Dnyanesh
Deedo IDDP-PUN-AD65Its promised completion date, Mar 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 90% of its units are booked.
Dudulgaon, Pune 412105 · by Nimit Group
Buying a flat here?
See every deed registered on it.
Its promised completion date, Mar 2025, has passed and MahaRERA does not show it completed
- This projectRegistered 27 Aug 2019, completion promised 30 Mar 2025, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100022117
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100022117 | 27 Aug 2019 | 30 Mar 2025 | 30 Mar 2025 | Nimit Group | Project page |
Documents41
1 document held by Deedo, 40 filings listed on MahaRERA's project page
Finance
- PAN CardPAN CARD.pdf · uploaded 16 Aug 2019Source
Legal
Show all 41 documentsShow fewer documents
Migrated
- 1 Building Plan Approval / NA Order for plotted developmentBUILDING.pdf · uploaded 16 Aug 2019Source
- 1 Commencement Certificates / NA Order for plotted developmentcommencement.pdf · uploaded 16 Aug 2019Source
- 1 Declaration in FORM BFORM B.pdf · uploaded 16 Aug 2019Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 16 Aug 2019Source
- 1 Proforma of Allotment letterNo Agreement Letter.PDF · uploaded 16 Aug 2019Source
- 2 Copy of Layout Approval (in case of layout)Revised plan HPSC1171_compressed.pdf · uploaded 22 Jun 2020Source
- 2 Building Plan Approval / NA Order for plotted developmentRevised plan HPSC1172_compressed (1).pdf · uploaded 22 Jun 2020Source
- 2 Commencement Certificates / NA Order for plotted developmentRevised CC.pdf · uploaded 22 Jun 2020Source
- 2 Proforma of Allotment letterAgreement_For_Sale.pdf · uploaded 23 Sep 2020Source
- 3 Proforma of Allotment letterAllotment_Letter.pdf · uploaded 23 Sep 2020Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)RERA AUDIT.pdf · uploaded 7 Oct 2020Source
- 4 Proforma of Allotment letterNIMIT AGREEMENT TO SALE 1-10-19.pdf · uploaded 13 Oct 2020Source
- 5 Proforma of Allotment letterALLOTTMENT LETTER UPLOAD.pdf · uploaded 13 Oct 2020Source
- 3 Copy of Layout Approval (in case of layout)Nimitplancopy1_compressed.pdf · uploaded 25 Jul 2021Source
- 3 Building Plan Approval / NA Order for plotted developmentNimitplancopy2_compressed.pdf · uploaded 25 Jul 2021Source
- 4 Building Plan Approval / NA Order for plotted developmentNimitplancopy3_compressed.pdf · uploaded 25 Jul 2021Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate 1.pdf · uploaded 8 May 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate 2.pdf · uploaded 8 May 2023Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate 3.pdf · uploaded 8 May 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)CA Form 5 Annual Report.pdf · uploaded 8 May 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 Signed _compressed.pdf · uploaded 8 May 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 Signed.pdf · uploaded 13 Mar 2024Source
- Form 5 (FY 2019-2020)RERA AUDIT FY 2019-20.pdf · uploaded 12 Feb 2026Source
- Form 5 (FY 2020-2021)CA Form 5 Annual Report.pdf · uploaded 12 Feb 2026Source
- Form 5 (FY 2021-2022)Form 5 Signed .pdf · uploaded 12 Feb 2026Source
- Form 5 (FY 2022-2023)FORM 5 Signed.pdf · uploaded 12 Feb 2026Source
Technical
- DocumentLAYOUT.pdf · uploaded 16 Aug 2019Source
- DocumentBUILDING.pdf · uploaded 16 Aug 2019Source
- DocumentRevised plan HPSC1171_compressed.pdf · uploaded 22 Jun 2020Source
- DocumentRevised plan HPSC1172_compressed (1).pdf · uploaded 22 Jun 2020Source
- DocumentNimitplancopy1_compressed.pdf · uploaded 25 Jul 2021Source
- DocumentNimitplancopy2_compressed.pdf · uploaded 25 Jul 2021Source
- DocumentNimitplancopy3_compressed.pdf · uploaded 25 Jul 2021Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel GAT NO 69
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, Office space, Shop20 units in all
- Address
- Gat No 69, Dudulgaon, DudulgaonPIN 412105
- Village
- Pimpri Chinchawad (M Corp.), Haveli taluka
- Location
- 18.67751, 73.88160
- Land area for this project
- 594 sq m (6,391 sq ft)
- Permissible built-up area
- 454 sq m (4,885 sq ft)
- Sanctioned built-up area
- 454 sq m (4,885 sq ft)
- Designated bank account
- 203
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
GAT NO 69
Boundaries
- North
- By Moshi Alandi Brt Road
- South
- Land Owned By Smt Parvatibai Bankar
- East
- Land Owned By Gaikwad
- West
- Land Owned By Shri Chaudhari
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking20 units
18 of 20 units booked (90%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 43.94 sq m · 473 sq ft | 3 | 3 |
| 1BHK | 44.97 sq m · 484 sq ft | 3 | 2 |
| 1BHK | 45.62 sq m · 491 sq ft | 2 | 2 |
| 1BHK | 47.38 sq m · 510 sq ft | 3 | 3 |
| 1BHK | 48.12 sq m · 518 sq ft | 3 | 3 |
| Office space | 45.34 sq m · 488 sq ft | 2 | 2 |
| Shop | 14.59 sq m · 157 sq ft | 1 | 1 |
| Shop | 22.58 sq m · 243 sq ft | 2 | 1 |
| Shop | 26.57 sq m · 286 sq ft | 1 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals6
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Vilas J Yele | — |
| Chartered accountant | Nipun A Bhandari And Associates | — |
| Chartered accountant | Pravin Salunke | — |
| Chartered accountant | Rohit Jadhav | — |
| Engineer | M/S. Rahul Kapse And Associates | — |
| Other | Mauli Construction | — |
Source: MahaRERA project page. Contact details are not shown.