RERA projects in Pimple Nilakh
43 projects under 44 MahaRERA registrations, registered 2019–2026. 11% have a completion date extended beyond the one promised.
43RERA projects
44Registrationssome projects hold several
22Completion still due22 past their completion date
12 monthsMedian extension beyond promised date11% of registrations extended
0Regulatory casesnone on MahaRERA's lists
5Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2019 | 1 |
| 2020 | 1 |
| 2021 | 5 |
| 2022 | 8 |
| 2023 | 14 |
| 2024 | 7 |
| 2025 | 6 |
| 2026 | 2 |
Projects in Pimple Nilakh
43 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Swayambhu PrathamSwayambhu Buildtech LLP | PR1260002502513 | 26 Feb 2026 | 31 Dec 2028 | — | Not yet due | 0 |
| Silvan CanopySoham Associates | PR1260002502118 | 20 Jan 2026 | 31 Dec 2028 | — | Not yet due | 0 |
| Mangal JeevanMangal Developers | PR1260002501914 | 29 Dec 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| AvantaPunamiya Properties LLP | PC1260002500973 | 26 Sep 2025 | 31 Dec 2026 | — | Not yet due | 0 |
| ElaraRegenesis Project Management LLP | P52100080060 | 22 Apr 2025 | 30 Jun 2029 | — | Not yet due | 0 |
| Midtown EleganceNeovis Landmarks LLP | P52100079661 | 20 Mar 2025 | 31 Dec 2026 | — | Not yet due | 0 |
| 24K Manor - Tower C and ShopsKolte-Patil Developers Limited | P52100079296 | 25 Feb 2025 | 30 Jun 2029 | — | Not yet due | 0 |
| CullinanM/s Garve Corporation | P52100078994 | 28 Jan 2025 | 31 Dec 2029 | — | Not yet due | 0 |
| Sai NeelVishal Anil Khairnar | PR1260002400072 | 8 Oct 2024 | 22 Sep 2026 | — | Promised date passed | 0 |
| Sanjog ResidencyDVM Constructions | P52100077495 | 20 Aug 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| 7 CosmosCosmos Urban Realty LLP | P52100055958 | 2 May 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| The AristaCristallo Infra LLP | P52100055954 | 2 May 2024 | 31 Aug 2027 | — | Not yet due | 0 |
| Sahil Heights A1Vaishnavi Promoters And Developers | P52100054948 | 21 Feb 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| MGP SiddhikshaMGP Developers | P52100054337 | 15 Jan 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| VirtuThe Excellaa | P52100054268 | 10 Jan 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Urban EdgeGruham Constructions | P52100052829 | 5 Oct 2023 | 2 Dec 2025 | — | Promised date passed | 0 |
| SwapnashilpTirupati Developers | P52100052543 | 8 Sep 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Rvk Aria Wing A BRvk Realty | P52100052177 | 27 Jul 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| 24K ManorKolte-Patil Developers Limited | P52100052151, P52100054048 | 24 Jul 2023 | 30 Jun 2028 | — | Not yet due | 0 |
| Audumber ResidencyShama Construction Through Properiter Vikram Manohar Kamthe | P52100051532 | 23 Jun 2023 | 31 Mar 2027 | — | Not yet due | 0 |
| Soham ShreeSoham Developers | P52100050479 | 17 Apr 2023 | 31 Dec 2024 | 31 Dec 2025 | Extended 12 mo | 0 |
| Green Alley Phase - IAjinkya Sanjay Tapkir | P52100050420 | 12 Apr 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Prabha HeightsAvadhoot Construction | P52100050353 | 5 Apr 2023 | 31 Dec 2025 | — | Promised date passed | 0 |
| Silver OrchidSilver Orchid | P52100050298 | 1 Apr 2023 | 31 Mar 2026 | — | Promised date passed | 0 |
| Samarth VillaD.a.borade & Sons | P52100050168 | 21 Mar 2023 | 31 Mar 2024 | — | Promised date passed | 0 |
| Green Alley Phase - IIAryan Developers | P52100049768 | 24 Feb 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Siddhi ApartmentMak Developers | P52100049485 | 15 Feb 2023 | 31 Jul 2024 | — | Promised date passed | 0 |
| ElinaTulip Venture | P52100048472 | 3 Jan 2023 | 31 Dec 2024 | — | Promised date passed | 0 |
| Orchid PlazaM K Buildcon | P52100048003 | 7 Dec 2022 | 30 Jun 2025 | — | Promised date passed | 0 |
| Green ParadiseVilas Eknath Nandgude | P52100047253 | 13 Oct 2022 | 31 Mar 2025 | 31 Dec 2028 | Extended 45 mo | 0 |
| MGP SuanandMGP Developers | P52100047122 | 10 Oct 2022 | 31 Dec 2024 | — | Promised date passed | 0 |
| EterniaA S Group | P52100045555 | 24 May 2022 | 25 Feb 2023 | 30 Sep 2024 | Extended 19 mo | 0 |
| 66 Avenue A B C BuildingR R Lunkad Landmarks LLP | P52100035034 | 29 Apr 2022 | 30 Jun 2025 | — | Promised date passed | 0 |
| Chandrakant SmrutiTejas Chandrakant Kaduskar | P52100032804 | 29 Jan 2022 | 31 Dec 2024 | — | Promised date passed | 0 |
| RaveeraInfinity Landmarks | P52100032611 | 14 Jan 2022 | 31 Dec 2024 | — | Promised date passed | 0 |
| Suyog SadanSuyog Builders | P52100032390 | 4 Jan 2022 | 30 Dec 2022 | — | Promised date passed | 0 |
| Aurum PetalsKalbhor Buildcon (I) LLP | P52100032003 | 3 Dec 2021 | 30 Jun 2024 | — | Promised date passed | 0 |
| Marigold CalendulaAudumbar Homes LLP | P52100031396 | 23 Oct 2021 | 30 Sep 2026 | — | Promised date passed | 0 |
| DhruvaaJK Realty | P52100031208 | 11 Oct 2021 | 31 Dec 2023 | 30 Jun 2024 | Extended 6 mo | 0 |
| Subhadra HeightsRushikesh Ramchandra Sathe | P52100030818 | 14 Sep 2021 | 31 Dec 2022 | 30 Dec 2023 | Extended 12 mo | 0 |
| OrchidsSai Balaji Constructions | P52100030725 | 8 Sep 2021 | 30 Jun 2026 | — | Promised date passed | 0 |
| TridentDeu Associates | P52100026732 | 21 Oct 2020 | 8 May 2024 | — | Promised date passed | 0 |
| 66 AvenueR R Lunkad Landmarks LLP | P52100021457 | 3 Jul 2019 | 28 Aug 2025 | — | Promised date passed | 0 |
Other localities in Haveli
- Pimpri Chinchawad (M Corp.)1,056 projects
- Baner370 projects
- Kothrud331 projects
- Wagholi266 projects
- Hadapsar201 projects
- Charholi169 projects
- Ravet169 projects
- Ambegaon Bk151 projects
- Lohgaon141 projects
- Kondhwa Bk137 projects
- Moshi136 projects
- Mundhawa132 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- Kolte-Patil Developers Limited2 projects
- MGP Developers2 projects
- R R Lunkad Landmarks LLP2 projects
- Ajinkya Sanjay Tapkir1 project
- Aryan Developers1 project
- A S Group1 project
- Audumbar Homes LLP1 project
- Avadhoot Construction1 project
- Cosmos Urban Realty LLP1 project
- Cristallo Infra LLP1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology