RERA projects in Deulwadi
2 projects under 2 MahaRERA registrations, registered 2017–2025. 50% have a completion date extended beyond the one promised.
Locality
2RERA projects
2Registrations
1Completion still due1 past their completion date
4 monthsMedian extension beyond promised date50% of registrations extended
0Regulatory casesnone on MahaRERA's lists
1Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 1 |
| 2018 | 0 |
| 2019 | 0 |
| 2020 | 0 |
| 2021 | 0 |
| 2022 | 0 |
| 2023 | 0 |
| 2024 | 0 |
| 2025 | 1 |
Projects in Deulwadi
2 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Origin KudalAxon Origin Kudal LLP | P52900080941 | 25 Aug 2025 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| Samruddhi ApartmentChirayu Properties LLP | P52900004545 | 9 Aug 2017 | 31 Oct 2018 | 31 Oct 2018 | Promised date passed | 0 |
Other localities in Kudal
Most active promoters
By projects registered here, as named on MahaRERA.
- Axon Origin Kudal LLP1 project
- Chirayu Properties LLP1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology