RERA projects in Narhe
387 projects under 37 MahaRERA registrations, registered 2017–2026. 32% have a completion date extended beyond the one promised.
Locality
387RERA projects
37Registrationssome projects hold several
11Completion still due26 past their completion date
4 monthsMedian extension beyond promised date32% of registrations extended
0Regulatory casesnone on MahaRERA's lists
498Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 19 |
| 2018 | 2 |
| 2019 | 1 |
| 2020 | 2 |
| 2021 | 0 |
| 2022 | 3 |
| 2023 | 2 |
| 2024 | 1 |
| 2025 | 3 |
| 2026 | 4 |
Projects in Narhe
387 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Shubh ShantiSwaroop Developers | PR1260002601240 | 20 Jul 2026 | 31 May 2031 | 30 Sep 2031 | Extended 4 mo | 0 |
| Nakshatra NandanvanSkyworks Developers | PM1260002600691 | 8 Jun 2026 | 31 Dec 2032 | 30 Apr 2033 | Extended 4 mo | 0 |
| Audumber PrarthiNest Vera Buildcon | PR1260002600549 | 26 May 2026 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| Lara SolitaireM/s SC Developers | PR1260002501970 | 1 Jan 2026 | 31 Aug 2028 | 31 Dec 2028 | Extended 4 mo | 0 |
| AurumM/S. Khandve Patil Constructions | PM1260002500321 | 22 Jul 2025 | 30 Jun 2029 | 30 Oct 2029 | Extended 4 mo | 0 |
| Riddhi Siddhi ImperiaRajesh Sadhuram Gurnani | P52100079517 | 10 Mar 2025 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Nandanvan ResidenceSai Siddhi Developers | P52100078918 | 20 Jan 2025 | 28 Sep 2028 | 28 Sep 2028 | Not yet due | 0 |
| Chaandrai VrundavanChaandrai SR Construction | P52100077169 | 29 Jul 2024 | 1 Dec 2027 | 1 Dec 2027 | Not yet due | 0 |
| SwapnshilpUmesh Vasantrao Meshram | P52100052025 | 19 Jul 2023 | 13 Feb 2025 | 13 Feb 2025 | Promised date passed | 0 |
| Vasant Vihar A WingA R Developers | P52100051719 | 27 Jun 2023 | 30 Sep 2026 | 30 Jan 2027 | Extended 4 mo | 0 |
| Viraj ParkViraj Enterprises | P52100047667 | 17 Nov 2022 | 31 Jul 2023 | 31 Jul 2023 | Promised date passed | 0 |
| Raghukul ResidencyJai Ganesh Developers | P52100032729 | 24 Jan 2022 | 31 Dec 2025 | 31 Dec 2025 | Promised date passed | 0 |
| Vaijnath Residency 2Sumeru Developers | P52100027327 | 2 Dec 2020 | 30 Jun 2026 | 30 Oct 2026 | Extended 4 mo | 0 |
| Sushrut Residency Phase IISumeru Developers | P52100025563 | 28 Jun 2020 | 30 Apr 2024 | 30 Apr 2024 | Promised date passed | 0 |
| Vasant Vihar B WingA R Developers | P52100022836 | 30 Oct 2019 | 1 Oct 2023 | 1 Oct 2023 | Promised date passed | 0 |
| Ishita ResidencyGanesh Machchhindra Sawant | P52100018503 | 12 Nov 2018 | 30 Dec 2021 | 30 Dec 2021 | Promised date passed | 0 |
| Kumar Omkar ShreeKumar Enterprises | P52100015579 | 8 Mar 2018 | 31 Dec 2027 | 31 Dec 2027 | Not yet due | 0 |
| Data Digambar NiwasOm Aavadhut Creation | P52100013966 | 2 Nov 2017 | 29 Dec 2023 | 29 Dec 2023 | Promised date passed | 0 |
| Shubharambha SkyShubharambha Developers | P52100013417 | 5 Oct 2017 | 10 Apr 2019 | 10 Apr 2019 | Promised date passed | 0 |
| Balaji VishwaBalaji Developers | P52100013310 | 22 Sep 2017 | 30 Oct 2021 | 30 Oct 2021 | Promised date passed | 0 |
| Keshav Rukmini SankulBhumkar Promoters And Builders | P52100012696 | 7 Sep 2017 | 20 Nov 2018 | 20 Nov 2018 | Promised date passed | 0 |
| Surabhi GardenSurabhi Developers | P52100012897 | 7 Sep 2017 | 30 Dec 2021 | 30 Dec 2021 | Promised date passed | 0 |
| Rahi ComplexShri Siddhi Developers | P52100012377 | 1 Sep 2017 | 31 Mar 2018 | 31 Mar 2018 | Promised date passed | 0 |
| Durvankur SrushtiDurvankur Vastunirmiti Private Limited | P52100010911, P52100047389 | 31 Aug 2017 | 31 Dec 2025 | 31 Dec 2025 | Promised date passed | 0 |
| premiaC.D. Developers | P52100005230, P52100008990 | 19 Aug 2017 | 31 Oct 2018 | 31 Oct 2018 | Promised date passed | 0 |
Other localities in Haveli
Most active promoters
By projects registered here, as named on MahaRERA.
- A R Developers2 projects
- Sumeru Developers2 projects
- Anant Narayan Gandale1 project
- Aone Shelters1 project
- Balaji Developers1 project
- Bhumkar Promoters And Builders1 project
- BKP Infraa1 project
- C.D. Developers1 project
- Chaandrai SR Construction1 project
- Dhankawade Patil Construction1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology