Padel, Sindhudurg
Deedo IDDL-SIN-PADEL10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects3
Registrations3
Completion still due21 past their date
Median extension4 months100% of registrations extended
Regulatory cases0none on MahaRERA's lists
10 in 10 registrations run late here
3 MahaRERA registrations in Padel
2 extended, not yet due1 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Padel
3 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Shri Ram SankulSankalp Developers | Due Jun 2030, extended 4 mo | — | — |
| Vrindavan ApartmentShri Durga Developers | 8 mo late | — | — |
| KrupasindhuKrupasindhu Constructions LLP | Due Apr 2028, extended 4 mo | — | — |
Nearby: other villages in Devgad
Most active promoters
- Krupasindhu Constructions LLP1 project
- Sankalp Developers1 project
- Shri Durga Developers1 project
Padel, in questions
How many projects in Padel run late?
10 in 10 MahaRERA registrations (3 of 3): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Padel by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology
