10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects19
Registrations19
Completion still due613 past their date
Median extension12 months58% of registrations extended
Regulatory cases0none on MahaRERA's lists

10 in 10 registrations run late here

19 MahaRERA registrations in Talegaon Dhamdhere

1 not yet due5 extended, not yet due13 past even the latest date

Extended registrations moved their completion date by a median of 12 months.

Projects in Talegaon Dhamdhere

19 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Sharanya ComplexSharanya ConstructionsDue Aug 2028, extended 4 mo——
Rustic MeadowsSanjay Gopichand JasujaDue Apr 2027, extended 4 mo——
Maitri VishwaVishwa Landmarks LLPDue Apr 2031, extended 4 mo——
Shreenath Market CityOzone InfrastructureDue Apr 2029, extended 4 mo—7%
Adinath ShrushtiAdinath Realty3 mo late—10%
All 19 projects →
Talegaon Dhamdhere market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Primary Housing Corporation Llp2 projects
  2. Sharanya Constructions2 projects
  3. Vishal Constructions2 projects
  4. Abhaydev Developers1 project
  5. Adinath Realty1 project
  6. Akash Enterprises1 project
  7. Arm Engineers1 project
  8. Chandra Reality1 project
  9. K K Buildcon Amenity And A Building1 project
  10. Maple City Developers1 project

Talegaon Dhamdhere, in questions

How many projects in Talegaon Dhamdhere run late?

10 in 10 MahaRERA registrations (18 of 19): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Talegaon Dhamdhere by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology