Lonavala (M Cl), Pune
Deedo IDDL-PUN-LONAVALA9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects40
Registrations49some projects hold several
Completion still due1633 past their date
Median extension4 months39% of registrations extended
Regulatory cases8on 1 project
9 in 10 registrations run late here
49 MahaRERA registrations in Lonavala (M Cl)
4 not yet due12 extended, not yet due33 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Lonavala (M Cl)
40 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Girnar ResidencyDivyayasha Builders Promoters And Developers | Due Dec 2028 | — | — |
| RaindropSadguru Developers | Due Apr 2027, extended 4 mo | — | — |
| Golan HeightsDivyayasha Builders, Promoters And Developers | Due Oct 2027, extended 4 mo | — | — |
| One LonvalaHoly Valley Lifescapes Private Limited | Due Dec 2026, extended 4 mo | — | — |
| Bliss EstatesBenjamin Michael Manuel | Due Apr 2027, extended 4 mo | — | — |
Nearby: other municipal areas in Mawal
Most active promoters
- Divyayasha Builders, Promoters And Developers6 projects
- Jitu Properties & Developments Pvt Ltd3 projects
- Elhanan Buildstruct Llp2 projects
- Neel Buildcon2 projects
- Truewin Realty Limited2 projects
- Ankush Narayan Chaudhari1 project
- Aps Developers1 project
- Ashapura And Ratan Developers1 project
- Benjamin Michael Manuel1 project
- Efficient Properties1 project
Lonavala (M Cl), in questions
How many projects in Lonavala (M Cl) run late?
9 in 10 MahaRERA registrations (45 of 49): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Lonavala (M Cl) by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology