Sindhudurg
Deedo IDDL-SIN-SINDHUDURG8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects522in 83 localities
Registrations534some projects hold several
Completion still due188259 past their date
Median extension4 months47% of registrations extended
Regulatory cases26on 26 projects
8 in 10 registrations run late here
534 MahaRERA registrations in Sindhudurg and the places within it
46 not yet due142 extended, not yet due259 past even the latest date87 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Sindhudurg
522 projects registered with MahaRERA in this district and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Shree Laxmi PlazzaMohan Vasudeo Hundare | Due Oct 2027, extended 4 mo | — | — |
| Nirman HeightsRohan Shashikant Ragaji | Due Dec 2026, extended 1 yr 9 mo | — | 15% |
| Ram Rajya ResidencyAditya Nikunj Shah | Due Apr 2029, extended 4 mo | — | — |
| Dipali ResidencyDattatray Construction | Completed | — | 100% |
| Venkatesh ApartmentSupreme Builders and Developers | 11 mo late | — | — |
| Ayaans AmbarySuman Developers | Due Oct 2027, extended 4 mo | — | 32% |
| Samarth PlazaUnique Infra | Due Apr 2027, extended 4 mo | — | — |
| Samarth AishwaryaSamarth Builders & Developers | Due Sep 2028, extended 4 mo | — | 6% |
| Amruta HeightsAnish Ajay Swar | Due Sep 2028, extended 4 mo | — | — |
| Shivshakti ApartmentSneha Chandrakant Rane | Due Apr 2028, extended 4 mo | — | 15% |
| Shiv TejAjinkya Construction | Due Oct 2031, extended 4 mo | — | — |
| Apna GharVyankatesh Vasant Deshpande | Due Sep 2028, extended 4 mo | — | — |
| Mahalaxmi ResidencyPrakash Rajaram Jaitapkar | Due Apr 2031, extended 4 mo | — | 4% |
| Kamat Vishwa - 2Pranav Prakash Kamat | Due Apr 2027, extended 4 mo | — | — |
| Manomay ResidencySumukh Developers | Due Apr 2027, extended 4 mo | — | — |
| Ashok ParkRajesh Ashok Pawaskar | Due Dec 2026 | — | — |
| Sahil Plaza B-WingNafees Ashraf Khan | Completed | — | 19% |
| Suvidha Suryakant ComplexBahar Dasharath Bhosale | 11 mo late | — | — |
| Shree Ganesh ApartmentsMrs Laxmi Rajaram Sawant | Due Jul 2028, extended 4 mo | — | 10% |
| Shree Tuljabhavani ComplexShree Tuljabhavani Developers | Due Apr 2031, extended 4 mo | — | — |
| Royal EnclaveElite Developers | Due Oct 2027, extended 4 mo | — | — |
| Dodamarg HeightsReality and Manufacture Group RMG | 11 mo late | — | 15% |
| Krupasindhu ApartmentPrawal Construction | Due Apr 2027, extended 4 mo | — | — |
| Ujwal ResidencyAjinkya Construction | Completed | — | 86% |
| Maitri ResidencyNeha Sanjay Vengurlekar | 1 yr 11 mo late | — | 17% |
Localities in Sindhudurg
- Kudal (Ct)58 projects
- Sawantwadi (M Cl)52 projects
- Kankavali44 projects
- Jamsande24 projects
- Malwan (M Cl)21 projects
- Vengurla (M Cl)19 projects
- Oras Bk.17 projects
- Kudal16 projects
- Sawantwadi16 projects
- Kankavli15 projects
- Banda (Ct)12 projects
- Kalmath11 projects
All 83 localities
- Dodamarg10
- Kasai9
- Majgaon (Ct)9
- Charathe8
- Maneri8
- Pinguli8
- Kumbharli7
- Devgad6
- Janvali6
- Kolgaon6
- Sangirde6
- Tarele6
- Malgaon5
- Vabhave5
- Niravade4
- Vengurla4
- Bhom3
- Kokisare3
- Kumbharmath3
- Malewad3
- Malwan3
- Padel3
- Vagde3
- Arawali2
- Deulwadi2
- Halval2
- Kasal2
- Kolamb2
- Mithbaon2
- Pandur2
- Shemadranewadi2
- Shiroda2
- Vaibhavvadi2
- Vazare2
- Wayari2
- Ajgaon1
- Ambeli1
- Amboli1
- Anandnagar1
- Ashiye1
- Bagadwadi1
- Bhogave1
- Chandoshi1
- Chauke1
- Chindar1
- Devgad1
- Dhamapur1
- Girapwadi1
- Girode1
- Gudhipur1
- Humrath1
- Kasarde1
- Katta1
- Kattagaon1
- Kavilkate1
- Khanoli1
- Kharepatan1
- Kinale1
- Kshetrafal1
- Kusarave1
- Nandgaon1
- Osargaon1
- Palasmb1
- Pawashi1
- Phondaghat1
- Ranbambuli1
- Sangave1
- Sateli Bhedshi1
- Tiravde1
- Waingani1
- Wayangani1
Other districts
Most active promoters
- Ajinkya Construction8 projects
- Sukhmani Constructions6 projects
- Ajinkkya Construction5 projects
- Nirmitee Builders & Developers5 projects
- Ranco Realty Pvt Ltd5 projects
- Benjamin Manwel Dsouza4 projects
- Chandrashekhar Suryakant Morvekar4 projects
- Consortexe Properties Pvt Ltd4 projects
- Manoj Vasant Mahadik4 projects
- Abhay Sharad Walawalkar3 projects
Sindhudurg, in questions
How many projects in Sindhudurg run late?
8 in 10 MahaRERA registrations (401 of 534): their completion date was extended or has passed, data through 20 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Sindhudurg by Deedo. Medians on fewer than 3 deeds are not shown.
Data through20 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology
