Sindhudurg
Deedo IDDL-SIN-SINDHUDURG8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects522in 83 localities
Registrations534some projects hold several
Completion still due188259 past their date
Median extension4 months47% of registrations extended
Regulatory cases26on 26 projects
8 in 10 registrations run late here
534 MahaRERA registrations in Sindhudurg and the places within it
46 not yet due142 extended, not yet due259 past even the latest date87 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Sindhudurg
522 projects registered with MahaRERA in this district and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Parvati PlazaPrakash Radhakrishna Mishal | Completed | — | — |
| Gobind DhamSukhmani Constructions | Due Dec 2027 | — | — |
| Ruturaj ShashwatChaitanya Suresh Kambli | Completed | — | 40% |
| Royal PlazaShailesh Bapu Jadhav | 2 yrs 3 mo late | — | — |
| Shrees Urban LifeSanket Shridhar Naik | Due Sep 2034, extended 4 mo | — | — |
| Eco Village Annexmanuraj enterprises | Due Apr 2028, extended 4 mo | — | — |
| Aarambh Business CentreConsortexe Properties Pvt Ltd | 3 yrs 5 mo late | — | — |
| Diksha Park Phase III BDashrath Babu Jadhav | 2 yrs 11 mo late | — | — |
| Sat BangalaKailas Suresh Satelkar | 1 yr 6 mo late | — | — |
| Amboli ParadiseBrumsy Creators | 11 mo late | — | — |
| Saira ApartmentJaved Hussain Khatib | Completed | — | — |
| Devaki RoyaleUmesh Sudhakar Sukhi | 11 mo late | — | — |
| Dattaguru NiwasD.S.S Group | Due Mar 2029 | — | — |
| Padmavati PlazaShivanand Dasharath Bhosale | 2 yrs 9 mo late | — | 60% |
| Sahyog - R ComplexSahyog Construction | Due Dec 2026 | — | — |
| Shree sai Balaji BuildersShree Sai Balaji Builders | Completed | — | — |
| Rana Mangalmurti PlazzaDamodar Krishna Rane | 5 mo late | — | 14% |
| Shri Shri EnclavesBalkrishna Bhaskar Sawant | Due Mar 2027 | — | 8% |
| Vaastu TathastuNilesh Arvind Manjarekar | Completed | — | — |
| Devgiri HeightsDarpan Construction | Due Jul 2027, extended 4 mo | — | — |
| Sadguru ComplexBhagwan Bhikaji Belekar | 11 mo late | — | — |
| Shri Samarth PlazaKishor Shahu Pangam | Due Dec 2026 | — | — |
| Sudhakar ArcadePrasad Raghunath Pangam | Completed | — | — |
| Harishchandra ResidencyHarishchandra Realty Solutions LLP | Due Feb 2029, extended 4 mo | — | — |
| Sai DarbarKailas Suresh Satelkar | Completed | — | 70% |
Localities in Sindhudurg
- Kudal (Ct)58 projects
- Sawantwadi (M Cl)52 projects
- Kankavali44 projects
- Jamsande24 projects
- Malwan (M Cl)21 projects
- Vengurla (M Cl)19 projects
- Oras Bk.17 projects
- Kudal16 projects
- Sawantwadi16 projects
- Kankavli15 projects
- Banda (Ct)12 projects
- Kalmath11 projects
All 83 localities
- Dodamarg10
- Kasai9
- Majgaon (Ct)9
- Charathe8
- Maneri8
- Pinguli8
- Kumbharli7
- Devgad6
- Janvali6
- Kolgaon6
- Sangirde6
- Tarele6
- Malgaon5
- Vabhave5
- Niravade4
- Vengurla4
- Bhom3
- Kokisare3
- Kumbharmath3
- Malewad3
- Malwan3
- Padel3
- Vagde3
- Arawali2
- Deulwadi2
- Halval2
- Kasal2
- Kolamb2
- Mithbaon2
- Pandur2
- Shemadranewadi2
- Shiroda2
- Vaibhavvadi2
- Vazare2
- Wayari2
- Ajgaon1
- Ambeli1
- Amboli1
- Anandnagar1
- Ashiye1
- Bagadwadi1
- Bhogave1
- Chandoshi1
- Chauke1
- Chindar1
- Devgad1
- Dhamapur1
- Girapwadi1
- Girode1
- Gudhipur1
- Humrath1
- Kasarde1
- Katta1
- Kattagaon1
- Kavilkate1
- Khanoli1
- Kharepatan1
- Kinale1
- Kshetrafal1
- Kusarave1
- Nandgaon1
- Osargaon1
- Palasmb1
- Pawashi1
- Phondaghat1
- Ranbambuli1
- Sangave1
- Sateli Bhedshi1
- Tiravde1
- Waingani1
- Wayangani1
Other districts
Most active promoters
- Ajinkya Construction8 projects
- Sukhmani Constructions6 projects
- Ajinkkya Construction5 projects
- Nirmitee Builders & Developers5 projects
- Ranco Realty Pvt Ltd5 projects
- Benjamin Manwel Dsouza4 projects
- Chandrashekhar Suryakant Morvekar4 projects
- Consortexe Properties Pvt Ltd4 projects
- Manoj Vasant Mahadik4 projects
- Abhay Sharad Walawalkar3 projects
Sindhudurg, in questions
How many projects in Sindhudurg run late?
8 in 10 MahaRERA registrations (401 of 534): their completion date was extended or has passed, data through 20 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Sindhudurg by Deedo. Medians on fewer than 3 deeds are not shown.
Data through20 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology