22 projects under 22 MahaRERA registrations, registered 2017–2026. 41% have a completion date extended beyond the one promised.
Locality
22RERA projects
22Registrations
7Completion still due15 past their completion date
24 monthsMedian extension beyond promised date41% of registrations extended
0Regulatory casesnone on MahaRERA's lists
27Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 7 |
| 2018 | 1 |
| 2019 | 2 |
| 2020 | 2 |
| 2021 | 2 |
| 2022 | 0 |
| 2023 | 1 |
| 2024 | 2 |
| 2025 | 1 |
| 2026 | 4 |
Projects in Shirur Gramin
22 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Shantivan Homes Phase 3Vishal Khaserao Dandawate | PP1260002602426 | 18 Oct 2026 | 30 Sep 2027 | — | Not yet due | 0 |
| Shantivan Homes Phase 7Sharad Kisan Kurandale | PP1260002602067 | 1 Oct 2026 | 30 Sep 2027 | 30 Sep 2027 | Not yet due | 0 |
| Shantivan Homes Phase 8Shekhar Valmik Kurundale | PP1260002601949 | 17 Sep 2026 | 30 Sep 2027 | 30 Sep 2027 | Not yet due | 0 |
| Shantivan Homes Phase 5Sagar Khaserao Dandawate | PP1260002601940 | 16 Sep 2026 | 30 Sep 2027 | 30 Sep 2027 | Not yet due | 0 |
| Daksha EnclaveAjit Govindlal Mutha | P52100079318 | 28 Feb 2025 | 25 Dec 2027 | 25 Apr 2028 | Extended 4 mo | 0 |
| Bramha HeightsRaju Annasaheb Kakade | P52100077440 | 16 Aug 2024 | 31 Mar 2027 | 31 Jul 2027 | Extended 4 mo | 0 |
| Oxy Gold E BuildingM M Developers | P52100056245 | 22 May 2024 | 31 Dec 2026 | 30 Apr 2027 | Extended 4 mo | 0 |
| Krushna ResidencyKokare And Associates | P52100051604 | 27 Jun 2023 | 31 Dec 2024 | 31 Dec 2025 | Extended 12 mo | 0 |
| Sai VyankateshPramod Eknath Shelake | P52100027837 | 8 Jan 2021 | 1 Mar 2024 | 1 Mar 2024 | Promised date passed | 0 |
| Mandai ComplexNew Manikraj Developers | P52100027785 | 3 Jan 2021 | 1 Apr 2024 | 1 Apr 2024 | Promised date passed | 0 |
| Oxy Gold DM M Developers | P52100025691 | 3 Jul 2020 | 13 Aug 2022 | 13 Aug 2022 | Promised date passed | 0 |
| SangramskyGanesh Dnyandeo Devkhile | P52100023922 | 14 Jan 2020 | 10 Nov 2023 | 10 Nov 2023 | Promised date passed | 0 |
| Rudra DesireRadhakrushana Madhukar Kale | P52100023077 | 29 Nov 2019 | 30 Mar 2023 | 30 Mar 2023 | Promised date passed | 0 |
| Highway CenterSrp Infra | P52100021066 | 31 May 2019 | 31 Mar 2023 | 31 Dec 2025 | Extended 33 mo | 0 |
| Venkatesh HeightsVenkatesh Associates | P52100015206 | 7 Feb 2018 | 30 Sep 2020 | 31 Dec 2023 | Extended 39 mo | 0 |
| Shivraj ResidencySomnath Shivaji Gaikwad | P52100014343 | 23 Nov 2017 | 31 Dec 2017 | 31 Dec 2017 | Promised date passed | 0 |
| Nakshatra Dreams 3Dream Keys Associates | P52100014113 | 7 Nov 2017 | 1 Mar 2021 | 31 Dec 2023 | Extended 33 mo | 0 |
| SaibanNirmiti Promoters and Builders | P52100013318 | 22 Sep 2017 | 30 Oct 2018 | 30 Oct 2020 | Extended 24 mo | 0 |
| Shivansh Complex 2Somnath Tukaram Jagdale | P52100012686 | 7 Sep 2017 | 31 Aug 2018 | 31 Aug 2018 | Promised date passed | 0 |
| Shree Sai LifestyleSaisamruddhi Construction | P52100010845 | 31 Aug 2017 | 31 Dec 2019 | 31 Dec 2019 | Promised date passed | 0 |
| KamalsandhyaSantosh Baban More | P52100008308 | 18 Aug 2017 | 31 Jul 2019 | 31 Jul 2019 | Promised date passed | 0 |
| Krushnai Vihar Phase-IKrushnai Associates | P52100001766 | 29 Jul 2017 | 30 Sep 2020 | 30 Mar 2024 | Extended 42 mo | 0 |
Other localities in Shirur
Most active promoters
By projects registered here, as named on MahaRERA.
- M M Developers2 projects
- Ajit Govindlal Mutha1 project
- Dream Keys Associates1 project
- Ganesh Dnyandeo Devkhile1 project
- Kokare And Associates1 project
- Krushnai Associates1 project
- New Manikraj Developers1 project
- Nirmiti Promoters and Builders1 project
- Pramod Eknath Shelake1 project
- Radhakrushana Madhukar Kale1 project
Data through18 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology