RERA projects in Pandur

2 projects under 2 MahaRERA registrations, registered 2022–2024. 50% have a completion date extended beyond the one promised.

Locality
2RERA projects
2Registrations
2Completion still due0 past their completion date
4 monthsMedian extension beyond promised date50% of registrations extended
0Regulatory casesnone on MahaRERA's lists
3Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20221
20230
20241

Projects in Pandur

2 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
GurukripaVastu DevelopersP5290007794914 Nov 202431 Dec 202830 Apr 2029Extended 4 mo0
Shri Shri EnclavesBalkrishna Bhaskar SawantP5290003455811 Apr 202231 Mar 202731 Mar 2027Not yet due0

Other localities in Kudal

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Balkrishna Bhaskar Sawant1 project
  2. Vastu Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology