Kalas, Pune
3 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects6
Registrations6
Completion still due24 past their date
Median extension8 months33% of registrations extended
Regulatory cases0none on MahaRERA's lists
10 in 10 registrations run late here
6 MahaRERA registrations in Kalas
2 extended, not yet due4 past even the latest date
Extended registrations moved their completion date by a median of 8 months.
Projects in Kalas
6 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Ajmera UptownAjmera Bora Associates | Due May 2031, extended 4 mo | — | — |
| Vighnaharta HeightsAmarnath Homes | 1 yr 10 mo late | — | 0% |
| Tirupati PrakritiTirupati Realtors | 1 yr 4 mo late | — | 25% |
| GreenYards-Phase 1Chaitanya Estate | Due Dec 2028, extended 1 yr | — | — |
| Kimaya SpacesSb Developers And Kimaya Associates | 2 yrs 10 mo late | — | 46% |
| CrestValsamma Mamachan | 7 yrs late | — | 50% |
Nearby: other localities in Haveli
Most active promoters
- Ajmera Bora Associates1 project
- Amarnath Homes1 project
- Chaitanya Estate1 project
- Sb Developers And Kimaya Associates1 project
- Tirupati Realtors1 project
- Valsamma Mamachan1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology