8 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects6
Registrations6
Completion still due51 past their date
Median extension4 months83% of registrations extended
Regulatory cases0none on MahaRERA's lists
Tarele market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

10 in 10 registrations run late here

6 MahaRERA registrations in Tarele

5 extended, not yet due1 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Tarele

6 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Hardik ComplexKishor Vishram KhadyeP5290007676028 Jun 202431 Dec 202730 Apr 2028Extended 4 mo0
Mahadik PlazaManoj Vasant MahadikP5290005532514 Mar 202431 Dec 202630 Apr 2027Extended 4 mo0
Dhruvi ApartmentAbhay Mangesh BhambureP529000546292 Feb 202431 Dec 203030 Apr 2031Extended 4 mo0
Samarth PlazaM/S Unique InfraP529000534856 Nov 202331 Dec 202630 Apr 2027Extended 4 mo0
Shraavan NivasGajanan Gopal BandivadekarP5290004980424 Feb 202331 Dec 202730 Apr 2028Extended 4 mo0
Shree ResidencyManoj Vasant MahadikP529000259582 Aug 202030 Nov 202330 Nov 2023Promised date passed0

Most active promoters

  1. Manoj Vasant Mahadik2 projects
  2. Abhay Mangesh Bhambure1 project
  3. Gajanan Gopal Bandivadekar1 project
  4. Kishor Vishram Khadye1 project
  5. M/S Unique Infra1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology