8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects522in 83 localities
Registrations534some projects hold several
Completion still due188259 past their date
Median extension4 months47% of registrations extended
Regulatory cases26on 26 projects

8 in 10 registrations run late here

534 MahaRERA registrations in Sindhudurg and the places within it

46 not yet due142 extended, not yet due259 past even the latest date87 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Sindhudurg

522 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Lotus ArcadeLotus ArcadeDue Jul 2028, extended 4 mo——
Tarangan B WingConsortexe Properties Pvt LtdDue Apr 2027, extended 4 mo——
Anaadih Shri DattaPrabhakar Krishnaji ParabDue Apr 2027, extended 4 mo——
Krishiv TowerSanjiv Sahadev ParabDue Jul 2028, extended 4 mo——
Sindhu Pratap ComplexAmey HomesDue May 2028, extended 4 mo——
Vaibhavlakshmi ApartmentRajendra Shashikant MoryeDue Jul 2029, extended 4 mo——
Vighnaraj ApartmentDhananjay Manohar KalsekarDue Apr 2031, extended 4 mo——
Dwarkamai ArcadeDinesh Anant RaneDue Apr 2029, extended 4 mo—65%
Shiv ResidencyShiv Real Estate Developers And BuildersDue Mar 2028——
AlturaBlock Buildtech LLPDue Dec 2027——
Shrikrushna City CentreLaxminarayan ConstructionDue Jan 2029, extended 4 mo——
Yog AnandAbome Real Estate Private LimitedDue Apr 2032, extended 4 mo——
Mahadik PlazaManoj Vasant MahadikDue Apr 2027, extended 4 mo—9%
Gobind DarshanSukhmani ConstructionsDue Apr 2031, extended 4 mo——
M J TowersMahesh Someshwar Joshi8 mo late——
Ruturaj AatmshreeChaitanya Suresh KambliDue Jun 2030, extended 4 mo—9%
Yog AnandDomilis Estate LLPDue Dec 2031——
Dattaprasad NiwasDattatray ConstructionDue Apr 2028, extended 4 mo—34%
Dhruvi ApartmentAbhay Mangesh BhambureDue Apr 2031, extended 4 mo——
Mangal Parv Nagari Phase-1Asif Abdul NaikDue Apr 2029, extended 4 mo——
Parulekar PlazaVision ConstructionDue Sep 2027——
Dreamz Goa Phase IILevel Up ConstructionsDue Apr 2029, extended 4 mo—9%
Prime VistaUmesh Sudhakar SukhiDue Dec 2027——
Sea PearlHiraya Constructions LLPDue Apr 2029——
Garden ViewS S ConstructionDue Apr 2028, extended 4 mo——
Sindhudurg market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Ajinkya Construction8 projects
  2. Sukhmani Constructions6 projects
  3. Ajinkkya Construction5 projects
  4. Nirmitee Builders & Developers5 projects
  5. Ranco Realty Pvt Ltd5 projects
  6. Benjamin Manwel Dsouza4 projects
  7. Chandrashekhar Suryakant Morvekar4 projects
  8. Consortexe Properties Pvt Ltd4 projects
  9. Manoj Vasant Mahadik4 projects
  10. Abhay Sharad Walawalkar3 projects

Sindhudurg, in questions

How many projects in Sindhudurg run late?

8 in 10 MahaRERA registrations (401 of 534): their completion date was extended or has passed, data through 20 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Sindhudurg by Deedo. Medians on fewer than 3 deeds are not shown.

Data through20 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology