Skip to content

RERA projects in Gorhe Bk.

8 projects under 8 MahaRERA registrations, registered 2017–2026. 75% have a completion date extended beyond the one promised.

Locality
8RERA projects
8Registrations
2Completion still due6 past their completion date
28 monthsMedian extension beyond promised date75% of registrations extended
1Regulatory caseson 1 project
8Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20174
20181
20190
20200
20211
20221
20230
20240
20250
20261

Projects in Gorhe Bk.

8 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
VrundavanSai Ganesh AssociatesPR126000250221029 Jan 202630 Jun 202730 Jun 2027Not yet due0
Mindspace Villas Phase IMs Lifestyle ResortsP5210004817115 Dec 202231 Mar 202431 Dec 2028Extended 57 mo0
Amar PrakritiEternity Buildcon LLPP5210003008929 Jul 202131 Mar 20245 Feb 2025Extended 11 mo0
Aaradhyaa LakehilRajaram Bhimrao HajareP5210001676512 Jun 201831 Dec 202431 Dec 2024Promised date passed1
Datta ViharSaidatta Associates Developers Promoters And BuildersP5210001131131 Aug 201731 Jan 201930 Mar 2022Extended 38 mo0
Mist AirG M Promoters LLPP5210001078431 Aug 201715 Dec 201814 Dec 2019Extended 12 mo0
Mist AquaGM Promoters LLPP5210000578514 Aug 201731 Aug 201830 Oct 2020Extended 26 mo0
Natures Blessings phase INagarkar DevelopersP5210000642914 Aug 201730 Sep 201930 Mar 2022Extended 30 mo0

Other localities in Haveli

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Eternity Buildcon LLP1 project
  2. G M Promoters LLP1 project
  3. GM Promoters LLP1 project
  4. Ms Lifestyle Resorts1 project
  5. Nagarkar Developers1 project
  6. Rajaram Bhimrao Hajare1 project
  7. Saidatta Associates Developers Promoters And Builders1 project
  8. Sai Ganesh Associates1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology