RERA projects in Karegaon

2 projects under 2 MahaRERA registrations, registered 2017–2024. 100% have a completion date extended beyond the one promised.

Locality
2RERA projects
2Registrations
1Completion still due1 past their completion date
11 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
2Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20171
20180
20190
20200
20210
20220
20230
20241

Projects in Karegaon

2 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Nisarg AnshGanesh Vasant WalkeP5210007666120 Jun 202431 Dec 202630 Apr 2027Extended 4 mo0
IndraprasthaOmkar DevelopersP5210000740017 Aug 201731 Aug 201928 Feb 2021Extended 18 mo0

Other localities in Shirur

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Ganesh Vasant Walke1 project
  2. Omkar Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology