RERA projects in Kokisare

3 projects under 3 MahaRERA registrations, registered 2017–2022. None has an extended completion date on record.

3RERA projects
3Registrations
1Completion still due2 past their completion date
—Median extension beyond promised date0% of registrations extended
1Regulatory caseson 1 project
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20171
20180
20191
20200
20210
20221

Projects in Kokisare

3 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Sadguru ComplexBhagwan Bhikaji BelekarP5290003343922 Feb 202231 Dec 2025—Promised date passed1
Siddhi Ganesh ParkManoj Vasant MahadikP5290002103531 May 201930 May 2027—Not yet due0
Samartha HillSitaram Krishna AdivarekarP5290000941122 Aug 20171 Aug 2019—Promised date passed0

Other localities in Vaibhavvadi

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Bhagwan Bhikaji Belekar1 project
  2. Manoj Vasant Mahadik1 project
  3. Sitaram Krishna Adivarekar1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology