9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects54
Registrations56some projects hold several
Completion still due3125 past their date
Median extension4 months52% of registrations extended
Regulatory cases1on 1 project

9 in 10 registrations run late here

56 MahaRERA registrations in Shirur

4 not yet due27 extended, not yet due25 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Shirur

54 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Shantivan Homes Phase 6Nikhil Jayavant DangeDue Sep 2027——
Rayat RegencySoham Constructions And DevelopersDue Aug 2030——
Star Gold PropertiesPerfect BuildersDue Apr 2029, extended 4 mo——
24 Aanand P2BJ ConstructionsDue Aug 2030, extended 4 mo——
24 Aanand P1BJ ConstructionsDue Feb 2029, extended 4 mo——
All 54 projects →
Shirur market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. BJ Constructions2 projects
  2. Mahendra D Phulfagar2 projects
  3. Nikhil Machhindra Raut2 projects
  4. S K Associates2 projects
  5. Soham Constructions And Developers2 projects
  6. Success Land Developers2 projects
  7. Aditya Corporate1 project
  8. A S Properties1 project
  9. Bhujbal Buildcon1 project
  10. Bora Developers1 project

Shirur, in questions

How many projects in Shirur run late?

9 in 10 MahaRERA registrations (52 of 56): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Shirur by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology