RERA projects in Lonikalbhor

17 projects under 20 MahaRERA registrations, registered 2017–2025. 30% have a completion date extended beyond the one promised.

Locality
17RERA projects
20Registrationssome projects hold several
3Completion still due17 past their completion date
16 monthsMedian extension beyond promised date30% of registrations extended
0Regulatory casesnone on MahaRERA's lists
29Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
201710
20183
20191
20202
20210
20222
20230
20241
20251

Projects in Lonikalbhor

17 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Dhruv AnganMagar Buildcon AopP5210007897828 Jan 202531 Dec 202730 Apr 2028Extended 4 mo0
Muktai Park Phase IShivshakti BuildconP5210005518211 Mar 202431 Dec 202531 Dec 2025Promised date passed0
Madhushila HeritageShree Sai ConstructionP5210003431930 Mar 202231 Dec 202431 Dec 2024Promised date passed0
Samartha ParadiseSamartha PropertiesP5210003270524 Jan 20227 Feb 20257 Feb 2025Promised date passed0
Royal OrchidRoyal Square DevelopersP521000274048 Dec 202026 Jul 202225 Jul 2023Extended 12 mo0
Sai ViharShree Sai ConstructionP521000238789 Jan 202030 Jan 202130 Jan 2021Promised date passed0
Meridian CrownMeridian AssociatesP521000207468 May 201930 Mar 202328 Mar 2024Extended 12 mo0
Jyoti ViharShardul ConstructionsP5210001537520 Feb 201830 Dec 202218 Apr 2028Extended 64 mo0
Ambar DarshanShivshakti Builders & DevelopersP5210000884313 Nov 201731 Dec 201731 Dec 2017Promised date passed0
Ambar VilasShivshakti PromotersP5210001141931 Aug 201730 Jun 201831 Dec 2027Extended 114 mo0
Sai ParkRachana ConstructionsP5210001138731 Aug 201730 Dec 202230 Dec 2022Promised date passed0
Tara CityNilesh Shivjee SinghP5210000931722 Aug 201731 Dec 201831 Dec 2018Promised date passed0
Tara JewelTara JewelP5210000741817 Aug 201731 Dec 201731 Dec 2017Promised date passed0
Crystal TowerOm Sai DevelopersP5210000675716 Aug 201730 Dec 202131 Aug 2023Extended 20 mo0
Sai LeelaSai ConstructionsP5210000693816 Aug 201731 Mar 201831 Mar 2018Promised date passed0
Satyam PrimroseSuresh Changdev DabadeP5210000551311 Aug 201730 Jun 201830 Jun 2018Promised date passed0
Venkatesh JoynestShree Venkatesh GroupP52100000990, P52100013900, P52100017998 +125 Jul 201730 Sep 202030 Sep 2020Promised date passed0

Other localities in Haveli

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Shree Sai Construction2 projects
  2. Magar Buildcon Aop1 project
  3. Meridian Associates1 project
  4. Nilesh Shivjee Singh1 project
  5. Om Sai Developers1 project
  6. Rachana Constructions1 project
  7. Royal Square Developers1 project
  8. Sai Constructions1 project
  9. Samartha Properties1 project
  10. Shardul Constructions1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology