Jambhul, Pune

Deedo IDDL-PUN-JAMBHUL

6 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects10
Registrations14some projects hold several
Completion still due212 past their date
Median extension12 months64% of registrations extended
Regulatory cases1on 1 project
Jambhul market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

10 in 10 registrations run late here

14 MahaRERA registrations in Jambhul

2 extended, not yet due12 past even the latest date

Extended registrations moved their completion date by a median of 12 months.

Projects in Jambhul

10 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Land of DreamsKrisala Buildscape LLPDue Jan 2029, extended 4 mo——
Osian Lifelands GrandeM/s Prime RealtyDue Apr 2027, extended 4 mo——
Presidential Park Phase 1Oneness Realtors1 yr 10 mo late——
Phase III Vision ShreeShubban Properties Vision Shree7 yrs 10 mo late—98%
Phase I Vision CityShubban Properties Vision City7 yrs 10 mo late—91%
Vision WoodsShubban Realtors8 yrs 7 mo late—79%
AnantsrishtiLandscape Reality4 yrs 4 mo late—49%
Elite Green AcresSunita Gajendra Patil6 yrs 10 mo late—86%
Saarrthi SwadeshSiddharth Properties8 yrs 1 mo late—92%
Xrbia AbodeXrbia Abode Developers Private Limited4 yrs 7 mo late—84%

Most active promoters

  1. Krisala Buildscape LLP1 project
  2. Landscape Reality1 project
  3. M/s Prime Realty1 project
  4. Oneness Realtors1 project
  5. Shubban Properties Vision City1 project
  6. Shubban Properties Vision Shree1 project
  7. Shubban Realtors1 project
  8. Siddharth Properties1 project
  9. Sunita Gajendra Patil1 project
  10. Xrbia Abode Developers Private Limited1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology