RERA projects in Wanwadi
21 projects under 22 MahaRERA registrations, registered 2017–2026. 77% have a completion date extended beyond the one promised.
Locality
21RERA projects
22Registrationssome projects hold several
17Completion still due5 past their completion date
4 monthsMedian extension beyond promised date77% of registrations extended
0Regulatory casesnone on MahaRERA's lists
29Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 5 |
| 2018 | 2 |
| 2019 | 2 |
| 2020 | 1 |
| 2021 | 0 |
| 2022 | 0 |
| 2023 | 3 |
| 2024 | 2 |
| 2025 | 4 |
| 2026 | 3 |
Projects in Wanwadi
21 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Ram ResidencyOpulent Builders | PC1260002600348 | 5 May 2026 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Symphony of The SkiesPrathamesh Developers and Builders | PM1261012502367 | 16 Feb 2026 | 31 Dec 2032 | 30 Apr 2033 | Extended 4 mo | 0 |
| Windsor Satya ViharWindsor Infracon LLP | PR1260002502293 | 9 Feb 2026 | 28 Dec 2028 | 28 Apr 2029 | Extended 4 mo | 0 |
| The Deva ResidencesSuresh Devendra Kothari Huf | PR1260002501436 | 11 Nov 2025 | 31 Dec 2026 | 31 Dec 2026 | Not yet due | 0 |
| Nature CastleShah and Shah Realty | PR1260002501172 | 10 Oct 2025 | 30 Jun 2029 | 30 Oct 2029 | Extended 4 mo | 0 |
| Punde HeightsPushkaraj Reality | P52100079495 | 10 Mar 2025 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| 5 RaceCourse By SkyiEnerrgia Skyi Landmarks | P52100077439, PR1262022501357 | 16 Aug 2024 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| Vasant BaharDarsheel Construction | P52100055663 | 5 Apr 2024 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Gold CrestGolden Magnum | P52100053975 | 18 Dec 2023 | 31 Dec 2026 | 30 Apr 2027 | Extended 4 mo | 0 |
| Empress GreensAnand Landmarks | P52100051728 | 27 Jun 2023 | 30 Jun 2030 | 30 Oct 2030 | Extended 4 mo | 0 |
| Kailash Kutir Phase-2Kakkad Developments | P52100050090 | 15 Mar 2023 | 30 Sep 2027 | 30 Jan 2028 | Extended 4 mo | 0 |
| IshanandMakawana Bros & Co (Hwp) | P52100025427 | 29 May 2020 | 30 Jun 2027 | 30 Jun 2027 | Not yet due | 0 |
| Maruti EnclaveMaruti Enclave | P52100023543 | 18 Dec 2019 | 30 Dec 2023 | 31 Dec 2027 | Extended 48 mo | 0 |
| Ram ResidencyOpulent Builders | P52100022811 | 30 Oct 2019 | 31 Jan 2027 | 31 May 2027 | Extended 4 mo | 0 |
| Golden EastVenkatesh Vilas Aop | P52100018329 | 23 Oct 2018 | 30 Dec 2022 | 31 Dec 2028 | Extended 72 mo | 0 |
| One PlaceU D Developers LLP | P52100016297 | 2 May 2018 | 30 Dec 2024 | 21 May 2025 | Extended 5 mo | 0 |
| Arihant AmbienceDharmesh Vasantrai Shah | P52100011343 | 31 Aug 2017 | 31 Dec 2017 | 31 Dec 2017 | Promised date passed | 0 |
| Arihant RoyaltyDharmesh Vasantrai Shah | P52100011091 | 31 Aug 2017 | 31 Dec 2017 | 31 Jul 2022 | Extended 55 mo | 0 |
| Arihant GardenDharmesh Vasantrai Shah | P52100009410 | 22 Aug 2017 | 31 Dec 2017 | 31 Dec 2017 | Promised date passed | 0 |
| Arihant AvenueDharmesh Vasantrai Shah | P52100009141 | 19 Aug 2017 | 31 Dec 2017 | 31 Dec 2017 | Promised date passed | 0 |
| Kshrugal BuildconKuldip Ramesh Baagwe | P52100004947 | 9 Aug 2017 | 15 Aug 2027 | 15 Dec 2027 | Extended 4 mo | 0 |
Other localities in Haveli
Most active promoters
By projects registered here, as named on MahaRERA.
- Dharmesh Vasantrai Shah4 projects
- Opulent Builders2 projects
- Anand Landmarks1 project
- Darsheel Construction1 project
- Enerrgia Skyi Landmarks1 project
- Golden Magnum1 project
- Kakkad Developments1 project
- Kuldip Ramesh Baagwe1 project
- Makawana Bros & Co (Hwp)1 project
- Maruti Enclave1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology