8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects522in 83 localities
Registrations534some projects hold several
Completion still due188259 past their date
Median extension4 months47% of registrations extended
Regulatory cases26on 26 projects

8 in 10 registrations run late here

534 MahaRERA registrations in Sindhudurg and the places within it

46 not yet due142 extended, not yet due259 past even the latest date87 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Sindhudurg

522 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Sgs Thakur ComplexMarian Louis Dsouza11 mo late——
Kamat HighlightPranav Prakash KamatCompleted—83%
Anand DhamAashirwad EnterpriseCompleted—25%
Shraavan NivasGajanan Gopal BandivadekarDue Apr 2028, extended 4 mo——
ATHANG SAI HOMES on S No 32/8/2 and 34/1B of Village Kolamb Malvan 416606Chandrashekhar Suryakant MorvekarDue Jul 2029, extended 4 mo—27%
Samarth PlazaTejas Harishchandra SamantDue Mar 2030, extended 4 mo——
Ashapuri ResidencyShirish Suryakant ShirsatheDue Apr 2029, extended 4 mo—8%
Ghd Casa GrandeGulshan Homez And Developers2 yrs 4 mo late—28%
Nilaya ZionSgm Estates & Resorts Private Limited2 yrs 11 mo late——
Gobind ComplexSukhmani ConstructionsDue Jul 2028, extended 4 mo—46%
Nirmitee AvighnaNirmitee Builders & DevelopersDue Apr 2029, extended 4 mo——
Shreyans ResidencyPradeep Balu JaitapkarDue Apr 2027, extended 4 mo—17%
Durga - MadhavArun Maruti Rawool1 yr 11 mo late—19%
Radha-Krushna NagariMayuresh DevelopersDue Feb 2029, extended 4 mo——
Shripad PlazaShivanand Dasharath BhosaleCompleted—28%
DyaneshwariDds BuildconDue Apr 2027, extended 4 mo—18%
Horizon GrandeMetric Homes Private LimitedDue Dec 2026—89%
Inamdar PlazaVijay Shridhar Tawde5 mo late——
Panchami HeightsGovind Janardan KhorjuvekarCompleted—29%
Shri Gopal AvenueSushant Shridhar NaikCompleted——
Mauli ResidencyKedar Naresh GawkarDue Jul 2027, extended 4 mo——
Srishti ImperiaNeeraj Mohan DesaiCompleted—63%
Manorama TownshipBhawani Heights Development Private Limited1 yr 6 mo late——
Vrukshavalli B-4Vijay Gangaram NaikDue Apr 2027, extended 4 mo——
Anandvan Sairaj Sankul Phase 1Consortexe Properties Pvt LtdDue Apr 2029, extended 4 mo—17%
Sindhudurg market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Ajinkya Construction8 projects
  2. Sukhmani Constructions6 projects
  3. Ajinkkya Construction5 projects
  4. Nirmitee Builders & Developers5 projects
  5. Ranco Realty Pvt Ltd5 projects
  6. Benjamin Manwel Dsouza4 projects
  7. Chandrashekhar Suryakant Morvekar4 projects
  8. Consortexe Properties Pvt Ltd4 projects
  9. Manoj Vasant Mahadik4 projects
  10. Abhay Sharad Walawalkar3 projects

Sindhudurg, in questions

How many projects in Sindhudurg run late?

8 in 10 MahaRERA registrations (401 of 534): their completion date was extended or has passed, data through 20 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Sindhudurg by Deedo. Medians on fewer than 3 deeds are not shown.

Data through20 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology