet due | 0 |
| 46 Banyan Tree - IChankhed Properties LLP | P52100018777 | 4 Dec 2018 | 30 Dec 2022 | — | Promised date passed | 0 |
Other localities in Mawal
- Talegaon Dabhade (M Cl)199 projects
- Wadagaon (Ct)111 projects
- Talegaon Dabhade (R)96 projects
- Lonavala (M Cl)40 projects
- Kivale39 projects
- Varale38 projects
- Gahunje31 projects
- Somatane25 projects
- Urse12 projects
- Kanhe11 projects
- Jambhul10 projects
- Katavi10 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- Abhilasha Developers3 projects
- Eden Real Projects LLP3 projects
- Chankhed Properties LLP1 project
- Guddwill Homes1 project
- Raga Developers1 project
- Shree Dattaguru Builders And Developers1 project