Triveni Trikaya Phase-1

Certificate Signed

Tulapur, Pune 412216 |Promoter: Sai Balaji Group

Residential / Group HousingRERAP52100016958
25 Jun 2018Registered with MahaRERA
30 Dec 2024Promised completion
30 Sep 2025Revised completionPushed back 9 months
3Buildings
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
3
Address
Gat No. 513P, 515P, 516P, 517P, 525P, Tulapur, TulapurPIN 412216
Designated bank account
171
Developed in phases
Yes

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.66863, 73.99101
Triveni Trikaya Phase-1 is at latitude 18.66863, longitude 73.99101.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 9 months

The latest completion date on record passed 1 year and 1 month ago.

Registered
25 Jun 2018
Promised
30 Dec 2024
Revised
30 Sep 2025

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210001695825 Jun 201830 Dec 202430 Sep 2025Sai Balaji GroupProject page

3 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Wing A210—
Wing B39—
Wing B49—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Documents

2 documents held by Deedo, 195 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardPANSAIBALAJIGROUP.pdf · uploaded 28 Nov 2018Source

Legal

  • Declaration Form BForm B.pdf · uploaded 29 May 2018Source
  • Legal Title reportTSR 38R.pdf · uploaded 1 Jun 2018Source
  • Legal Title reportTSR 25R.pdf · uploaded 1 Jun 2018Source
  • Legal Title reportTSR 18R.pdf · uploaded 1 Jun 2018Source
  • Legal Title reportTSR 365R.pdf · uploaded 1 Jun 2018Source
Show all 197 documentsShow fewer documents

Legal

  • Legal Title reportTSR 51R.pdf · uploaded 1 Jun 2018Source
  • OtherEnvironmental Clearance.pdf · uploaded 24 May 2019Source
  • OtherMPCB Consent Letter.pdf · uploaded 24 May 2019Source
  • Declaration Form BForm B Triveni Trikaya.pdf · uploaded 25 Feb 2025Source

Migrated

  • 1 Details of encumbrancesEncumbrance Certificate.pdf · uploaded 29 May 2018Source
  • 1 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 29 May 2018Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 29 May 2018Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 29 May 2018Source
  • 1 Copy of the legal title reportTSR 38R.pdf · uploaded 1 Jun 2018Source
  • 2 Copy of the legal title reportTSR 25R.pdf · uploaded 1 Jun 2018Source
  • 3 Copy of the legal title reportTSR 18R.pdf · uploaded 1 Jun 2018Source
  • 4 Copy of the legal title reportTSR 365R.pdf · uploaded 1 Jun 2018Source
  • 5 Copy of the legal title reportTSR 51R.pdf · uploaded 1 Jun 2018Source
  • 1 Building Plan Approval (IOD)A2 Plan.pdf · uploaded 1 Jun 2018Source
  • 2 Building Plan Approval (IOD)B3 Plan.pdf · uploaded 1 Jun 2018Source
  • 3 Building Plan Approval (IOD)B4 Plan.pdf · uploaded 1 Jun 2018Source
  • 1 Certificates of CA (Form 3)CA Certificate.pdf · uploaded 1 Jun 2018Source
  • 1 Proforma of Allotment letterSample Agreement.pdf · uploaded 1 Jun 2018Source
  • 1 PAN CardPANSAIBALAJIGROUP.pdf · uploaded 28 Nov 2018Source
  • 1 Certificates of CA (Form 5)ITR Form 2017-18 Sai Balaji Group.pdf · uploaded 28 Nov 2018Source
  • 1 OtherEnvironmental Clearance.pdf · uploaded 24 May 2019Source
  • 2 OtherMPCB Consent Letter.pdf · uploaded 24 May 2019Source
  • 2 Certificates of CA (Form 5)Form 5 (2018-19).pdf · uploaded 7 Oct 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5 (2018-19).pdf · uploaded 12 Feb 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 (2019-20).pdf · uploaded 12 Feb 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate 22-07-21.pdf · uploaded 12 Aug 2021Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate 22-07-21.pdf · uploaded 12 Aug 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 2A - June 2019.pdf · uploaded 12 Aug 2021Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 2A - September 2019.pdf · uploaded 12 Aug 2021Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 2A - December 2019.pdf · uploaded 12 Aug 2021Source
  • 4 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 2A - March 2020.pdf · uploaded 12 Aug 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A - December 2020.pdf · uploaded 12 Aug 2021Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A - March 2021.pdf · uploaded 12 Aug 2021Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of Inventory 01-08-2021.pdf · uploaded 12 Aug 2021Source
  • 2 Certificates of CA (Form 3)CA Certificate 22-07-21.pdf · uploaded 12 Aug 2021Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate 22-11-21.pdf · uploaded 25 Feb 2022Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate 25-06-22.pdf · uploaded 15 Jul 2022Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate 25-06-22.pdf · uploaded 15 Jul 2022Source
  • 3 Certificates of CA (Form 3)CA Certificate 25-06-22.pdf · uploaded 15 Jul 2022Source
  • 1 Declaration in FORM BForm B Triveni Trikaya.pdf · uploaded 25 Feb 2025Source
  • 1 Declaration about Commencement CertificateFORMAT D Commemncement Declaration.pdf · uploaded 25 Feb 2025Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)FORMAT A (3).pdf · uploaded 25 Feb 2025Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsANNEXURE A ANUP.pdf · uploaded 25 Feb 2025Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsANNEXUYRE A RAKESH.pdf · uploaded 25 Feb 2025Source
  • 1 Disclosure for secured/unsecured finance availed for the projectDisclouser of secuered loan.pdf · uploaded 25 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Triveni Trikaya 31-12-2018 (form 2) 07-Mar-2025 19-15-50.pdf · uploaded 10 Mar 2025Source
  • 20 Architect’s Certificate of Percentage of Completion of Work (Form 1)Triveni Trikaya 31-12-2024 (form 1) 07-Mar-2025 19-08-32.pdf · uploaded 10 Mar 2025Source
  • 19 Architect’s Certificate of Percentage of Completion of Work (Form 1)triveni Trikaya 30-09-2024 (form1) 07-Mar-2025 19-05-42.pdf · uploaded 10 Mar 2025Source
  • 18 Architect’s Certificate of Percentage of Completion of Work (Form 1)Triveni Trikaya 30-06-2024 (form 1) 07-Mar-2025 19-02-31.pdf · uploaded 10 Mar 2025Source
  • 17 Architect’s Certificate of Percentage of Completion of Work (Form 1)triveni Trikaya 31-03-2024 (Form1) 07-Mar-2025 18-58-33.pdf · uploaded 10 Mar 2025Source
  • 16 Architect’s Certificate of Percentage of Completion of Work (Form 1)Triveni Trikaya 31-12-2023 (Form1) 07-Mar-2025 18-54-40.pdf · uploaded 10 Mar 2025Source
  • 15 Architect’s Certificate of Percentage of Completion of Work (Form 1)Triveni Trikaya 30-09-23 07-Mar-2025 18-51-08.pdf · uploaded 10 Mar 2025Source
  • 14 Architect’s Certificate of Percentage of Completion of Work (Form 1)Triveni Trikaya 30-06-2023 (Form1) 07-Mar-2025 18-48-08.pdf · uploaded 10 Mar 2025Source
  • 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)Triveni Trikaya 31-03-2023 (Form1) 07-Mar-2025 18-44-07.pdf · uploaded 10 Mar 2025Source
  • 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)Triveni Trikaya 31-12-2022 (form 1) 07-Mar-2025 18-40-33.pdf · uploaded 10 Mar 2025Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Triveni Trikaya 30-06-2022 (Form 1) 07-Mar-2025 18-33-29.pdf · uploaded 10 Mar 2025Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Triveni Trikaya 31-03-2022 (Form 1) 07-Mar-2025 18-30-15.pdf · uploaded 10 Mar 2025Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Triveni Trikaya 31-12-2021 (Form 1) 07-Mar-2025 18-24-53.pdf · uploaded 10 Mar 2025Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Triveni Trikaya 30-06-2021 (Form 1) 07-Mar-2025 18-16-06.pdf · uploaded 10 Mar 2025Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Triveni Trikaya 31-03-21(form 1) 07-Mar-2025 18-10-30.pdf · uploaded 10 Mar 2025Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)triveni trikaya 31-03-2020 (form 1) 07-Mar-2025 18-02-56.pdf · uploaded 10 Mar 2025Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)triveni trikaya 31-03-2019 (form 1) 07-Mar-2025 17-55-24.pdf · uploaded 10 Mar 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)triveni trikaya 31-12-2019 (Form 1) 07-Mar-2025 17-59-09.pdf · uploaded 10 Mar 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)triveni trikaya 31-12-2018 (form 1) 07-Mar-2025 17-50-00.pdf · uploaded 10 Mar 2025Source
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)Triveni Trikaya 30-09-2022 (Form1) 07-Mar-2025 18-37-19.pdf · uploaded 10 Mar 2025Source
  • 13 Certificates of CA (Form 3)12 Triveni Trikaya 30-09-2022 (form 3).pdf · uploaded 10 Mar 2025Source
  • 14 Certificates of CA (Form 3)13 Triveni Trikaya 31-12-2022 (form 3).pdf · uploaded 10 Mar 2025Source
  • 15 Certificates of CA (Form 3)14 Triveni Trikaya 31-03-2023 (form 3).pdf · uploaded 10 Mar 2025Source
  • 16 Certificates of CA (Form 3)15 Triveni Trikaya 30-06-2023 (form 3).pdf · uploaded 10 Mar 2025Source
  • 17 Certificates of CA (Form 3)15 Triveni Trikaya 30-09-2023 (form 3).pdf · uploaded 10 Mar 2025Source
  • 18 Certificates of CA (Form 3)16 Triveni Trikaya 31-12-2023 (form 3).pdf · uploaded 10 Mar 2025Source
  • 19 Certificates of CA (Form 3)17 Triveni Trikaya 31-03-2024 (form 3).pdf · uploaded 10 Mar 2025Source
  • 20 Certificates of CA (Form 3)Triveni Trikaya 30-06-2024 (form 3).pdf · uploaded 10 Mar 2025Source
  • 21 Certificates of CA (Form 3)Triveni Trikaya 30-09-2024 (form 3).pdf · uploaded 10 Mar 2025Source
  • 22 Certificates of CA (Form 3)Triveni Trikaya 31-12-2024 (form 3).pdf · uploaded 10 Mar 2025Source
  • 3 Certificates of CA (Form 3)triveni Trikaya 31-03-2019 (form 3) 10-Mar-2025 11-18-21_11zon.pdf · uploaded 10 Mar 2025Source
  • 12 Certificates of CA (Form 3)11 Triveni Trikaya 30-06-2022 (form 3).pdf · uploaded 10 Mar 2025Source
  • 11 Certificates of CA (Form 3)10 triveni Trikaya 31-03-2022 (form 3).pdf · uploaded 10 Mar 2025Source
  • 10 Certificates of CA (Form 3)9 Triveni Trikaya 31-12-2021 (form 3).pdf · uploaded 10 Mar 2025Source
  • 9 Certificates of CA (Form 3)8 Triveni Trikaya 30-09-2021 (form 3).pdf · uploaded 10 Mar 2025Source
  • 8 Certificates of CA (Form 3)7 Triveni Trikaya 30-06-2021 (form 3).pdf · uploaded 10 Mar 2025Source
  • 7 Certificates of CA (Form 3)6 Triveni Trikaya 31-03-2021 (form 3).pdf · uploaded 10 Mar 2025Source
  • 6 Certificates of CA (Form 3)5 Triveni Trikaya 31-12-2020 (form 3).pdf · uploaded 10 Mar 2025Source
  • 5 Certificates of CA (Form 3)1 triveni Trikaya 31-12-2018 form 3.pdf · uploaded 10 Mar 2025Source
  • 4 Certificates of CA (Form 3)Triveni Trikaya 31-03-2020 (form 3) 10-Mar-2025 11-38-27_11zon.pdf · uploaded 10 Mar 2025Source
  • 2 Certificates of CA (Form 3)triveni Trikaya 31-03-2019 (form 3) 10-Mar-2025 11-18-21_11zon.pdf · uploaded 10 Mar 2025Source
  • 1 Certificates of CA (Form 3)triveni Trikaya 31-12-2019(form 3) 10-Mar-2025 11-29-05_11zon.pdf · uploaded 10 Mar 2025Source
  • 5 Certificates of CA (Form 5)Form5 01-04-2023 Trivene Trikaya 23-24.pdf · uploaded 10 Mar 2025Source
  • 4 Certificates of CA (Form 5)Form5 01-04-2022 Trivene Trikaya (22-23).pdf · uploaded 10 Mar 2025Source
  • 2 Certificates of CA (Form 5)Form5 01-04-2020 Trivene Trikaya (20-21).pdf · uploaded 10 Mar 2025Source
  • 3 Certificates of CA (Form 5)Form5 01-04-2021 Trivene Trikaya (21-22).pdf · uploaded 10 Mar 2025Source
  • 1 Certificates of CA (Form 5)Form5 01-04-2019 Trivene Trikaya 19-20.pdf · uploaded 10 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Triveni Trikaya 31-12-2018 (form 2) 07-Mar-2025 19-15-50.pdf · uploaded 10 Mar 2025Source
  • 19 Engineer’s Certificate on Cost Incurred on Project (Form 2)triveni Trikaya 31-12-2024 (form 2) 07-Mar-2025 20-14-25.pdf · uploaded 10 Mar 2025Source
  • 18 Engineer’s Certificate on Cost Incurred on Project (Form 2)Triveni Trikaya 30-09-2024 (form 2) 07-Mar-2025 20-12-05.pdf · uploaded 10 Mar 2025Source
  • 17 Engineer’s Certificate on Cost Incurred on Project (Form 2)triveni Trikaya 30-06-2024 (form 2) 07-Mar-2025 20-09-48.pdf · uploaded 10 Mar 2025Source
  • 16 Engineer’s Certificate on Cost Incurred on Project (Form 2)triveni Trikaya 31-03-2024 (form 2) 07-Mar-2025 20-06-44.pdf · uploaded 10 Mar 2025Source
  • 15 Engineer’s Certificate on Cost Incurred on Project (Form 2)triveni Trikaya 31-12-2023 (Form 2) 07-Mar-2025 20-04-16.pdf · uploaded 10 Mar 2025Source
  • 14 Engineer’s Certificate on Cost Incurred on Project (Form 2)triveni Trikaya 30-09-2023 (form 2) 07-Mar-2025 20-01-32.pdf · uploaded 10 Mar 2025Source
  • 13 Engineer’s Certificate on Cost Incurred on Project (Form 2)triveni Trikaya 30-06-2023 (form 2) 07-Mar-2025 19-58-40.pdf · uploaded 10 Mar 2025Source
  • 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)triveni Trikaya 31-03-2023 (form 2) 07-Mar-2025 19-55-51.pdf · uploaded 10 Mar 2025Source
  • 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)triveni Trikaya 31-12-2022 (Form 2) 07-Mar-2025 19-53-03.pdf · uploaded 10 Mar 2025Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)triveni Trikaya 30-09-2022 (Form 2) 07-Mar-2025 19-50-42.pdf · uploaded 10 Mar 2025Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Triveni Trikaya 30-06-2022 (form 2) 07-Mar-2025 19-48-05.pdf · uploaded 10 Mar 2025Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)triveni Trikaya 31-03-2022 (Form 2) 07-Mar-2025 19-45-14.pdf · uploaded 10 Mar 2025Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Triveni Trikaya 31-12-2021(form 2) 07-Mar-2025 19-42-42.pdf · uploaded 10 Mar 2025Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)triveni Trikaya 30-09-2021 (form 2) 07-Mar-2025 19-39-20.pdf · uploaded 10 Mar 2025Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Triveni Trikaya 30-06-2021 (form2) 07-Mar-2025 19-34-41.pdf · uploaded 10 Mar 2025Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)triveni Trikaya 31-03-2021 (form2) 07-Mar-2025 19-31-59.pdf · uploaded 10 Mar 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)triveni Trikaya 31-03-2020 (form 2) 07-Mar-2025 19-26-06.pdf · uploaded 10 Mar 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Triveni Trikaya 31-03-2019 (Form 2) 07-Mar-2025 19-20-08.pdf · uploaded 10 Mar 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 2A 18-19 Trivene Trikaya.pdf · uploaded 10 Mar 2025Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A 20-21 Trivene Trikaya.pdf · uploaded 10 Mar 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A 19-20 Trivene Trikaya.pdf · uploaded 10 Mar 2025Source
  • 1 Disclosure of sold/ booked inventory1 Triveni Trikaya Sold unsold _Date 31-12-2018.pdf · uploaded 10 Mar 2025Source
  • 18 Disclosure of sold/ booked inventoryTriveni Trikaya Sold - Unsold _Date 31-12-2024.pdf · uploaded 10 Mar 2025Source
  • 17 Disclosure of sold/ booked inventory17 Triveni Trikaya Sold-unsold _Date 30-09-2024.pdf · uploaded 10 Mar 2025Source
  • 16 Disclosure of sold/ booked inventory17 Triveni Trikaya Sold unsold _Date 30-06-2024.pdf · uploaded 10 Mar 2025Source
  • 15 Disclosure of sold/ booked inventory16Triveni Trikaya Sold unsold _Date 31-03-2024.pdf · uploaded 10 Mar 2025Source
  • 14 Disclosure of sold/ booked inventory15Triveni Trikaya Sold unsold _Date 31-12-2023.pdf · uploaded 10 Mar 2025Source
  • 13 Disclosure of sold/ booked inventory14 Triveni Trikaya Sold unsold _Date 30-09-2023.pdf · uploaded 10 Mar 2025Source
  • 12 Disclosure of sold/ booked inventory13 Triveni Trikaya Sold unsold _Date 30-06-2023.pdf · uploaded 10 Mar 2025Source
  • 11 Disclosure of sold/ booked inventory12 Triveni Trikaya Sold unsold _Date 31-03-2023.pdf · uploaded 10 Mar 2025Source
  • 10 Disclosure of sold/ booked inventory11Triveni Trikaya Sold unsold _Date 31-12-2022.pdf · uploaded 10 Mar 2025Source
  • 9 Disclosure of sold/ booked inventory10 Triveni Trikaya Sold unsold _Date 30-09-2022.pdf · uploaded 10 Mar 2025Source
  • 8 Disclosure of sold/ booked inventory9 Triveni Trikaya Sold unsold _Date 30-06-2022.pdf · uploaded 10 Mar 2025Source
  • 7 Disclosure of sold/ booked inventory8 Triveni Trikaya Sold unsold _Date 31-03-2022.pdf · uploaded 10 Mar 2025Source
  • 6 Disclosure of sold/ booked inventory6 Triveni Trikaya Sold unsold _Date 31-03-2021.pdf · uploaded 10 Mar 2025Source
  • 5 Disclosure of sold/ booked inventory5 Triveni Trikaya Sold unsold _Date 31-12-2020.pdf · uploaded 10 Mar 2025Source
  • 4 Disclosure of sold/ booked inventory4 Triveni Trikaya Sold unsold _Date 31-03-2020.pdf · uploaded 10 Mar 2025Source
  • 3 Disclosure of sold/ booked inventory3 Triveni Trikaya Sold unsold _Date 31-12-2019.pdf · uploaded 10 Mar 2025Source
  • 2 Disclosure of sold/ booked inventory2 Triveni Trikaya Sold unsold _Date 31-03-2019.pdf · uploaded 10 Mar 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A 21-22 Trivene Trikaya.pdf · uploaded 10 Mar 2025Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A Ram Agarwal.pdf · uploaded 10 Mar 2025Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A Sham Agarwal.pdf · uploaded 10 Mar 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A 22-23 Trivene Trikaya.pdf · uploaded 10 Mar 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A 23-24 Trivene Trikaya.pdf · uploaded 10 Mar 2025Source
  • 1 a Details of encumbrances concerned to Financefincial encumberence certificate.pdf · uploaded 11 Mar 2025Source
  • 6 Certificates of CA (Form 5)form 5 (4).pdf · uploaded 11 Mar 2025Source
  • 1 b Details of encumbrances concerned to Legalfincial encumberence certificate.pdf · uploaded 11 Mar 2025Source
  • 1 Other – TechnicalPert Chart Trivene Trikaya.pdf · uploaded 12 Mar 2025Source
  • 1 CERSAI detailsdeclration instead of CERSAI report.pdf · uploaded 18 Mar 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentVerification of CC Triveni Trikaya.pdf · uploaded 21 Mar 2025Source

Technical

  • DocumentLayout.pdf · uploaded 29 May 2018Source
  • DocumentB4 Plan.pdf · uploaded 1 Jun 2018Source
  • DocumentA2 Plan.pdf · uploaded 1 Jun 2018Source
  • DocumentB3 Plan.pdf · uploaded 1 Jun 2018Source
  • Other – TechnicalPert Chart Trivene Trikaya.pdf · uploaded 12 Mar 2025Source

Technical (Architect)

  • DocumentArchitect Certificate 25-06-22.pdf · uploaded 15 Jul 2022Source
  • DocumentTriveni Trikaya 31-12-2018 (form 2) 07-Mar-2025 19-15-50.pdf · uploaded 10 Mar 2025Source
  • Documenttriveni trikaya 31-12-2018 (form 1) 07-Mar-2025 17-50-00.pdf · uploaded 10 Mar 2025Source
  • Documenttriveni trikaya 31-12-2019 (Form 1) 07-Mar-2025 17-59-09.pdf · uploaded 10 Mar 2025Source
  • Documenttriveni trikaya 31-03-2019 (form 1) 07-Mar-2025 17-55-24.pdf · uploaded 10 Mar 2025Source
  • Documenttriveni trikaya 31-03-2020 (form 1) 07-Mar-2025 18-02-56.pdf · uploaded 10 Mar 2025Source
  • DocumentTriveni Trikaya 31-03-21(form 1) 07-Mar-2025 18-10-30.pdf · uploaded 10 Mar 2025Source
  • DocumentTriveni Trikaya 30-06-2021 (Form 1) 07-Mar-2025 18-16-06.pdf · uploaded 10 Mar 2025Source
  • DocumentTriveni Trikaya 31-12-2021 (Form 1) 07-Mar-2025 18-24-53.pdf · uploaded 10 Mar 2025Source
  • DocumentTriveni Trikaya 31-03-2022 (Form 1) 07-Mar-2025 18-30-15.pdf · uploaded 10 Mar 2025Source
  • DocumentTriveni Trikaya 30-06-2022 (Form 1) 07-Mar-2025 18-33-29.pdf · uploaded 10 Mar 2025Source
  • DocumentTriveni Trikaya 30-09-2022 (Form1) 07-Mar-2025 18-37-19.pdf · uploaded 10 Mar 2025Source
  • DocumentTriveni Trikaya 31-12-2022 (form 1) 07-Mar-2025 18-40-33.pdf · uploaded 10 Mar 2025Source
  • DocumentTriveni Trikaya 31-03-2023 (Form1) 07-Mar-2025 18-44-07.pdf · uploaded 10 Mar 2025Source
  • DocumentTriveni Trikaya 30-06-2023 (Form1) 07-Mar-2025 18-48-08.pdf · uploaded 10 Mar 2025Source
  • DocumentTriveni Trikaya 30-09-23 07-Mar-2025 18-51-08.pdf · uploaded 10 Mar 2025Source
  • DocumentTriveni Trikaya 31-12-2023 (Form1) 07-Mar-2025 18-54-40.pdf · uploaded 10 Mar 2025Source
  • Documenttriveni Trikaya 31-03-2024 (Form1) 07-Mar-2025 18-58-33.pdf · uploaded 10 Mar 2025Source
  • DocumentTriveni Trikaya 30-06-2024 (form 1) 07-Mar-2025 19-02-31.pdf · uploaded 10 Mar 2025Source
  • Documenttriveni Trikaya 30-09-2024 (form1) 07-Mar-2025 19-05-42.pdf · uploaded 10 Mar 2025Source
  • DocumentTriveni Trikaya 31-12-2024 (form 1) 07-Mar-2025 19-08-32.pdf · uploaded 10 Mar 2025Source

Technical (Engineer)

  • DocumentEngineer Certificate 25-06-22.pdf · uploaded 15 Jul 2022Source
  • DocumentTriveni Trikaya 31-12-2018 (form 2) 07-Mar-2025 19-15-50.pdf · uploaded 10 Mar 2025Source
  • DocumentTriveni Trikaya 31-03-2019 (Form 2) 07-Mar-2025 19-20-08.pdf · uploaded 10 Mar 2025Source
  • Documenttriveni Trikaya 31-03-2020 (form 2) 07-Mar-2025 19-26-06.pdf · uploaded 10 Mar 2025Source
  • Documenttriveni Trikaya 31-03-2021 (form2) 07-Mar-2025 19-31-59.pdf · uploaded 10 Mar 2025Source
  • DocumentTriveni Trikaya 30-06-2021 (form2) 07-Mar-2025 19-34-41.pdf · uploaded 10 Mar 2025Source
  • Documenttriveni Trikaya 30-09-2021 (form 2) 07-Mar-2025 19-39-20.pdf · uploaded 10 Mar 2025Source
  • DocumentTriveni Trikaya 31-12-2021(form 2) 07-Mar-2025 19-42-42.pdf · uploaded 10 Mar 2025Source
  • Documenttriveni Trikaya 31-03-2022 (Form 2) 07-Mar-2025 19-45-14.pdf · uploaded 10 Mar 2025Source
  • DocumentTriveni Trikaya 30-06-2022 (form 2) 07-Mar-2025 19-48-05.pdf · uploaded 10 Mar 2025Source
  • Documenttriveni Trikaya 30-09-2022 (Form 2) 07-Mar-2025 19-50-42.pdf · uploaded 10 Mar 2025Source
  • Documenttriveni Trikaya 31-12-2022 (Form 2) 07-Mar-2025 19-53-03.pdf · uploaded 10 Mar 2025Source
  • Documenttriveni Trikaya 31-03-2023 (form 2) 07-Mar-2025 19-55-51.pdf · uploaded 10 Mar 2025Source
  • Documenttriveni Trikaya 30-06-2023 (form 2) 07-Mar-2025 19-58-40.pdf · uploaded 10 Mar 2025Source
  • Documenttriveni Trikaya 30-09-2023 (form 2) 07-Mar-2025 20-01-32.pdf · uploaded 10 Mar 2025Source
  • Documenttriveni Trikaya 31-12-2023 (Form 2) 07-Mar-2025 20-04-16.pdf · uploaded 10 Mar 2025Source
  • Documenttriveni Trikaya 31-03-2024 (form 2) 07-Mar-2025 20-06-44.pdf · uploaded 10 Mar 2025Source
  • Documenttriveni Trikaya 30-06-2024 (form 2) 07-Mar-2025 20-09-48.pdf · uploaded 10 Mar 2025Source
  • DocumentTriveni Trikaya 30-09-2024 (form 2) 07-Mar-2025 20-12-05.pdf · uploaded 10 Mar 2025Source
  • Documenttriveni Trikaya 31-12-2024 (form 2) 07-Mar-2025 20-14-25.pdf · uploaded 10 Mar 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Tulapur, Haveli taluka

Survey, CTS, gat or plot numbers

515P516P517P525PGat No. 513P

Boundaries

North
Amenity Space
South
Gat No 513P 515P 516P 525P
East
12 Mtr Wide Internal Road
West
Gat No 526

Source: registration certificates and MahaRERA's project page, as stated there.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology