8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects522in 83 localities
Registrations534some projects hold several
Completion still due188259 past their date
Median extension4 months47% of registrations extended
Regulatory cases26on 26 projects

8 in 10 registrations run late here

534 MahaRERA registrations in Sindhudurg and the places within it

46 not yet due142 extended, not yet due259 past even the latest date87 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Sindhudurg

522 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Shree Laxmi PlazzaMohan Vasudeo HundareDue Oct 2027, extended 4 mo——
Nirman HeightsRohan Shashikant RagajiDue Dec 2026, extended 1 yr 9 mo—15%
Ram Rajya ResidencyAditya Nikunj ShahDue Apr 2029, extended 4 mo——
Dipali ResidencyDattatray ConstructionCompleted—100%
Venkatesh ApartmentSupreme Builders and Developers11 mo late——
Ayaans AmbarySuman DevelopersDue Oct 2027, extended 4 mo—32%
Samarth PlazaUnique InfraDue Apr 2027, extended 4 mo——
Samarth AishwaryaSamarth Builders & DevelopersDue Sep 2028, extended 4 mo—6%
Amruta HeightsAnish Ajay SwarDue Sep 2028, extended 4 mo——
Shivshakti ApartmentSneha Chandrakant RaneDue Apr 2028, extended 4 mo—15%
Shiv TejAjinkya ConstructionDue Oct 2031, extended 4 mo——
Apna GharVyankatesh Vasant DeshpandeDue Sep 2028, extended 4 mo——
Mahalaxmi ResidencyPrakash Rajaram JaitapkarDue Apr 2031, extended 4 mo—4%
Kamat Vishwa - 2Pranav Prakash KamatDue Apr 2027, extended 4 mo——
Manomay ResidencySumukh DevelopersDue Apr 2027, extended 4 mo——
Ashok ParkRajesh Ashok PawaskarDue Dec 2026——
Sahil Plaza B-WingNafees Ashraf KhanCompleted—19%
Suvidha Suryakant ComplexBahar Dasharath Bhosale11 mo late——
Shree Ganesh ApartmentsMrs Laxmi Rajaram SawantDue Jul 2028, extended 4 mo—10%
Shree Tuljabhavani ComplexShree Tuljabhavani DevelopersDue Apr 2031, extended 4 mo——
Royal EnclaveElite DevelopersDue Oct 2027, extended 4 mo——
Dodamarg HeightsReality and Manufacture Group RMG11 mo late—15%
Krupasindhu ApartmentPrawal ConstructionDue Apr 2027, extended 4 mo——
Ujwal ResidencyAjinkya ConstructionCompleted—86%
Maitri ResidencyNeha Sanjay Vengurlekar1 yr 11 mo late—17%
Sindhudurg market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Ajinkya Construction8 projects
  2. Sukhmani Constructions6 projects
  3. Ajinkkya Construction5 projects
  4. Nirmitee Builders & Developers5 projects
  5. Ranco Realty Pvt Ltd5 projects
  6. Benjamin Manwel Dsouza4 projects
  7. Chandrashekhar Suryakant Morvekar4 projects
  8. Consortexe Properties Pvt Ltd4 projects
  9. Manoj Vasant Mahadik4 projects
  10. Abhay Sharad Walawalkar3 projects

Sindhudurg, in questions

How many projects in Sindhudurg run late?

8 in 10 MahaRERA registrations (401 of 534): their completion date was extended or has passed, data through 20 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Sindhudurg by Deedo. Medians on fewer than 3 deeds are not shown.

Data through20 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology