5 projects under 5 MahaRERA registrations, registered 2022–2026. 60% have a completion date extended beyond the one promised.
Locality
5RERA projects
5Registrations
3Completion still due2 past their completion date
4 monthsMedian extension beyond promised date60% of registrations extended
0Regulatory casesnone on MahaRERA's lists
8Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2022 | 2 |
| 2023 | 0 |
| 2024 | 0 |
| 2025 | 2 |
| 2026 | 1 |
Projects in Bhegadewadi
5 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Avishkar Hortus 2Arun Baban Marathe | PR1260002600957 | 29 Jun 2026 | 31 May 2027 | 30 Sep 2027 | Extended 4 mo | 0 |
| Cocoon HomesCanvas Estates | PR1260002501272 | 20 Oct 2025 | 30 Oct 2029 | 28 Feb 2030 | Extended 4 mo | 0 |
| Avishkar HortusArun Baban Marathe | P52100079971 | 8 Apr 2025 | 31 May 2027 | 30 Sep 2027 | Extended 4 mo | 0 |
| Ohana CountyNorthstar Realty | P52100047063 | 29 Sep 2022 | 31 Dec 2024 | 31 Dec 2024 | Promised date passed | 0 |
| Chinchechi BaugArun Baban Marathe | P52100045463 | 19 May 2022 | 31 May 2025 | 31 May 2025 | Promised date passed | 0 |
Other localities in Mulshi
Most active promoters
By projects registered here, as named on MahaRERA.
- Arun Baban Marathe3 projects
- Canvas Estates1 project
- Northstar Realty1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology