RERA projects in Shikrapur
33 projects under 34 MahaRERA registrations, registered 2017–2026. 18% have a completion date extended beyond the one promised.
33RERA projects
34Registrationssome projects hold several
14Completion still due20 past their completion date
27 monthsMedian extension beyond promised date18% of registrations extended
0Regulatory casesnone on MahaRERA's lists
2Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 14 |
| 2018 | 5 |
| 2019 | 0 |
| 2020 | 2 |
| 2021 | 2 |
| 2022 | 2 |
| 2023 | 6 |
| 2024 | 1 |
| 2025 | 1 |
| 2026 | 1 |
Projects in Shikrapur
33 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Ekdant PlazaShree Developers And Builders | PR1260002602066 | 1 Oct 2026 | 30 Jun 2028 | — | Not yet due | 0 |
| Shivsrushti Market-1Saishraddha Developers and Builders | PC1260002500355 | 24 Jul 2025 | 31 Dec 2029 | — | Not yet due | 0 |
| DnyaneshwarWinstar Infra | P52100055863 | 23 Apr 2024 | 31 Mar 2027 | — | Not yet due | 0 |
| Garden CitySubhaj Construction And Developments LLP | P52100052761 | 22 Sep 2023 | 31 Oct 2028 | — | Not yet due | 0 |
| Kamal BaugSaptarshi Buildcon | P52100052708 | 22 Sep 2023 | 31 Dec 2030 | — | Not yet due | 0 |
| Eco Gram Phase 3Shri Siddhivinayak Builders | P52100052248 | 2 Aug 2023 | 31 Dec 2028 | — | Not yet due | 0 |
| Sai ZionSai Builtcon | P52100050738 | 28 Apr 2023 | 31 Mar 2028 | — | Not yet due | 0 |
| Shikrapur Business MarketSharad Laxman Bangar | P52100050261 | 27 Mar 2023 | 31 May 2027 | — | Not yet due | 0 |
| Vindhya HeightsMhalsakant Properties | P52100049521 | 15 Feb 2023 | 27 Dec 2027 | — | Not yet due | 0 |
| NandanWinstar Infra | P52100046468 | 4 Aug 2022 | 31 Mar 2025 | — | Promised date passed | 0 |
| Abhilasha Wing A And Wing BM/S Kudale Sable Builders | P52100032361 | 29 Dec 2021 | 31 Dec 2026 | — | Not yet due | 0 |
| shikrapur Trade CentrePride landmarks | P52100031674, P52100047205 | 3 Nov 2021 | 1 Sep 2025 | — | Promised date passed | 0 |
| Rajvardhan Shopping CentreBhauso Kisan Langhe | P52100026639 | 12 Oct 2020 | 30 Jun 2023 | 29 Jun 2024 | Extended 12 mo | 0 |
| EcoviharSiddhesh Ramchandra Bangar | P52100026385 | 16 Sep 2020 | 23 Mar 2025 | — | Promised date passed | 0 |
| Vrundavan ParkShree Saishraddha Developers & Builders | P52100018019 | 3 Oct 2018 | 17 Sep 2021 | 17 Mar 2023 | Extended 18 mo | 0 |
| Eco Villas IISaptarshi Properties | P52100016979 | 26 Jun 2018 | 30 Apr 2019 | — | Promised date passed | 0 |
| Green Nest ResidencySharad Laxman Bangar | P52100016896 | 22 Jun 2018 | 30 May 2024 | — | Promised date passed | 0 |
| Maitri GoldMaitri Developers And Builders | P52100016857 | 20 Jun 2018 | 31 Dec 2026 | — | Not yet due | 0 |
| Eco VillasSaptarshi Properties | P52100015574 | 8 Mar 2018 | 31 Aug 2018 | — | Promised date passed | 0 |
| Dew DropsGreen Homes | P52100001436 | 13 Nov 2017 | 31 Dec 2017 | — | Promised date passed | 0 |
| AbhilashaKudale Sable Builders | P52100008268 | 18 Aug 2017 | 30 Nov 2020 | 30 May 2022 | Extended 18 mo | 0 |
| HarmonyNandakumar Lapalikar | P52100007996 | 18 Aug 2017 | 30 Dec 2026 | — | Not yet due | 0 |
| Triaa PrincetownTriaa Infracon LLP | P52100007683 | 17 Aug 2017 | 1 Aug 2022 | — | Promised date passed | 0 |
| EcogramShri Siddhivinayak Builders | P52100005900 | 14 Aug 2017 | 31 Mar 2018 | — | Promised date passed | 0 |
| SAMARPIT CITY - A1 and A2Sadguru Constructions | P52100005177 | 10 Aug 2017 | 31 Dec 2019 | 31 Dec 2023 | Extended 48 mo | 0 |
| AmrutkalashAmrutkalash Properties | P52100004921 | 9 Aug 2017 | 31 Dec 2027 | — | Not yet due | 0 |
| EcogramShri Siddhivinayak Builders | P52100004669 | 9 Aug 2017 | 31 Mar 2018 | — | Promised date passed | 0 |
| Aura City D3,D4Bhagvati infra | P52100004141 | 8 Aug 2017 | 31 Oct 2018 | — | Promised date passed | 0 |
| Lilium Phase IIAmol Shirish Jakate | P52100003808 | 6 Aug 2017 | 30 Dec 2022 | 31 Dec 2028 | Extended 72 mo | 0 |
| Pancharatna GulmoharPancharatna Developers And Builders | P52100003840 | 6 Aug 2017 | 30 Dec 2021 | 31 Dec 2024 | Extended 36 mo | 0 |
| Aura City D5,D6Bhagvati infra | P52100003585 | 5 Aug 2017 | 31 Oct 2018 | — | Promised date passed | 0 |
| Aura City D11,D12Bhagvati infra | P52100003048 | 4 Aug 2017 | 31 Aug 2018 | — | Promised date passed | 0 |
| Aura City D1,D2Bhagvati infra | P52100003069 | 4 Aug 2017 | 31 Aug 2018 | — | Promised date passed | 0 |
Other localities in Shirur
- Shirur53 projects
- Shirur Gramin21 projects
- Talegaon Dhamdhere17 projects
- Dingrajwadi4 projects
- Koregaon Bhima (Ct)4 projects
- Ranjangaon Ganpati3 projects
- Karegaon2 projects
- Saradwadi2 projects
- Wadhu Bk.2 projects
- Babhulsar Kh.1 project
- Hivare1 project
- Kohakdewadi1 project
Most active promoters
By projects registered here, as named on MahaRERA.
- Bhagvati infra4 projects
- Shri Siddhivinayak Builders3 projects
- Saptarshi Properties2 projects
- Sharad Laxman Bangar2 projects
- Winstar Infra2 projects
- Amol Shirish Jakate1 project
- Amrutkalash Properties1 project
- Bhauso Kisan Langhe1 project
- Green Homes1 project
- Kudale Sable Builders1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology