2,214 MahaRERA projects in Pune are past their promised completion date, and MahaRERA shows no completion for them.

Most overdue first

Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 29 of 45.

ProjectLocalityPromisedRevisedDelivery
The Grand MajestiqueVenkateshwara Construction CompanyAmbegaon BkDec 2024Dec 20241 yr 11 mo late
Triveni Trikaya Phase-1Sai Balaji GroupTulapurDec 2024Sep 20251 yr 11 mo late
Vastu RajyogVastu Developers And BuildersTalegaon Dabhade (R)Dec 2024Dec 20241 yr 11 mo late
Vastu Savali Phase IIVastu DevelopersTalegaon Dabhade (R)Dec 2024Dec 20241 yr 11 mo late
Vishwa Laxmi ResidencySantosh Ramchandra JagtapSasvad (M Cl)Dec 2024Dec 20241 yr 11 mo late
VaastuvivaABCDB U Bhandari VaastuWakadDec 2024Dec 20241 yr 11 mo late
Vascon GoodlifeVascon Engineers LtdKataviDec 2024Dec 20241 yr 11 mo late
Ventila ParkKrushnarang BuildersPimpri Chinchawad (M Corp.)Dec 2024Nov 20251 yr 11 mo late
Vighnaharta HeightsAmarnath HomesKalasDec 2024Dec 20241 yr 11 mo late
Yash ApartmentSuryoday DevelopersTalegaon Dabhade (M Cl)Dec 2024Dec 20241 yr 11 mo late
19 GRAND WEST - C WING and D WINGShivam Development Ventures LLPThergaonDec 2024Dec 20241 yr 11 mo late
27 AvenueEight Elements Realty LLPAkurdiDec 2024Dec 20241 yr 11 mo late
28 PearlsBhakti BuildersPimpri Chinchawad (M Corp.)Dec 2024Dec 20241 yr 11 mo late
29 Gold Coast Phase 6Mantra 29 Gold Cost Developers LLPDhanoriDec 2024Dec 20251 yr 11 mo late
41 Evoke Bldg CKrisala AssociatesRavetDec 2024Dec 20251 yr 11 mo late
41cosmoKrisala Enterprises LLPTathwadeDec 2024Jun 20251 yr 11 mo late
51 Balewadi Residences - Phase 2Mega Spaces LLPBalewadiDec 2024Dec 20241 yr 11 mo late
Aaradhya ParkAkshay Balasaheb KalokheWadagaon (Ct)Dec 2024Dec 20241 yr 11 mo late
Aaradhyaa LakehilRajaram Bhimrao HajareGorhe Bk.Dec 2024Dec 20241 yr 11 mo late
Akashdeep Co-Operative Housing SocietySushil Chandrakant BahiratPune (M Corp.)Dec 2024Dec 20241 yr 11 mo late
Akshay HeritageAkshay BuildersWadmukhwadiDec 2024Dec 20241 yr 11 mo late
Anjaneri InfinityTejaram Magaji Choudhary And Tarachand Tejaram ChoudharyPune (M Corp.)Dec 2024Dec 20241 yr 11 mo late
Apex Business Court Phase IINbp Realty LLPPune (M Corp.)Dec 2024Dec 20241 yr 11 mo late
Avasa GrovelandNaiknavare Housing Developments Pvt LtdMahalungeDec 2024Dec 20241 yr 11 mo late
AvasagrasslandNaiknavare Housing Developments Pvt. Ltd.MahalungeDec 2024Dec 20241 yr 11 mo late
Avonvistaproject4NaiknavareprofileconstructionspvtltdMahalungeDec 2024Dec 20251 yr 11 mo late
Blue Bells ParkBenjamin Michael ManuelPune (M Corp.)Dec 2024Dec 20241 yr 11 mo late
Blue Oak ExoticaShri Sai AssociatesKondhwa KhurdDec 2024Dec 20251 yr 11 mo late
Castle RoyalStar DevelopersPune (M Corp.)Dec 2024Jun 20251 yr 11 mo late
Chowhan Residency Phase IIThe Lifestile RealtyUndriDec 2024Dec 20251 yr 11 mo late
City One PanacheShree Sai KeystoneRavetDec 2024Dec 20241 yr 11 mo late
Civcon ResidencyArchway PropertiesYerawadaDec 2024Aug 20251 yr 11 mo late
CrystalSaijyoti DevelopersWadagaon (Ct)Dec 2024Dec 20241 yr 11 mo late
Chandrakant SmrutiTejas Chandrakant KaduskarPimple NilakhDec 2024Dec 20241 yr 11 mo late
Composite Housing Scheme on Plot D1 at Sant Tukaram Nagar Pimpri PunePune Housing and Area Development Board PunePimpri Chinchawad (M Corp.)Dec 2024Dec 20251 yr 11 mo late
Composite Housing Scheme on Plot E2 at Sant Tukaram Nagar Pimpri PunePune Housing and Area Development Board PunePimpri Chinchawad (M Corp.)Dec 2024Dec 20251 yr 11 mo late
Diamond 1Usman Hasan ShaikhMamurdiDec 2024Dec 20251 yr 11 mo late
Divine FlorinaDivine PropertiesMoshiDec 2024Dec 20251 yr 11 mo late
Dnyaneshwar ApartmentDnyaneshwar Sonba DharpaleKatrajDec 2024Dec 20241 yr 11 mo late
Dream ParadiseShivswayambhu AssociatesJalochiDec 2024Dec 20241 yr 11 mo late
DwarkaPravin Keshav BadhekarKothrudDec 2024Dec 20251 yr 11 mo late
ElysiaTriaa Eliseo Housing LLPMundhawaDec 2024Dec 20251 yr 11 mo late
Ganesh Prime VeraR D DevelopersAmbegaon BkDec 2024Jul 20251 yr 11 mo late
Ganesh Prime Vera Building AR D DevelopersAmbegaon BkDec 2024Jul 20251 yr 11 mo late
Ganga Legend B2Goel Ganga India Pvt LtdBavadhan BkDec 2024Apr 20251 yr 11 mo late
Gulmohar Villas - ANatraj Shamrao SatavWagholiDec 2024Dec 20241 yr 11 mo late
Gulmohar Villas - CNalini Chowdary GogineniWagholiDec 2024Dec 20241 yr 11 mo late
Gurukrupa VrundavanGurukrupa DevelopersKiwaleDec 2024Sep 20251 yr 11 mo late
Green ParkClassic DevelopersPimpri Chinchawad (M Corp.)Dec 2024May 20251 yr 11 mo late
Ira EnclaveP G DevelopersHadapsarDec 2024Dec 20241 yr 11 mo late

Delayed projects by district

SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology