Shikrapur, Pune

Deedo IDDL-PUN-SHIKRAPUR

8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects35
Registrations36some projects hold several
Completion still due1521 past their date
Median extension4 months42% of registrations extended
Regulatory cases0none on MahaRERA's lists

8 in 10 registrations run late here

36 MahaRERA registrations in Shikrapur

6 not yet due9 extended, not yet due21 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Shikrapur

35 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Ekdant PlazaShree Developers And BuildersDue Jun 2028——
Shivsrushti Market-1Saishraddha Developers and BuildersDue Apr 2030, extended 4 mo——
ShantaiWinstar InfraCompleted——
DnyaneshwarWinstar InfraDue Jul 2027, extended 4 mo——
Garden CitySubhaj Construction And Developments LLPDue Oct 2028——
Kamal BaugSaptarshi BuildconDue Dec 2030——
Eco Gram Phase 3Shri Siddhivinayak BuildersDue Apr 2029, extended 4 mo—42%
Sai ZionSai BuiltconDue Jul 2028, extended 4 mo—4%
Shikrapur Business MarketSharad Laxman BangarDue Sep 2027, extended 4 mo——
Vindhya HeightsMhalsakant PropertiesDue Apr 2028, extended 4 mo—13%
Shikrapur Trade Center Phase IIIPride landmarks8 mo late——
NandanWinstar InfraCompleted——
Abhilasha Wing A And Wing BKudale Sable BuildersDue Apr 2027, extended 4 mo—49%
shikrapur Trade CentrePride landmarks1 yr 2 mo late——
Rajvardhan Shopping CentreBhauso Kisan Langhe3 yrs 5 mo late—17%
EcoviharSiddhesh Ramchandra Bangar1 yr 8 mo late——
Vrundavan ParkShree Saishraddha Developers & BuildersCompleted, extended 1 yr 6 mo—12%
Eco Villas IISaptarshi PropertiesCompleted——
Green Nest ResidencySharad Laxman BangarCompleted——
Maitri GoldMaitri Developers And BuildersDue Dec 2026—15%
Eco VillasSaptarshi PropertiesCompleted——
Dew DropsGreen HomesCompleted—85%
AbhilashaKudale Sable BuildersCompleted, extended 1 yr 6 mo—89%
HarmonyNandakumar LapalikarCompleted—33%
Triaa PrincetownTriaa Infracon LLP4 yrs 3 mo late—23%
Shikrapur market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Bhagvati Infra4 projects
  2. Shri Siddhivinayak Builders3 projects
  3. Winstar Infra3 projects
  4. Kudale Sable Builders2 projects
  5. Pride Landmarks2 projects
  6. Saptarshi Properties2 projects
  7. Amol Shirish Jakate1 project
  8. Amrutkalash Properties1 project
  9. Bhauso Kisan Langhe1 project
  10. Green Homes1 project

Shikrapur, in questions

How many projects in Shikrapur run late?

8 in 10 MahaRERA registrations (30 of 36): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Shikrapur by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology