Skip to content

Charholi, Pune

Deedo IDDL-PUN-CHARHOLI

9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects171
Registrations183some projects hold several
Completion still due53130 past their date
Median extension4 months34% of registrations extended
Regulatory cases0none on MahaRERA's lists

0 deeds a month, 0% of them rentals

Registered sales and rentals, the 24 months to November 2026

Registered sales and rentals by month
MonthSalesRentals
December 202400
January 202500
February 202500
March 202500
April 202500
May 202500
June 202500
July 202500
August 202500
September 202500
October 202500
November 202500
December 202500
January 202600
February 202600
March 202600
April 202600
May 202600
June 202600
July 202600
August 202600
September 202600
October 202600
November 202610

1 sale and 0 rentals in the last 12 months · Source: IGR Maharashtra Index II, registered sale and leave-and-licence deeds

9 in 10 registrations run late here

183 MahaRERA registrations in Charholi

16 not yet due37 extended, not yet due130 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Charholi

171 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Veridian ParkPlatinum BuildersDue Dec 2028——
Destination 24 Avenue D BuildingD R Gavhane Landmarks LLPDue Sep 2027——
Mountain JewelGVMG DevelopersDue Apr 2029, extended 4 mo——
Tanish MeridianTanish PropertiesDue Apr 2031, extended 4 mo——
Bestate AxisBestate Commercial Development CompanyDue Aug 2028, extended 4 mo——
All 171 projects →
Charholi market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Pride Builders Llp9 projects
  2. D R Gavhane Landmarks Llp6 projects
  3. Charholi Infrastructure Llp3 projects
  4. Diamond Nexus Associates3 projects
  5. Jaikul Associates3 projects
  6. Sai Tirupati Properties3 projects
  7. Sam Developers3 projects
  8. Aakar Realties2 projects
  9. Avani Corp2 projects
  10. Chaitanya Buildcon2 projects

Charholi, in questions

How many projects in Charholi run late?

9 in 10 MahaRERA registrations (167 of 183): their completion date was extended or has passed, data through 22 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Charholi by Deedo. Medians on fewer than 3 deeds are not shown.

Latest deal · Primary sale · Apr 2026

₹25–50 L

Data through20 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology