Katavi, Pune
Deedo IDDL-PUN-KATAVI8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects10
Registrations13some projects hold several
Completion still due310 past their date
Median extension18 months8% of registrations extended
Regulatory cases1on 1 project
8 in 10 registrations run late here
13 MahaRERA registrations in Katavi
3 not yet due10 past even the latest date
Extended registrations moved their completion date by a median of 18 months.
Projects in Katavi
10 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Urban NestGM Ventures | Due Dec 2030 | — | — |
| Riddhi HeightsV4 Enterprises | Due Jun 2029 | — | — |
| Prospera ParadiseK B D Realty | Due Dec 2028 | — | — |
| Prospera Palms SapphireK B Developers & Associates | 3 yrs 5 mo late | — | — |
| Prospera Palms PearlK B D Realty | 3 yrs 5 mo late | — | — |
Nearby: other localities in Mawal
Most active promoters
- K B D Realty3 projects
- K B Developers & Associates2 projects
- Earnest And Shah Ventures1 project
- GM Ventures1 project
- Kakade Vtp Associates1 project
- V4 Enterprises1 project
- Vascon Engineers Ltd1 project
Katavi, in questions
How many projects in Katavi run late?
8 in 10 MahaRERA registrations (10 of 13): their completion date was extended or has passed, data through 7 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Katavi by Deedo. Medians on fewer than 3 deeds are not shown.
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology