Grace Avenue
Deedo IDDP-PUN-0MEECompletion was pushed back 1 year and 6 months to Sep 2026, and that date has passed too; no MahaRERA orders on record; 13% of its units are booked.
Baner, Pune 411045 · Property rates in Baner · by Trimurthy Narayan
Buying a flat here?
See every deed registered on it.
Completion was pushed back 1 year and 6 months to Sep 2026, and that date has passed too
- This projectRegistered 5 Jun 2024, completion promised 31 Mar 2025, revised to 30 Sep 2026, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
- Rental · 60 mo · Aug 2026
- Primary sale · Jul 2026
- Primary sale · Jul 2026
- Rental · 33 mo · Aug 2024
- Primary sale · Jul 2024
- Primary sale · Jul 2024
| Month | Flat | Kind | Area | Price | Record |
|---|---|---|---|---|---|
| Aug 2026 | Unit 401 | Rental | — | View Rental, Aug 2026 | |
| Jul 2026 | Unit 404 | Primary sale | 591 sq ft | View Primary sale, Jul 2026 | |
| Jul 2026 | Unit 401 | Primary sale | 849 sq ft | View Primary sale, Jul 2026 | |
| Aug 2024 | Not on record | Rental | — | View Rental, Aug 2024 | |
| Jul 2024 | Unit 102 | Primary sale | 849 sq ft | View Primary sale, Jul 2024 | |
| Jul 2024 | Unit 103 | Primary sale | 591 sq ft | View Primary sale, Jul 2024 |
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page. Construction % is the average of the developer's own declared activity progress to MahaRERA, not an inspection.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100066459
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100066459 | 5 Jun 2024 | 31 Mar 2025 | 30 Sep 2026 | Trimurthy Narayan | Project page |
Documents66
20 documents held by Deedo, 46 filings listed on MahaRERA's project page
Show all 66 documentsShow fewer documents
Other (9)
Document library
- Copy of the legal title reportTitle Report.pdf · uploaded 2 Mar 2024View
- a Details of encumbrances concerned to FinanceFIn Enc_20240302_0001.pdf · uploaded 2 Mar 2024View
- b Details of encumbrances concerned to LegalFIn Enc_20240302_0001.pdf · uploaded 2 Mar 2024View
- Copy of Layout Approval (in case of layout)Plan Blue Print_compressed.pdf · uploaded 2 Mar 2024View
- Building Plan Approval / NA Order for plotted developmentPlan Blue Print_compressed.pdf · uploaded 2 Mar 2024View
- Commencement Certificates / NA Order for plotted developmentcommencement Certificate.pdf · uploaded 2 Mar 2024View
- Commencement Certificates / NA Order for plotted developmentNA_order.pdf · uploaded 2 Mar 2024View
- Declaration about Commencement CertificateFormat D Decl Commencement Certificate.pdf · uploaded 2 Mar 2024View
- Declaration in FORM BDeclaration Form B_20240302_0001.pdf · uploaded 2 Mar 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect cer_20240302_0001.pdf · uploaded 2 Mar 2024View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate.pdf · uploaded 2 Mar 2024View
- Disclosure of sold/ booked inventoryDisclosure of Inventory Sold Unsold.pdf · uploaded 2 Mar 2024View
- Disclosure of Interest in Other Real Estate OrganizationsDisclosure Interest in other project.pdf · uploaded 2 Mar 2024View
- Proforma of Allotment letterAllotment Letter.pdf · uploaded 2 Mar 2024View
- Deviation Report with respect to Allotment letterDeviation Allotment Letter.pdf · uploaded 2 Mar 2024View
- Other – TechnicalAnnexure A.pdf · uploaded 11 Mar 2024View
- Other – FinanceFIn Enc_20240302_0001.pdf · uploaded 11 Mar 2024View
- CERSAI detailsCersai Report.pdf · uploaded 11 Mar 2024View
- Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSeparate Account Declaration.pdf · uploaded 11 Mar 2024View
- Proforma of Agreement for saleAFS 20-05-2024.pdf · uploaded 20 May 2024View
- Deviation Report with respect to model copy of AgreementReport Deviation (Agreement).pdf · uploaded 20 May 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1.PDF · uploaded 27 Mar 2025View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)Form2.PDF · uploaded 27 Mar 2025View
- Disclosure of sold/ booked inventorySold Unsold.pdf · uploaded 27 Mar 2025View
- Form 1Form 1 - Grace Avenue as on Dec 2025.pdf · uploaded 25 Apr 2026View
- Form 2Form 2 - Grace Avenue as on Dec 2025.pdf · uploaded 25 Apr 2026View
- Disclosure of Sold and Booked InventoryCircular 29 - Grace Avenue as on June 2025.pdf · uploaded 25 Apr 2026View
- Form 1Form 1 - Grace Avenue as on Dec 2025.pdf · uploaded 25 Apr 2026View
- Form 2Form 2 - Grace Avenue as on Dec 2025.pdf · uploaded 25 Apr 2026View
- Disclosure of Sold and Booked InventoryCircular 29 - Grace Avenue as on Dec 2025.pdf · uploaded 25 Apr 2026View
- Form 1Form 1 - Grace Avenue as on Dec 2025.pdf · uploaded 25 Apr 2026View
- Form 2Form 2 - Grace Avenue as on Dec 2025.pdf · uploaded 25 Apr 2026View
- Disclosure of Sold and Booked InventoryCircular 29 - Grace Avenue as on Dec 2025.pdf · uploaded 25 Apr 2026View
- Form 5 (FY 2024-2025)Form 5 Grace Avenue For FY 2024-25.pdf · uploaded 9 Jun 2026View
- Form 1Form 1 as on March 2026.pdf · uploaded 24 Sep 2026View
- Form 2Form 2 as on March 2026.pdf · uploaded 24 Sep 2026View
- Disclosure of Sold and Booked InventoryCircular 29 as on March 2026.pdf · uploaded 24 Sep 2026View
- Form 1Form 1 as on June 2026.pdf · uploaded 24 Sep 2026View
- Form 2Form 2 as on June 2026.pdf · uploaded 24 Sep 2026View
- Disclosure of Sold and Booked InventoryCircular 29 as on June 2026.pdf · uploaded 24 Sep 2026View
Promoter documents
Technical documents
Financial documents
- Other – FinanceFIn Enc_20240302_0001.pdf · uploaded 11 Mar 2024View
Proforma allotment letter
- Proforma allotment letterAllotment Letter.pdfView
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsSurvey 123/3, Survey Number 123/3 · Pune Municipal Corporation
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Active
- Unit types
- Living Room Kitchen16 units in all
- Address
- Survey Number 123/3, Baner Mahalunge Road, BanerPIN 411045
- Village
- Baner, Haveli taluka
- Location
- 18.56463, 73.77824
- Land area for this project
- 700 sq m (7,535 sq ft)
- Permissible built-up area
- 1,232 sq m (13,261 sq ft)
- Sanctioned built-up area
- 1,232 sq m (13,261 sq ft)
- Planning authority
- Pune Municipal Corporation
- Designated bank account
- Idbi Bank
- Litigation declared by promoter
- None declared
- Financial encumbrance declared
- None declared
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Survey Number 123/3
Boundaries
- North
- Private Layout Plot No 7
- South
- Private Layout Plot No 3
- East
- Internal Road
- West
- Survey No 22
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking16 units · 25 parking spaces
16 units registered
| Type | Carpet area | Units |
|---|---|---|
| Living Room Kitchen | 54.9 sq m · 591 sq ft | 8 |
| Living Room Kitchen | 78.85 sq m · 849 sq ft | 8 |
Parking
| Type | Two-wheeler | Four-wheeler | Bus | Visitor | Total |
|---|---|---|---|---|---|
| Closed/Covered | 0 | 0 | 0 | 0 | 25 |
| Open Space | 0 | 0 | 0 | 0 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Construction progress2 buildings and areas
Work completed, as the promoter reported it to MahaRERA (Form 1)
Residential
Show all 11 activitiesShow fewer activities
Common areas and amenities
Show all 15 activitiesShow fewer activities
Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.
Professionals7
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Shailesh Patil | — |
| Chartered accountant | N B Sayed & Associates | — |
| Chartered accountant | Rohit Gadsing & Co | — |
| Chartered accountant | Rutuja Narsingh & Associates | — |
| Engineer | Sandip Rangdal | — |
| Engineer | S K Consultants & Engineers | — |
| Other | Grace Infra | — |
Source: MahaRERA project page. Contact details are not shown.
Grace Avenue in numbers
Registered deals, summarised
Deedo has 6 registered documents at Grace Avenue, from Jul 2024 to Aug 2026: 4 sales, 2 leave and licence agreements. The median registered sale since Jul 2024 works out to about ₹10,600 per sq ft, at a median of ₹76 L a deal; 0% of sales were resales.
- What is the price per sq ft at Grace Avenue?
- The median registered sale since Jul 2024 works out to about ₹10,600 per sq ft, at a median of ₹76 L a deal; 0% of sales were resales.
- How many properties have been sold at Grace Avenue?
- 4 sales are registered at Grace Avenue.
- Are properties at Grace Avenue rented out?
- Yes: 2 leave and licence agreements are registered at Grace Avenue.
- Where does this data come from?
- The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at Grace Avenue by Deedo, last updated with deals registered in Aug 2026.
Latest deal · Rental · Aug 2026
₹20–50k / month